Free Essay

Littlefield

In:

Submitted By alexander45
Words 1792
Pages 8
June 9, 2013 Section 2, Team 9

Managing Capacity and Lead Time at Littlefield Technologies – Team 9’s Summary
The purpose of this simulation was to effectively manage a job shop that assembles digital satellite system receivers. The objective was to maximize cash at the end of the product life-cycle (270 days) by optimizing the process design.
REVENUE
25000 20000 15000 10000 5000 1 9 17 25 33 41 49 57 65 73 81 89 97 105 113 121 129 137 145 153 161 169 177 185 193 201 209 217 225 233 241 249 257 265 Total Revenue Demand DAYS 0

Figure 1 : Revenue and demand

DEMAND 25 20 15 10 5 0

As shown by the figure above, total revenues generally followed the same trend as demand. The few sections of negative correlation formed the basis for our critical learning points. Although the process took a while to completely understand during the initial months of the simulation, the team managed to adjust, learn quickly and finish in 7th place with a cash balance of $1,501,794. For the purpose of this report, we have divided the simulation into seven stages after day 50, explicating the major areas of strategically significant decisions that were made and their resulting effects. Initial Operations Strategy - Days 0 to 50 The goal was to act conservatively and avoid making reactionary decisions. The strategy was to reduce lead-time to 0.25 days (6 hours) as quickly as possible. The rationale was: • To move to contract option two which allowed us to maximize revenues per job; • To maintain work-in-process (WIP) inventory of less than 100 units to avoid turning away new customer orders until this backlog was cleared. A second stuffer was purchased as this was highly utilized during the first 50 days of the simulation. We also switched to smaller batch sizes (two lots of 30 kits each) to monitor its effects on lead times. Stage 1 – Days 50 to 88 On day 59, with the average daily job lead-time at 0.3, we recognized an opportunity to generate higher revenues via contract two. By day 71, the tuner had reached maximum capacity and a second one was purchased. However, lead times began to rise quickly so we moved back to contract one. Once operations stabilized by day 73, we successfully reduced lead times by decreasing the batch size to 3x20. By day 84, the tester was almost over utilized and the queues were increasing. In order to expedite jobs, we gave priority to jobs slated for step four. Stage 2 – Days 89 to 114 As demand increased, the queue for the tester reached 109 jobs. We increased the lot size 1x60 to clear this queue. The tester utilization was expected to continue on its upward trend and so another tester was bought on day 108. The batch size was also reduced back from 1x60 to 3x20. Economic Order Quantity (EOQ) At day 114, we tried to determine the appropriate batch size to minimize the inventory costs. Our research lead us to Economic Order Quantity. This required a forecasted demand to calculate the EOQ over various periods in the simulation. We plotted number of jobs arriving against the days and added a Page 1 of 3

June 9, 2013 Section 2, Team 9 regression line to predict demand at day 150, when the demand was supposed to stabilize. Our regression line gave us an equation of Demand = (0.0651 x Day Number) + 1.0651. At day 150 (assumed to be the peak), our formula predicted an average demand of 10.8 jobs per day. We approximated this to 11 for the sake of simplicity. 2 �� �� ��

������ =

D = Forecasted annual demand = 11×365 = 4015 orders per year S = Set up cost/order (assumed to be the shipping cost) =
!!!""!#$ !"#$# !"#$!!" !" ! !!!"#$%&

=

!""" !"#

= $8.33

H = Holding cost/order = assumed at 1/3rd the cost of the order = . 333 ×$600 = $200 Therefore EOQ = 18.3. We decided that the batch size of 3x20 was the optimal size and would further reduce lead times by reducing the WIP inventory. On day 114, the batch sizes were switched once again to 3x20 kits. At this time, the tuner was at low utilization (approx. 20%) so there seemed to be sufficient capacity to handle this switch in batch sizes. Now that we had two tuners running, the results we had experienced around day 73 were not anticipated. Stage 3 – Days 115 to 128 On day 116, we performed an analysis of our data points up to and including day 114 and concluded that contract two would be more lucrative if average lead times were kept under 0.33 days. While this would have meant $0 revenues on some days, our net profits would still be higher. Due to increased demand and an inability to process 3x20 units, the queues at the stuffer and tuner spiked on day 121. We knew that demand would continue to increase and so we purchased another stuffer. The negative correlation between revenues and demand at this time is seen in Figure 2.

