Instructions: Please complete all 3 multi-part problems for this week's assignment.

2-1 Basic Estimating Problem
Please look at the Attached Excel sheet for answer for first problem only.

2-2 Three-point Estimate Problem (a)
Data: a = the best case estimate = $0.24/lb. m= the most likely estimate = $0.30/lb. b= the worst case estimate = $0.62/lb.
Answer: We have to determine the E-value: E = (a + (4*m) + b) /6 E = (0.24 + (4 * 0.30) + 0.62)/ 6 E = $0.34/lb. (b)
Data: a = the best case estimate = 37 tons m= the most likely estimate = 40 tons. b= the worst case estimate = 49 tons
Answer: We have to determine the E-value: E = (a + (4*m) + b) /6 E = (37 + (4 * 40) + 47)/ 6 E = 40.66 tons or 41 tons if you want to round it up.

(c) Using the estimates from 1 & 2, what is the expected cost for structural steel over the life of the project? ( 41 tons * 2000lbs.) = 82,000 lbs.
Therefore, the estimates would be: $0.34/lb * 82,000 lbs = $27,880 (d) Using the "Complex" three-point method, what is the expected cost for structural steel over the life of the project? Expected cost: $0.34/lb * 82,000 lbs = $27,880
Most optimistic cost: $0.24/lb * 74,000 lbs = $17,760
Most pessimistic cost: $0.62/lb * 98,000 lbs = $60,760
The final estimated cost for the material is: (($17,760 + (4 * $27,880) + $60,760))/6 = $31,673.33
2-3 Contingency Allowance Problem

(a) 1.50 ($80 + $3 + $6) + 1.20($7 + $5.5 + $6.5)+ 1.05($15 + $12 +$3.70+$1.50+$18) =$209.01 209 / 1000 = $0.21
(b)
$0.21 @ 150% markup (2.5 * $0.21) = $0.525 An additional 100% reseller mark-up would bring retail price to (2 * $0.525) = $1.05 which is bellow the target retail price for the new sandwich of $1.49, there will be a profit of $0.44. (c) I don’t quite understand this question, but from the above calculation shows that the cost per sandwich, $1.05, is bellow the target retail price for the new sandwich of $1.49, there will be a profit of $0.44. Therefore, the project should be approved.

(d)
Need to firm up estimates for order of magnitude and budget items, and revise estimates before project can proceed.

Similar Documents

Premium Essay

Pm 592 Study Guide

...PM592 On-line – Study Guide for Final Examination The final is an open book/open notes examination. The final includes nine questions, and is worth a total of 300 points. The sample problems here represent the types of problems that may appear on the final. There are solutions to the problems at the end. There will also be discussion problems. I have provided a list of the topics from which the discussion questions will be taken. On problems, please show all calculations when you complete the final. Problems: (TCO B) Three-point estimate: Problem (TCO B) Contingency Pricing: Problem (TCO G) Crashing: Problem (TCO C) WBS: Problem (TCO E) Resource Allocation/Leveling: Problem (TCO F, G) Earned Value/PMIS: Problem (TCO C) General Budget development, sensitivity: Problem Discussion topics: (TCO D) Accounting, PMIS, and Project Control (TCO A) Budgeting processes and techniques (TCO E) Resource Allocation Matrix (TCO F) Project Control Process (TCO F, G) EVM and EAC: Discussion: Terminal Course Objectives A Given the WBS and work packages develop an understanding of budgeting processes using top-down and bottom-up techniques. B Given the WBS and work packages, analyze the various cost estimating processes and investigate approaches used to justify and allocate contingency funds. C Given the project plan, develop budget estimates in appropriate categories including but not limited to labor, non-labor, overhead...