MEMORANDUM
Date : February 23, 2013
To : Claudia Lau, Senior Manager
From : Rachel Lee, Project Manager
Subject : Progress of Ernst and Young’s Annual Family Day Event 2013
Ernst and Young’s annual Family Day event has been scheduled to be held on the third Saturday of May, which is 25th May 2013. The event aims to enhance the level of interaction among the staff members and their families through a variety of exciting games and activities organized. Since Ernst and Young emphasizes on the harmonious yet dynamic working environment, the Family Day event acts as a token of appreciation for the contributions and efforts of its employees, meanwhile it provides a chance for the employees to take a breather with their families. Therefore, this report is to enlighten you on the progress of the preparation for the company’s annual Family Day event.
Past Progress
Theme
The theme of our Family Day event is “I Love You, You Love Me, We’re Happy Family”, which has been decided on 9th February 2013. This theme was selected as we strongly believe that the bond among employees is essential, as well as the family ties. To achieve maximum efficiency and effectiveness, the relationship among employees should be equivalent to a camaraderie seen in a medical or military unit, in which everyone works collaboratively. Through this theme, the company also wishes to emphasize that employees should not neglect their families despite heavy workloads at times.
Date and Time
The General Manager, Miss Jennifer Lim has approved the date of the Family Day event, which is on 25th May 2013. It has been our culture to organize Family Day in the middle of the year as we believe that this is the most suitable time for employees to unwind themselves. The grand event would commence at 9.00 a.m. and end at 11.30 p.m.
Venue
We have made reservations with Avillion Port Dickson, Seremban on 10th February 2013, with a reasonable price of RM13,000, to hold our Family Day event at the open space near the East gate of the resort. Avillion Port Dickson has become our choice because of its breathtaking beachfront view. As white-collar workers are often trapped in the hustle and bustle of cities, we believe that the rhythmic waves which roll towards the white sparkling beach would ease the tension of our staff and their families. Furthermore, Avillian Port Dickson is well-known as an ideal place for recreation and relaxation for its mesmerizing scenery will help one to discard and purge all worries from the mind.
Event’s Schedule
To ensure that our Family Day event can be carried out smoothly, our event planner has come up with the event’s schedule. The Family Day event’s schedule is as follow: Time | Activities | 9.00 a.m. | Arrival and registration of staff and their families | 10.00 a.m. | Arrival of special guests | 10.30 a.m. | Opening ceremony | 11.00 a.m. | Performance by Jing Chang’s band | 11.45 a.m. | Lunch buffet | 1.15 p.m. | Side stall games, lucky draws | 3.30 p.m. | Sandcastle building, egg-catching, coloring contest and guli-searching | 5.30 p.m. | Beach sports games: Tug-of-War, Volleyball and mass Yoga exercise | 7.30 p.m. | Barbeque dinner | 11.00 p.m. | Prize giving ceremony | 11.30 p.m. | Closing ceremony |