REV

Figure 2: Stage 3

DEMAND

25000 20000 15000 10000 5000

18 16 14 12 10 8 6 4 2 118 120 122 124 126 128 130 132

0 0 Additionally, revenue was decreasing as lead-time had spiked to DAYS almost 24 hours. As such, we switched back to contract one to Total Revenue Demand reduce our losses. This strategy seemed successful and by day 125, lead times were decreasing and we switched back to contract two. Demand, however, continued to increase and by day 128, our tuner was over utilized and our queue for the tuner was in excess of 200 units. The team had overlooked the fact that the tuner took relatively the same time to process a 1x60 unit order as a 3x20 unit order; this oversight was starting to cost us deeply. There was no way to “purge” the system of our queues by halting orders; the alternative was to switch the batch size to 1x60 kits to clear the queue. The eventual recovery can be seen from days 128 to 132 in figure 2.

Stage 4 – Days 129 – 142 Purging the system was a slow process, but was essential to bring down lead times. The effects of the change in lot size to 1x60 were seen within a few days and the queues at the tuner were back down to manageable levels. The team realized the tuner would be unable to handle our calculated batch size of 3x 20. We conducted a cost benefit analysis using estimated lead times and revenues to determine if we should buy a third tuner. We decided that our demand was almost at its peak and our analysis concluded that no significant benefit would be realized from purchasing another tuner. We decided to optimize the process using a batch size of 2x30. Page 2 of 3

June 9, 2013 Section 2, Team 9 Stage 5 – Days 143 – 176 This period was a reality check for the demand forecast. The incredible variability in the demand at the peak levels was not accounted for. The number of arrivals reached 20 on some of the days, far in excess of the predicted value of 11. The tuner was again unable to handle the demand, leading to station three queues in excess of 200 units. As shown in Figure 3, revenues dropped as demand increased. The lot size was again changed to 1x 60 implementing our “purging” strategy from Stage 3. Once queue sizes were back to normal and the revenues started to match the demand, we switched the lot size back to 2x30.
REV

25000 20000 15000 10000 5000

Figure 3: Stage 5

DEMAND

25 20 15 10 5

Stage 6 – Days 177 – 220: Exit Strategy 0 0 As demand began to decrease at day 180, we maintained our DAYS approach (batch sizes of 2x30 kits and contract two). The team Total Revenue Demand considered the variability in demand that was previously overlooked and decided to only retire one stuffer at day 218 and one tester at day 219, ensuring we would have enough capacity to maintain a low lead time even at a demand of ten orders per day. This strategy proved effective and we maximized profits through the remainder of the simulation.
163
166 169 175 160

