I. Pre-Feasibility Study – Identification of Proposed 220 KV link [4 weeks]
II. Feasibility Study – Investment/Project Approval [+ 10 weeks]
III. Engineering & Contracting – Specifications, Tendering & Awarding [+12 weeks]
IV. Project Execution, Monitoring and Management
V. Procurement of power through State/Open Access

Considering the load requirements, transmission system availability, PTC has prioritized refinery locations where up gradation to 220KV transmission system should be undertaken:-

Priority Refiner Location Energy Requirement Present Connectivity
I Panipat 149 MW 132 KV Gujarat 117 MW 66 KV
II Mathura 58 MW 33 KV Haldia 58 MW 33 KV
III Bongaigaon 26.6 MW 132 KV Guwahati 17 MW 33 KV Barauni 44 MW 33 KV ASSESSING FEASIBLE GRID INTERCONNECTION
I – Prefeasibility Study

I. Site visit for relevant data collection and studies on optimal/feasible substations for 220KV grid interconnection in consultation with State and IOCL officials.
II. Studying the technical pre-feasibility & recommendations for the identified options.
III. Examining commercial feasibility of the proposed option/project based on savings accrued from competitive procurement of power through grid, cost benefit analysis and payback period

II – Feasibility Study

I. Collection of relevant data at different substations for grid interconnection, including the power supply scenario, voltage fluctuation, frequency variation, availability of transmission corridor for power procurement and assessing the stability of selected grid substation.
II. Survey of transmission line and associated activities limited to feasibility of