Budget
On 21st February 2013, our budget of RM74,200 was approved by the Finance Department Manager, Mr. Albert Toh. This significant amount includes RM13,000 as the reservation fee for our venue for the Family Day event, RM10,000 for the expenses of games and activities, RM8,000 for site decoration, RM20,000 for lunch buffet and barbeque dinner and RM3,200 for the lighting and sound effect at the site. We will also incur additional costs for 50 items of prizes for lucky draws which are around RM10,000. In addition, we estimated to spend RM10,000 to invite the Taiwan’s famous singer, Jing Chang and her band to perform on stage for one hour.
Present Status
Registration
The registration for the Family Day event has been ongoing throughout the organization since 18th February 2013. Employees are required to register themselves, as well as their participating family members, through the company’s Intranet latest by 5.00 p.m. on 25th March 2013. We have highlighted that late comers will not be entertained.
Invitation
We have sent invitation letters to the Chief Executive Officer of Ernst and Young in Malaysia, Mr. Lee Gaik Thuah, the Chief Financial Officer, Mr. Chen Joo Guan, the General Manager, Miss Jennifer Lim and the Board of Directors as the guests of the opening ceremony in this event. Meanwhile, we are waiting for the confirmation letter from our special guest who is Taiwan’s renowned singer, Jing Chang and her band. We will contact our guests of honor via email or telephone as a reminder if they fail to confirm their attendance with us by 22nd March 2013 (Friday).
Sponsorship
As we have sent the sponsorship letters to three companies which include KPMG, Public Bank and Air Asia Company, we are now waiting for their confirmation. The purpose of the sponsorship is to foster the relationship among businesses. For KPMG, we are requesting for the sponsorship of the grand prize in lucky draws which values at RM5,000. We are also hoping that Public Bank will sponsor us with the second prize for lucky draws which costs around RM3,000. Being a frequent client of Air Asia Company for business trips, we are looking forward to receiving the sponsorship of the third prize of lucky draws which values at RM1,000 from Air Asia. Furthermore, we are making an appointment with the General Manager of the Star newspaper corporation, Mr Alex Lim to discuss about the sponsorship in covering our corporate achievements and celebration of Family Day event in the weekend newspaper.
Food
We have looked into various menus with estimated costs to ensure that our expenses for food do not exceed the given budget. Our secretary, Ms Cecilia Chew is writing to the Operations Manager of Avillian Port Dickson, Mr. Tee Guilay to make reservations for lunch buffet on 25th May 2013. We will be booking a medium-sized ballroom to accommodate all our participants. Besides, we are also requesting from Avillian Port Dickson to provide the facilities for us to have barbeque dinner on the beach.
Games and Activities
Considerable progress has been made for the planning of interesting and exciting games and activities. On 20th February 2013, several senior managers of Ernst and Young have communicated to us their choice of preferred games. Nevertheless, we discovered that some of the suggested games do not suit the objectives of the Family Day event. Although water sports activities such as parachuting, windsurfing and scuba diving would be challenging and adventurous, they would not be the cup of tea for majority employees and their family members. Therefore, we are in the midst of proposing appropriate activities and games for the grand event. The following is a list of recommended activities that could be carried out. 1. Beach volleyball which encourages sportsmanship among employees 2. Tug of War which will be a good workout under the sun 3. Sandcastle building competition among families which ignites the team spirit 4. Guli searching in the sand for children which would be a relaxing and enjoyable activity for children 5. Side stall games such as the Hoopla, Ball-in-the-Basket game, Basketball-shooting game and Hit-the-Bell game 6. Egg catching game to test the responsiveness of players 7. Coloring contest which enhances children’s coloring skills and creativity 8. Basic Yoga exercise on the beach coached by Avillian Port Dickson’s Yoga Club trainers 9. Barbeque at the beach at night
Future Schedule
Site Decoration
Our team will pay site visits and conduct environmental assessment for the next few weeks. We will only put up ornaments by the beach two days before the Family Day event, which is on 23th May 2013. Makeshift counters as information centre with flashes from brilliant neon lights will be set up at the East gate of Avillian Port Dickson, facing the crystal blue sea. We will also erect sufficient tents, the exact number which is to be determined by 25th March 2013, along the seaside, decorated with colorful balloons and flags. We wish to create a cozy ambience for the participants.
Sound and Lighting Effects
After researching several sound and lighting effects companies, we will contact Thien Teong Sound & Light Sdn Bhd for their professional services after confirming the number of participants on 25th March 2013. We wish to provide accurate information of the number of participants for the sound and lighting coverage of the site. There should be no problem in signing another contract with Thien Teong Sound & Light Sdn Bhd as we had performed several business dealings in the past. Therefore, we estimate that we can confirm the sound and lighting effects service provider end of next month, before 29th March 2013.
Prizes
The first, second and third prizes for the lucky draws will be obtained from sponsorships. The company will fork out approximately RM10,000 for additional 50 items of lucky draw prizes, which will cost about RM200 each. The items will include 15 bicycles, 15 electronic cookers, 10 Hp printers and 10 hampers. These items will be purchased by 1st May 2013.

Souvenirs
We will be giving out souvenirs to every participant of the Family Day event as an appreciation of their support and attendance. We will also present souvenirs to our special guests as a token of gratitude at the end of our event.
Up to today, our team has not confronted with any major problems. Each team member is striving to perform the tasks well. Therefore, we are confident that all the tasks could be completed on schedule. We hope that you would find this report satisfactory. Should there be any inquiries or suggestions regarding the Family Day event, please feel free to contact the Project Manager, Ms Rachel Lee at 012-8663456 or via email at rachellee@eny.com.