Lessons Learned The overarching takeaway from this exercise is the importance of being pro-active rather than re-active. This is elucidated through the main points below: 1) Demand forecasting: We initially neglected demand variability and so failed to estimate the capacity of the process. This also impacted the EOQ calculation. We should have considered using a 95% confidence interval. The standard deviation at day 114 was around 3 which would have given us a maximum demand range from 5 – 17 orders/day (���������� = ������������������ ������������ ± 2 ���������������� ��������������������) 2) Economic Order Quantity: Through this process, we were introduced to the EOQ concept. The EOQ calculation would have been beneficial at the start of the process (day 50). Even though we would have had to make several assumptions, it would have provided a better starting point. 3) Criticality of a thorough Analysis: An analysis of the capacity and utilization of the tuner would have made it obvious that a batch size of 20 would be too much for two tuners to handle in conjunction with three stuffers. Using the times given the stations and incorporating an allowance for the variability in the demand and the queues (buffers) before each station, we would have realized that our setup of 3-2-2 using 2x30 units would have been optimal from the start. Furthermore, an analysis of the two contracts at the outset and the determination of the breakeven point for the lead times would have made the decisions of switching contracts fairly easy. 4) Interdependency of operational measures: As we decreased the batch size, we reduced leadtime by minimizing WIP inventory (lead time was proportional to lot size). However, this is not the only factor affecting lead. We also needed to consider the capacity of the machines and the variability in inputs in collaboration with our analysis. 5) Decisions made in haste are rarely good ones: While the initial strategy was to avoid making hasty decisions, it was easy to get caught up in the ‘competition’. There were periods where contracts and lot sizes were switched back and forth without any real analysis. It would be prudent to maintain a control system to ensure hasty decisions are not made. Overall, the Littlefield simulation provided a valuable lesson in plant operations, particularly as they relate to issues of variability, demand forecasting and the interdependence of operational measures. Page 3 of 3

172

178

Similar Documents

Premium Essay

Littlefield

...Background In early January 2006, Littlefield Technologies (LT) opened its first and only factory to produce its newly developed Digital Satellite System (DSS) receivers. Littlefield Technologies mainly sells to retailers and small manufacturers using the DSS’s in more complex products. Littlefield Technologies charges a premium and competes by promising to ship a receiver within 24 hours of receiving the order, or the customer will receive a rebate based on the delay. The product lifetime of many high-tech electronic products is short, and the DSS receiver is no exception. LT managers have decided that, after 268 days of operation, the plant will cease producing the DSS receiver, retool the factory, and sell any remaining inventories. As this is a short life-cycle product, managers expect that demand during the 268 day period will grow as customers discover the product, eventually level out, and then decline. In the initial months, demand is expected to grow at a roughly linear rate. Demand is then expected to stabilize. Eventually, demand should begin to decline at a roughly linear rate. Although orders arrive randomly to LT, management expects that, on average, demand will follow the trends outlined above. Management’s main concern is managing the capacity of the factory in response to the complex demand pattern. Delays resulting from insufficient capacity undermine LT’s promised lead times and ultimately force LT to turn away orders. In particular, if an order’s...

Words: 1783 - Pages: 8

Premium Essay

Littlefield

...LittleField In the LittleField Game 2, our team had to plan how to manage the capacity, scheduling, purchasing, and contract quotations to maximize the cash generated by the lab over its lifetime. We knew that our output was lower than demand right when Game 2 started. 1st stage, we knew there will be bottleneck at station 1 and 3 so additional machines must be purchased. We decided to purchase an additional machine for station 1 because it was $10,000 cheaper, utilization was higher here, and this is where all the orders started. We also reorder point (kits) and reorder quantity (kits), giving us a value of 49 and 150. 2nd stage, we have to reorder quantity (kits) again giving us a value of 70. In two days, we spend a lot of money on kits so we realize we only needed two machines at station 2 and 3. We then reorder point (kits) to a value of 55 and reorder quantity (kits) to 104. We are making money now at station 2 and station 3. However, we realize that we are not making money quick enough so we change our station 2 priority to 4 and use the money we generate to purchase additional machine at station 1. We now have a total of five machines at station 1 to clear the bottlenecks and making money quickly. Stage 2 strategy was successful in generating revenue quickly. 3rd stage, while the focus of the first two stages was making the most money, we will now turn our strategy in keeping our lead against other teams. We bought more reorder point (kits) and sold it for contract...

