...Executive Summary In November of 1989, the City of Denver began the construction phase of its new airport with the expected completion in Fall of 1993. This project was received with political and public support and promised to aid in preventing an economic free fall. The city used as many Denver area contractors and services as possible to keep their promise of increasing the economic benefits of the new airport. Due to construction beginning later that scheduled, the design-build approach was used, which led to a number of circumstances where partially constructed, or constructed areas had to be changed causing duplication of work, increased costs and delays. Due to lack of proper planning, and that the assumption that airlines would build their own baggage system, an airport wide baggage system was not included in the final plan for the airport. BAE, after already been contracted by United to build their baggage system, was approached and agreed to build an airport wide baggage system based on negotiated conditions. At this point the scheduling and construction of the project and baggage system was out of control. As BAE worked on building and installing the baggage system, the negotiated conditions were not met, leading to further delays. The city took action to filed a lawsuit against BAE penalizing them $12,000 a day for not finishing the baggage system, possibly BAE’s reputation around the world. I recommend that BAE propose a plan for this point in the...
Words: 2198 - Pages: 9
...Executive Summary BAE Automated systems was contracted by the United Airlines to build the baggage management for them at the Denver International Airport (DIA). The management team at DIA, looking at the response from other airlines towards the leasing of the own baggage systems, decided to build an integrated system for baggage management at DIA. The DIA approached BAE for the completion of this 195 million dollar project. After much deliberation on the project specifications and timelines, BAE decided to take up the project however they enforced many timelines and freeze dates to be strictly followed by the DIA. BAE highlighted the need for privileges such as unrestricted access and priority treatment which would be necessary for timely completion of the project. The project eventually ran into difficulties after the death of Slinger, the new point of contact between the BAE and the Denver government. Gail Edmond was not as autonomous as Slinger was and even though she tried her best to manage the situation. The issue snow balled into a situation where an external consultant was hired to assess the situation, from a German firm “Longplan”, and based on their recommendation the DIA decided to go ahead with the plan to construct a backup baggage management systems. They also decided to put the blame for the delay in the opening of the airport on BAE and issued a fine of $12,000 per day from the promised date of delivery and also the whole amount of development of the backup...
Words: 1509 - Pages: 7
...BAE Automated Systems Executive Summary This report concerns the automated baggage handling system which was built by BAE Automated systems. Faced with the need for greater airport capacity, the city of Denver elected to construct a new state- of- the- art airport that would cement Denver’s position as an air transportation hub. Covering a land area of 140km-squared, the airport was to be the largest in the United States and have the capacity to handle more than 50 million passengers annually. A mechanized baggage system was at the heart of the new Denver Airport, as for all major new airports. In the case of Denver, this was to be something unique: the “integrated Automated Baggage Handling System”, originally designed to distribute all baggage, including transfers- automatically between check-in, the aircraft and pick-up on arrival. The airport’s baggage handling system was a critical component in the plan. By automating baggage handling, aircraft turnaround time was to be reduced to as little as 30 minutes. Faster turnaround meant more efficient operations and was a cornerstone of the airports competitive advantage. Despite the good intentions, the plan rapidly dissolved as underestimation of the project’s complexity resulted in problems and public humiliation for everyone involved. Thanks mainly to problems with the baggage system, the airport’s opening was delayed by a full 16 months. Expenditure to maintain the empty airport and interest charges on construction...
Words: 2625 - Pages: 11
...Functionality Of Original BAE Design Problems and Solutions System Complexity Comparative Functionality Opening Delays Financial Hardship Summary Glossary References THE DENVER INTERNATIONAL AIRPORT AUTOMATED BAGGAGE HANDLING SYSTEM by Michael Schloh Computer Science Department School of Engineering California Polytechnic State University 1996 Date Submitted: February 16, 1996 Advisor: Daniel Stearns ABSTRACT This document discusses events at the new Denver International Airport that resulted in opening delays of the airport. The scope is limited to the automated baggage handling system, which was the primary source of failure warranting the airport's several opening delays. Analysis of the failing system is comprehensive. Research is conducted using a variety of sources. The final report is published on the worldwide web. CONTENTS Introduction 1 Reasons For Automation 2 Functionality Of Original BAE Design 3 Problems and Solutions 6 System Complexity 12 Comparative Functionality 14 Opening Delays 15 Financial Hardship 17 Summary 19 Glossary 20 References 21 INTRODUCTION This research concerns the automated baggage handling system which was built by BAE Automated Systems, Incorporated of Carrollton, Texas for the Denver International Airport. The analysis of this system provides an important topic of study. From the baggage system's failure, principles of computer systems were clarified and many lessons were learned or relearned by those involved in the BAE project. While there are...