Similar Documents

Free Essay

Progress Report

...Ms Gloria friend of 12 years is migrating and decided to sell Ms Gloria her house for JMD$3,000,000.00. Ms Gloria applied to the National Housing Trust (NHT) June 26, 2014 for a loan to purchase the property and was approved for the maximum amount of JMD$4,500,000.00 that is granted by the NHT. Since she has already gotten JMD$3,000,000.00 to purchase the property, she is applying for the remaining JMD$1,500,000.00 to renovate the property and as such she provided the NHT with a progress report. The duration of the schedule is as follows: * Building plan for approval by the parish council (May 14, 2015 to August 14, 2015) * NHT approval of renovation funds by August 31, 2015. * Complete phase 1 of work by September 20, 2015. * Complete phase 2 of work by October 14, 2015. * Complete phase 3 of work by November 14. 2015. Work done prior to this application: 1. Removal of the original zinc roof. 2. Removal of windows and doors. 3. Removal of old tiles 4. Get Building plan drawn for the decking that will replace the zinc roofing. 5. Get the Building plan approve by the local parish council for the steel work in the propose deck roof. 6. Getting quotation from the construction company for labor cost. 7. Getting pro-forma invoice from material suppliers. Problems encountered during the preparation phase prior to NHT approval of renovation funds: 1. After the removal of the zinc roof, it was realized that the electrical wiring...

Words: 382 - Pages: 2

Premium Essay

Progress Report

...This is the progress report that you requested us to submit about our long report on, Coca Cola’s most successful and unsuccessful advertisements. Since the beginning of the long report we have been meeting every wednesday to work on completing the multiple criteria assigned. On our first night we discussed which company would provide the best advertisements to analyze. Unanimously we decided Coca Cola to be an excellent lead company with plenty of campaigns to choose from. After some basic research we narrowed down the long list of Coca Cola’s advertisements to a more manageable one. Our new list consisted of four successful and four unsuccessful ad campaigns allowing us to focus our research. The research completed helped us to determine a total of four ads that could be best analyzed throughout our long report. We then used that research to compose and submit our proposal for approval. After we received our proposal back and reviewed the suggestions, we revised any errors. Within the proposal we included employees from different advertising agencies we had an interest in writing letters to. We then composed our own letters containing a series of different questions and sent the letters to our designated experts in hopes to attain additional information. Finally, we finished our research for the long report and determined where each source would be used within the document. Throughout our meetings we did run into a few complications. One was finding a day,...

Words: 293 - Pages: 2

Free Essay

Progress Report

...Summary We are working on developing a bike-sharing infrastructure in Vancouver. Our goal is to implement a network with 100 bikes and 10 stations located throughout downtown Vancouver. Mainly around sky-train stations and the busiest streets. Residents and visitors will have access to an easy, convenient and fun means of transportation. Bike2Go will be available 24 hours a day, 365 days a year. The station network will provide twice as many docking points as bicycles, assuring there will be a nearby dock for all users. Our fleet will include robust, practical, and stylish Vanhawk Valour smart bikes. Works Completed We have conducted market research and studied current successful instances of our company in other cities around the world. Users can purchase 24 or 72-hour short-term memberships and receive ride codes to unlock a bicycle. Long-term memberships are ideal for Vancouver residents and can be purchased by the month or the year. Long-term members will receive a card key that can be inserted directly into the bike station to instantly unlock a bike to ride. Riders will pay increments for the total amount of time they have used the bike. After several test drives, and public surveys, we decided to purchase Vanhawks Valour bicycles as our product bicycles. Vanhawks is a Canadian company that manufactures the first carbon fiber smart bike. The Valour features Bluetooth 4.0, Gyroscope, Accelerometer, Magnetometer, Speed sensor, GPS Receiver, Mesh-network, Blindspot...

Words: 426 - Pages: 2

Free Essay

Progress Report

...WHAT IS pH  AND HOW IS IT MEASURED?            A Technical Handbook for Industry                                                            CHAPTER 1 – INTRODUCTION  Why Is pH Measurement Necessary?  3  CHAPTER 2 – WATER AND AQUEOUS SOLUTIONS  The Properties of Water  Ion Product Constant of Water  Molarity  4    4  5  CHAPTER  3  –  FUNDAMENTALS  OF  pH  Definition of pH  pH Values and Hydrogen/Hydroxide Concentration  How is pH Measured?  Activity versus Concentration  The Nernst Equation  The Standard Hydrogen Electrode  6    6    7    7    9    9  CHAPTER 4 – THE pH SENSOR  pH Electrodes  The Measuring Electrode  Asymmetry Potential  Sodium Ion Error  Acid Error  Temperature  Effects  The Reference Electrode  The Reference Junction  Junction Potentials  Gel‐filled Reference Electrode  Buffers  Calibration  11    13  13  14    15  15   16    17  17    18    18  18  CHAPTER  5  –  CARE  OF  pH  ELECTRODES  Dehydration  Factors Detrimental to Electrode Life  Transportation  Storage  22    22  22   23  CHAPTER 6 – COMMON APPLICATIONS  Cooling Tower Control  Food Processing  Coal Industry  Plating Waste Treatment  Ultrapure Water    24    24           24          25          25  BIBLIOGRAPHY                                                                                                  27    GLOSSARY                                      ...