Words: 431 - Pages: 2

Premium Essay

Littlefield

...Littlefield Simulation II Based on our success in the last Littlefield Simulation, we tried to utilize the same strategy as last time. Our goals were to minimize lead time by reducing the amount of jobs in queue and ensuring that we had enough machines at each station to handle the capacity. We wanted to keep the lead time between .5 and 1 day in order to get the maximum amount of revenue per job. We utilized data from the first 50 days and put it in an Excel chart to forecast the demand for the jobs. We knew that the demand would follow the same pattern of increasing to a point, leveling off, and then decreasing at the end. Our goal was to keep lead time to a minimum in order to maximize our completed orders and gain maximum profits.  In order to keep lead time to a minimum, we attempted to keep all of the queues of the stations below 4 in order to reduce waiting time at each station.  To accomplish this, we ordered more machines for each station. We started by first buying a machine for station 1 on day 52 because it had the highest queue. Next, we ordered a machine for station 2 on day 74 and one for station 3 on day 80. This drastically reduced the number of jobs in queue at each station and kept our lead time below a day.  In hindsight, we should have waited more than 6 days to purchase machine 3 until all settled down and we had time to build up capital from the machine 2 purchase.  Towards the end of the simulation, we used a similar strategy to the last simulation and...

Words: 751 - Pages: 4

Premium Essay

Littlefield

...Strategy description Revenue maximization:Our strategy main for round one was to focus on maximizing revenue. We did not want the revenue to ever drop from $1000, so we took action based on the utilization rates of the machines. We needed to have sufficient capacity to maintain lead times of less than a day and at most, 1 day and 9 hours. Based on the linear decrease in revenue after a lead time of one day, it takes 9 hours for the revenue to drop to $600 and our profits to be $0. In terms of when to purchase machines, we decided that buying machines as early as possible would be ideal as there was no operating costs after the initial investment in the machine. Having more machines seemed like a win-win situation since it does not increase our expenses of running the business, yet decreases our risk of having lead times of over a day. The only expense we thought of was interest expense, which was only 10% per year. Therefore, we took aproactive approach to buying machines and purchased a machine whenever utilization rates rose dangerously high or caused long queues. As we will see later, this was a slight mistake since the interest rate did have a profound impact on our earnings compared to other groups. Machine configuration: Our final machine configuration (which was set on Day 67) was 3 machine 1's, 2 machine 2's, and2 machine 3's. This lasted us through the whole simulation with only a slight dip in revenue during maximum demand. In terms of choosing a priority for...

Words: 1738 - Pages: 7

Premium Essay

Littlefield

...Responsiveness at Littlefield Technologies Background Littlefield Technologies (LT) has developed another DSS product. The new product is manufactured using the same process as the product in the assignment “Capacity Management at Littlefield Technologies” — neither the process sequence nor the process time distributions at each tool have changed. The LT factory began production by investing most of its cash into capacity and inventory. Specifically, on day 0, the factory began operations with three stuffers, two testers, and one tuner, and a raw materials inventory of 9600 kits. This left the factory with zero cash on hand. Customer demand continues to be random, but the long-run average demand will not change over the product’ 486-day lifetime. At s the end of this lifetime, demand will end abruptly and factory operations will be terminated. At this point, all capacity and remaining inventory will be useless, and thus have no value. Management is currently quoting 7-day lead times, but management would like to charge the higher prices that customers would pay for dramatically shorter lead times. In addition, because the factory is essentially bootstrapping itself financially, management is worried about the possibility of bankruptcy. To minimize this threat, management policy dictates that new equipment cannot be purchased if the remaining cash balance would be insufficient to purchase at least one order quantity’ worth of raw materials. s Operations Policies at Littlefield LT uses...

Words: 923 - Pages: 4

Premium Essay

Littlefield

...Background In early January 2006, Littlefield Technologies (LT) opened its first and only factory to produce its newly developed Digital Satellite System (DSS) receivers. Littlefield Technologies mainly sells to retailers and small manufacturers using the DSS’s in more complex products. Littlefield Technologies charges a premium and competes by promising to ship a receiver within 24 hours of receiving the order, or the customer will receive a rebate based on the delay. The product lifetime of many high-tech electronic products is short, and the DSS receiver is no exception. LT managers have decided that, after 268 days of operation, the plant will cease producing the DSS receiver, retool the factory, and sell any remaining inventories. As this is a short life-cycle product, managers expect that demand during the 268 day period will grow as customers discover the product, eventually level out, and then decline. In the initial months, demand is expected to grow at a roughly linear rate. Demand is then expected to stabilize. Eventually, demand should begin to decline at a roughly linear rate. Although orders arrive randomly to LT, management expects that, on average, demand will follow the trends outlined above. Management’s main concern is managing the capacity of the factory in response to the complex demand pattern. Delays resulting from insufficient capacity undermine LT’s promised lead times and ultimately force LT to turn away orders. In particular, if an order’s...

Words: 254 - Pages: 2

Premium Essay

Littlefield

...Littlefield Technologies Assignment 5 PM on February 22 . Starting at 5 PM on Wednesday, February 27, the simulation will begin The game will end at 9 PM on Sunday, March 3. Accessing your factory http://quick.responsive.net/lt/toronto3/entry.html Littlefield Technologies’’ Operations board stuffing testing tuning Operations Policies at Littlefield Purchasing Supplies Processing in Batches Contract Pricing Borrowing from the Bank Cash Balance The winning team is the team with the most cash at the end of the game (cash on hand less debt). Current State of the System and Your Assignment At the end of day 350, the factory will shut down and your final cash position will be determined. Starting at 5 PM on Wednesday, February 27, the simulation will begin The game will end at 9 PM on Sunday, March 3. PLEASE DO NOT WAIT UNTIL THE FINAL SECONDS TO MAKE YOUR CHANGES. SOMETIMES THEY TAKE A FEW MINUTES TO BE PROCESSED. Written Assignment: Analysis of Game 2 of Littlefield Technologies Simulation Due March 14, 8:30 am in eDropbox Your group is going to be evaluated in part on your success in the game and in part on how clear, well structured and thorough your write-up is. The write-up only covers the second round, played from February 27 through March 3. It should not discuss the first round. Your write-up should address the following points: • A brief description of what actions you chose and when. Not a full list of every action, but the major...

Words: 637 - Pages: 3

Free Essay

Littlefield

...B6016 Managing Business Operations Report on Littlefield Technologies Simulation Exercise By Group 4: Anise Tan Qing Ye Aneel Gautam Chu Kar Hwa, Leonard Tan Kok Wei Ranking Reflecting on the simulation exercise, we have made both correct and incorrect decisions. Nevertheless, although we ranked 4th (Exhibit 1: OVERALL TEAM STANDING), we believe we gained a deeper understanding of queuing theory and have obtained invaluable experience from this exercise. Rank | Team | Cash Balance ($) | 1 | bigmoney1 | 1,346,320 | 2 | techwizard | 1,312,368 | 3 | makebigmoney | 1,141,686 | 4 | beaters123 | 895,405 | 5 | donothing | 588,054 | 6 | mas001 | 472,296 | Exhibit 1 : OVERALL TEAM STANDING Decisions Made A summary of the rationale behind the key decisions made would perhaps best explain the results we achieved. . Decision 1 Day | Parameter | Value | 54 | station 1 machine count | 2 | When the exercise started, we decided that when the lead time hit 1 day, we would buy one station 1 machine based on our analysis that station 1 takes the longest time which is 0.221 hrs simulation time per batch. (Exhibit 2: Average time per batch of each station). As day 7 and day 8 have 0 job arrivals, we used day 1-6 figures to calculate the average time for each station to process 1 batch of job arrivals. Base on the average time taken to process 1 batch of job arrivals, we were able to figure out how many...