Words: 11054 - Pages: 45

Premium Essay

Weekly Progress Report

...University of Phoenix Material Weekly Progress Report Template Submit your Learning Team’s weekly progress report at the end of Week Two, Three, and Four to the instructor using the template below. Answer the questions as a team. Your team may choose to answer either in bullet form or paragraph form as long as the questions are answered sufficiently. Learning Team __E______ Week ___3____ 1. What did the team plan to do this week? This week we put together a starting point for our project. 2. What is the team planning to do next week? Next week we plan on adding more to our project. 3. Provide a summary of what the team created this week. This week we created a power point that we will be using for our project. 4. Is the team on schedule, ahead of schedule, or behind schedule? I believe that we are on schedule. 5. If you are behind schedule, what are you going to do to get back on schedule? We have gotten on schedule by creating a power point that each member can add their own information to. 6. What issues or obstacles face the team and how are you going to address them? As of right now it seems as if some of us where having computer or internet issues but everyone seem to be back on track. If we have any further issues we will have to join together as a team to complete the assignments that we have to turn...

Words: 252 - Pages: 2

Premium Essay

Weekly Progress Report

...University of Phoenix Material Weekly Progress Report Template Submit your Learning Team’s weekly progress report to the facilitator at the end of Weeks Two, Three, and Four. Use the following template and answer the questions as a team. Your team may answer either in bullet or paragraph form as long as the questions are answered. Learning Team¬¬¬¬¬¬__________________A________________ Week ________2________ 1. What did the team plan to do this week? For this week, we each established what we were going to contribute to the final project. Alyssa Noriega committed to focus on the anticipated effects of this technology on health care as well as formatting resources. 2. What is the team planning to do next week? We will all communicate with each other as well as work on our key points and rough draft for week 5. 3. Provide a summary of what the team created this week. We each chose a portion of the final assignment that we will cover. We also established an outline so that each member can get a clear understanding of what they are responsible of doing. 4. Is the team on schedule, ahead of schedule, or behind schedule? Overall the team is on schedule as well as me. We will continue to communicate with those who may be a bit tied up due to personal reasons. 5. If you are behind schedule, what will you do to get back on schedule? Not applicable. 6. What issues or obstacles face the team? How will you address them? ...

Words: 295 - Pages: 2

Premium Essay

Chronological Progress Report

...To: Diane Kullman CEO of American Express International, Inc. From: Stella Consulting Agency Subject: Progress on Stella Consulting Agency’s formal report on the expansion of American Express International, Inc. in Singapore Stella Consulting Agency has obtained most of the information necessary to decide further strategies on expanding American Express International, Inc. banking business in Singapore. The agency is currently analyzing and organizing the information for the formal report. The formal report will be submitted no later than December 13. Work Completed To investigate the feasibility of American Express International, Inc. expanding operations into Singapore, Stella Consulting Agency submitted a research proposal that defined our topics to investigate a list of preliminary sources. The research proposal includes the problem, country overview, and qualifications sections. Three sources that were discovered have also been included in the methods section. The three sources are: 1. The multi-cultural cosmopolitan city of Singapore is the most competitive in Asia and is officially the world’s easiest place to do business. 2. The Government is well known for its pro-business policy regardless of world economic situations and crisis, while promoting assets such as integrity, quality, reliability, productivity, rule of law and enforcement of intellectual property rights. 3. Government approval is not required for foreigners...

Words: 398 - Pages: 2

Premium Essay

Ifa Progress Report

...32965 Information Note by World Bank Staff July 12,2005 TABLE CONTENTS OF I N T R O D U C T I O N .............................................................................................................. I . I1 . 3 4 10 10 11 13 14 14 17 19 THE GLOBAL AGENDA .......................................................................................... PROGRESS IN THE IFA AGENDA ....................................................................... The Financial Sector Assessment Program (FSAP) ............................................. The Reports on the Observance o f Standards and Codes (ROSC) ....................... The Financial Sector Reform and Strengthening Initiative (FIRST) .................... The Financial Sector Reform and Strengthening Initiative (FIRST) .................... Combating Money Laundering and Terrorist Financing (AML/CFT) ................. Debt Sustainability & Debt Management ............................................................. Social Protection................................................................................................... A. B. C. C. D. E. F. ANNEX Accounting and Auditing ........................................................................................... Corporate Governance ............................................................................................. Insolvency and Creditor Rights ................................................................................ ...