Words: 1324 - Pages: 6

Premium Essay

Littlefield Simulation

...ev ev Littlefield Simulation Report: Team A Ending Cash Balance: $1,915,226 (6th Place) Return On Investment: 549% ROI=Final Cash-Day 50 Cash-PP&E ExpenditurePP&E Expenditure→ 1,915,226-97,649-280,000280,000=549% Analysis of the First 50 Days The Littlefield Technologies management group hired Team A consulting firm to help analyze and improve the operational efficiency of their Digital Satellite Systems receivers manufacturing facility. Upon the preliminary meeting with Littlefield management, Team A were presented with all pertinent data from the first 50 days of operations within the facility in order for the firm to analyze and develop an operational strategy to increase Littlefield’s throughput and ultimately profits. Figure 1: Day 1-50 Demand and Linear Regression Model Figure 1: Day 1-50 Demand and Linear Regression Model With little time to waste, Team A began by analyzing demand over the first 50 days of operations in order to create a linear regression model to predict demand into the future in order to make critical operational decisions; refer to Figure 1. In Littlefield, total operational costs are comprised of raw material costs, ordering costs and holding costs. Raw material costs are fixed, therefore the only way to improve the facility’s financial performance without changing contracts is to reduce ordering and holding costs. As such, the first decision to be made involved inventory management and raw material ordering. Inventory management...

Words: 2674 - Pages: 11

Premium Essay

Reort on Littlefield

...INTRODUCTION The managing of our factory at Littlefield Technologies thought us Production and Operations Management techniques outside the classroom. We experienced live examples of forecasting and capacity management as we moved along the game. Throughout the game our strategy was to apply the topic leant in Productions and Operation Management Class to balance our overall operations. The game started off by us exploring our factory and ascertaining what were the do’s and don’ts. The initial goal of the goal was to correlate the Re Order Point with the Customer Order Queue. To forecast Demand we used Regression analysis. We looked and analyzed the Capacity of each station and the Utilization of same. The team ascertained our job completion and our Lead Time. Our strategy throughout the stimulation was to balance our work station and reduce the bottleneck. PRIOR TO THE GAME The team consulted and decided on the name of the team that would best suit the team. With much anticipation we reviewed all the literate that was provided subsequently to assist us in decision making at Littlefield Technologies. DAY 1 (8 OCTOBER 3013) Data was extracted from “plot job arrival “and analyzed. The information was used to calculate the forecast demand using the regression analysis. The next step was to calculate the Economic Order Point (EOP) and Re Order Point (ROP) was also calculated. A discussion ensued and we decided to monitor our revenue on this day. The strategy yield a...

Words: 1090 - Pages: 5

Premium Essay

Littlefield Simulations

...Thundercats Team Contract November 4th, 2014 Mission The mission of our team is to complete all aspects of the team assignment on time and to the full requirements set forth by Professor McNickle. Project We will work to the best of our abilities on the Littlefield simulation and will work as a team to make agreed upon manufacturing changes as often as is deemed needed. In addition, we will research and tour Darigold Inc. to evaluate their operations, providing analysis and recommended changes where we deem applicable. Our goal is to function as a reciprocal interdependent team, using each members’ varied skills and time to complete tasks both well and on time. To ensure we are focused and accomplish these set goals, the following guidelines...

Words: 395 - Pages: 2

Premium Essay

Littlefield Technologies

...Running head: Capacity Management Capacity Management at Littlefield Technologies Anteaus Rezba Leena Alex Marcio de Godoy Pennsylvania State University Initial Strategy Definition Our strategy was to keep track of each machine’s capacity and the order queue. Initially, we tried not to spend much money right away with adding new machines because we were earning interest on cash stock. However, once the initial 50 days data became available, we used forecasting analyses to predict demand and machine capacity. Our goal was to buy additional machines whenever a station reached about 80% of capacity. Day 50 Once the initial first 50 days of data became available, we plotted the data against different forecasting methods: Moving average, weighted moving average, exponential smoothing, exponential smoothing with trend, and exponential smoothing with trend and season. Out of these five options, exponential smoothing with trend displayed the best values of MSE (2.3), MAD (1.17), and MAPE (48%). In addition, the data clearly showedprovided noted that the demand was going to follow an increasing trend for the initial 150 days at least. Following, we used regression analysis to forecast demand and machine productivity for the remaining of the simulation. As explained on in chapter 124, we used the following formula: y = a + b*x. A linear regression of the day 50 data resulted in the data shown on Table 1 (attached)below. | |Station ...