Words: 12222 - Pages: 49

Premium Essay

Staff Mid Year Progress Report

...| 2013/2014 Staff Mid-Year Performance Progress Report | | Employee Name | | Employee ID | | Employee’s Manager | | Job Title | | Job Title | | Department / College | | Evaluation Period | | I. Customer Service | Ratings: Excellent (4), Good (3), Average (2), Poor (1) | Line Manager’s Ratings | Improvements Needed | Respond to customer inquiries in a timely and professional manner | | | Deals with customer complaints in a professional and respectful manner | | | Understands customer needs and fulfils them | | | Shows respect for others and builds trust with internal/external customers | | | Competence in knowing ADU operations to properly inform customers | | | Listens carefully and show proper attention when dealing with internal/external customers | | | II. Goals and Objectives (New or as per last evaluation) Ratings: Excellent (4), Good (3), Average (2), Poor (1) | List of Objectives/ KPIs | Achievements | Rating | Improvements Needed | 1. Reducing missing documents on the student’s file | 90% of students file have no missing document | | | 2. Restructuring of student files and records both undergraduate and postgraduate | Retrieval and deliver of record to users in efficient manner | | | 3. No. of student complaints recorded with respect to inaccuracies in student information | 99% of students information is accurate in ERP system as per in the student’s file | | | ...

Words: 272 - Pages: 2

Premium Essay

Biden Reports Progress on Budget Deal

...This article is about the budget deal that’s currently being debated about that would cut federal spending by as much as 33 billion dollars and dodge a government shutdown. As of right now, there is a difference in what should be included in it and not included in the budget. If the deal were to be approved, the deal would be the largest single year budget cut in U.S. history. The government would be funded through the current fiscal year, which ends in September, and then end stopgap resolutions. The senate and the house have agreed on 10 billion dollars in budget cuts, but they are now searching for another 23 billion dollars in cuts according to lawmakers and aides from both sides. House leaders said they will vote March 31st to make their bill for 61 billion dollars in budget cuts if the senate fails to act by April 8th. How it would pass constitutionally is not likely, as the Senate has rejected that bill and President Obama has vowed to veto it. House Republicans are very frustrated because the Senate Democrats haven't submitted their proposal yet. This bill will most likely die and not become a budget in my opinion. This article relates to American government because it involves the House of Representatives, the Senate and the President in proposing bills and budgets. It basically relates to how a bill becomes a law. The House of Representatives seem to be the only ones who appear to favor the budget while the Senate and President do not. In order for a bill like this...

Words: 478 - Pages: 2

Free Essay

Implementation of New Digital Audio Workstation - Fl Studio

...[pic] Progress Report with working outline/rough draft For Margaret Sledziewski, Supervisor Prepared by: Bilal Zaheer Researcher Submitted: November 2, 2007 Steamline Production To: Margaret Sledziewski From: Bilal Date: November 1, 2007 Re: Progress report Implementation of new digital audio workstation - FL Studio On October 19, 2007, I proposed an Implementation of new digital audio workstation - FL Studio. After your approval of my project, we have encountered a couple problems but other than that everything is going well and all the work will be done by November 19, 2007. This memo reports the progress report, the problem we have encountered and the conclusions. Background As you know, FL Studio is a digital audio workstation which can record, mix, create, and edit sounds. It has a sequencer that makes it possible to create beats from patterns, which is the foundation of any track. The program currently used by the firm is fairly complicated and hard to use. This results in poor production. By using FL studio, we can create exact tracks which we intend to make. In my research I found that our competition has increased. Other similar companies have also upgraded their software to assist them in meeting their clients’ demands. I however, found out that none of them are using this software. This software is very helpful for our music industry and can give us an upper hand against our competitors. Project...

Words: 974 - Pages: 4

Free Essay

Memorandum

...Memorandum DATE: February 7, 2014 TO: Steven Teh, General Manager FROM: Elizabeth Lee, Chairperson SUBJECT: WORK PROGRESS OF GRAND OPENING OF SRS FURNITURE COMPANY NEW SHOWROOM This memo depicts the work progress of me and my committee members for preparing the grand opening of new showroom, SRS HOME DÉCOR in Bandar Baru, Kampar. Last year, SRS Furniture receives a very good feedback from customer on providing good quality furniture and creates an outstanding sales performance in Ipoh, Perak. Hence, we decided to enlarge our business to Kampar to benefit more household in acquiring high quality furniture. The proposed launching date of our new showroom will be on February 28, 2014 (Friday). The preparation of SRS Furniture Company’s new showroom had been started since January 2nd, 2014. Until today, the work has entered second stage and all works are carrying out as original schedule. Past Progress/ Work Completed (i) Financing Budget On January 3rd, the very first committee meeting had been conducted to discuss the budget needed to fund the overall activities for the event. The budget manager is requested to submit a budget report with each items clearly stated with the actual expenditure amount and has the result that total expenses for the event are RM 200, 000 and it is approved by the Finance Department of the company. The allocation of budget is on refreshment, celebrities and event speaker’s fees, technical equipment and other necessary resources running the...

Words: 867 - Pages: 4

Free Essay

Project Status Report

...[PROJECT STATUS REPORT] Rev. 1.0, 25/10/2013 Company here Bi-weekly Project Status Report GENERAL INFORMATION Project Name Project Manager Project ID Number Prepared by Project Sponsor Reporting Period Ending Date [DD/MM/YYYY] Report Number Section I TASKS/MILESTONES COMPLETED This section only includes tasks/milestones that are completed since last reporting period (Report Number CT-BWR-09, dated 23/05/2012). [Insert rows as needed] Description of Task/Milestone Baseline Finish Date [DD/MM/YYYY] Current Status* Actual Finish Date [DD/MM/YYYY] Remarks [PROJECT STATUS REPORT] Rev. 1.0, 25/10/2013 Section II Company here ISSUES IDENTIFIED [Insert rows as needed] Description of Issue Reported by Reported Date [DD/MM/YYYY] Estimated Resolution Date [DD/MM/YYYY] Remarks Section III PROJECT CHANGES [Insert rows as needed] Change Reques t ID No. Description of Change Change Requestor Approval Status Action Steps Actual Resolution Date [DD/MM/YYYY] Current Change Status* [PROJECT STATUS REPORT] Rev. 1.0, 25/10/2013 Section IV Company here UPCOMING TASKS/MILESTONES This section only includes tasks/milestones that are to be completed by next reporting period, ending 06/06/2012. [Insert rows as needed] Description of Task/Milestone Baseline Finish Date [DD/MM/YYYY] Current Status* Remarks *Key: This column should be populated with the task/milestone current status. Valid options...

Words: 386 - Pages: 2

Free Essay

Contract

...right to request for detail quotation for provisional sum or can also request for alternative quote including for other subcontractor and suppliers Clause 3 * The form of security can be approved or disapproved by him and he must have access to security at any time to recover any claim for damages caused by contractor during WUC Clause 5 * He must make sure that all the document & necessary information with number of copies are provided to contractor , not to be used , copied nor reproduced for any purpose other than WUC Clause 8.2 * He has right to request for detail breakdown for contract sum by trade including preliminaries, profit and overhead, a cash flow forecast for a period for WUC precedent to payment for the first progress certificate and any progressive certificate thereafter Clause 8.3A * He must make sure...

Words: 1026 - Pages: 5

Free Essay

Apple vs. Samsung Effects of Globalization

...APPLICATION For CNPCIW Vendor/Bidders List China National Petroleum Corporation International and Watan Oil & Gas Afghanistan Limited. (CNPCIW) June 2012 Application Submission Form NOTE: The application submission shall be presented on the Applicant’s company stationary, in the case of a Joint Venture, on company stationary of the lead partner and stamped by company seal. Date: [08, December, 2012] Reference: Execution of upcoming Services & Supply Projects under CNPCIW, Afghanistan Subject: Application for CNPCIW Vendor/bidder List |To: |CNPCIW | | |Attn: Contracts Office | | |House No. 1029, Street 15 | | |Lane 6, Wazir Akbar Khan | | |Kabul, Afghanistan | Dear Sir/Madam, Being duly authorized to represent and act on behalf of Green Tech Construction & Engineering Co., and having reviewed and fully understood all of the Application requirements and information provided, the undersigned hereby applies for Application to be included on the CNPCIW Vendor List for Works (Contractors). Your organization and its authorized representatives are hereby authorized to conduct any inquiries or investigations to verify the statements, documents, and information submitted in connection with this application, and to...

Words: 938 - Pages: 4