Words: 671 - Pages: 3

Premium Essay

Mount Vernon Ladies Association History

...The Mount Vernon Ladies’ Association (MVLA) is the private, non-profit organization that has owned and operated George Washington’s Mount Vernon since 1860. Founded by Ann Pamela Cunningham of South Carolina, the Association is the oldest national historic preservation organization in the United States. In 1853, Miss Cunningham’s mother observed the dilapidated Mount Vernon Mansion from a boat in the Potomac River. She was horrified at the sight of Washington’s once grand house covered with peeling paint and overgrown weeds. Its famous piazza was nearing collapse, propped up by old sailing masts. “I was painfully distressed,” she later wrote to her daughter, “at the ruin and desolation of the home of Washington, and the thought passed through my mind: Why was it that the women of his country did not try to keep it in repair, if the men could not do it?” Inspired by her mother’s conviction, Ann Pamela Cunningham launched a campaign to raise the funds necessary to purchase and preserve the home of Washington. The Association she founded in 1853 included a network of supporters working under a council of 13 women from across the nation. They appealed to the American people to raise $200,000 in an unprecedented grassroots fundraising campaign. Five years later the Association purchased the Mansion, outbuildings and 200 surrounding acres from John Augustine Washington III, a great-grandnephew of George Washington. Following the success of the fundraising campaign, Miss Cunningham,...

Words: 484 - Pages: 2

Free Essay

Littlefield Game Report

...LITTLEFIELD CAPACITY GAME REPORT When we started to play game, we waited a long time to play game because there are several stations for buying machines and these machines have different processes. Thus, we did not know which machine is suitable for us; therefore, we waited 95 days to buy a new machine. First of all, we purchased a second machine from Station 1; however, we could not think Station 1 would be a bottleneck process. Hence, we wasted our cash and our revenue decreased from $1,000,000 to $120,339, which was a bad result for us. Moreover, we bought two machines from Station 2 because; it would be better idea to increase our revenue more than Station 1. Furthermore, we thought that buying machines from Station 3 was unnecessary because of the utilization’ in that station. In addition to this factor, we thought that buying several machines from different stations would decrease our revenue in the following days. Before buying machines from two main stations, we were in good position among our competitors. After we purchased machines from Station 1 and Station 2, our revenue and cash balance started to decrease due to the variable costs of buying kits. In addition, we were placed 17th position in overall team standing. Within the framework of all these, our cash balance was $120,339 at the end of the game, since we could not sell those machines and our result was not quite good as our competitors’ positions. We could have used different strategies for the Littlefield...

Words: 357 - Pages: 2

Premium Essay

Littlefield Simulation Analysis

...Littlefield Initial Strategy When the simulation first started we made a couple of adjustments and monitored the performance of the factory for the first few days. Initially we set the lot size to 3x20, attempting to take advantage of what we had learned from the goal about reducing the lead-time and WIP. We also changed the priority of station 2 from FIFO to step 4. After viewing the queues and the capacity utilization at each station and finding all measures to be relatively low, we decided that we could easily move to contract 3 immediately. Except for one night early on in the simulation where we reduced it to contract 2 because we wouldn’t be able to monitor the factory for demand spikes, we operated on contract 3 almost the entire time. This proved to be the most beneficial contract as long as we made sure that we had the machines necessary to accommodate the increasing demand through day 150. Machine Purchases The first time our revenues dropped at all, we found that the capacity utilization at station 2 was much higher than at any of the other stations. So we purchased a machine at station 2 first. Station 2 never required another machine throughout the simulation. After all of our other purchases, utilization capacity and queuing at station 2 were still very manageable. As demand began to rise we saw that capacity utilization was now highest at station 1. We nearly bought a machine there, but this would have been a mistake. A huge spike in demand...

Words: 1327 - Pages: 6