Words: 12573 - Pages: 51
...Module 8 Session Project: Case Study BAE Automated Systems DIA Baggage-Handling Systems Table of Contents Topic Pages Executive Summary 3 Introduction 4-5 Issue Identification and Root Case Analysis 6-8 Alternatives and Options 9 Recommendations 10 Implementation Plan 11 Monitor & Control 12-13 Exhibits 14 Executive Summary Denver International Airport(DIA) project started in November 1989 it was a very large project. Implementing the automated baggage handling in the middle of the project made it even more complex. Denver after being behind schedule for 18 months the Airport finally opened in February 1995. Once completed the airport had 5 runaways an 88 gates. The baggage handling system of the airport was initially built for United Airlines whom insisted on the system in the earlier planning stages. Denver officials agreed the automated baggage system will be a great addition to the airport; however not just for United Airlines concourse but all concourses in the airport. Boeing Airport Equipment(BAE) was contracted for building the system by officials in Denver long after the construction on the airport began. When the airport opened it had both the automated, a back-up for the automated system and conventional baggage handling system in place. Unfortunately, the...
Words: 3154 - Pages: 13
...Running head: CASE REVIEW ANALYSIS OF THE DENVER INTERNATIONAL AIRPORT 1 Case Review Analysis of the Denver International Airport And Its Baggage Handling System Warner Sherman CASE REVIEW ANALYSIS OF THE DENVER INTERNATIONAL AIRPORT Table of Contents 2 Summary of Findings……………………………………………………………..………. 3 Background Information…………………………………………………….……............. 3 Problem Statement………………………………………………………………..…..…… 4 Analysis of Alternatives…………………………………………………………………… 4 Detailed Recommendations………………………………………………...……………... 5 Implementation and Evaluation…………………………………………………………… 6 References………………………………………………………………………………… 8 Appendix A.……………………………………………………………………………… 14 CASE REVIEW ANALYSIS OF THE DENVER INTERNATIONAL AIRPORT Summary of Findings 3 There has been considerable controversy documented through case study over the inadequacy of project and risk management structure associated with the Boeing Airport Equipment (BAE) automation design technology for a new baggage transport system at the Denver International Airport (DIA). Research background conducted by Kerzner (2011) under Case 23 revealed a documented tenyear history of this complex project with inherent risks. In another case study conducted by Montealegre, Keil, and Robinson (2000), a risk practice methodology was presented through “lessons learned” for improved implementation of the project’s risk management structure. Unfortunately, analogy comparisons for this type of project to incorporate past...
Words: 4143 - Pages: 17
...6. A hermeneutic analysis of the Denver International Airport Baggage Handling System Stasys Lukaitis, School of Information Systems, Deakin University Jacob Cybulski, School of Information Systems, Deakin University Abstract This paper attempts to demonstrate the principles of hermeneutics in an effort to understand factors affecting Information Systems (IS) projects. As hermeneutics provides a systematic method of interpreting text from multiple information sources, thus, Information Systems being prima facie defined and documented as text documents, are eminently suited for this mode of investigation. In this paper, we illustrate hermeneutics by analysing a sample case study document describing the well-known Denver International Airport (DIA) Automated Baggage Handling System project, which was extensively reported in the IS and management press and studied by Montealegre and his colleagues. As a result of the hermeneutic approach to the analysis of this document, a new ‘flexibility’ factor has been discovered to play an important, yet unreported, role in the DIA system demise. In the DIA case, the observed flexibility factor influenced the quality of the interaction between the actors, the prevailing environment and the information systems. Introduction Although there are several reports of information systems projects that have applied hermeneutics (Boland, 1991; Klein and Myers, 1999; Myers, 1994a), there are very few publications that explain the actual hermeneutic...
Words: 8291 - Pages: 34
...------------------------------------------------- BAE AUTOMATED BAGGAGE HANDLING REPORT DENVER INTERNATIONAL AIRPORT March 31, 2015 SCM GURPREET SINGH GILL March 31, 2015 SCM GURPREET SINGH GILL SCOPE The Denver Automatic Baggage system is to enhance the ground time efficiency. With the installment of automatic system the close out time will also get reduced and effectively decrease the work load of sorting and handling of baggage. Basically, this project introduce the project management to monitor and control few areas of knowledge such as scope, time, cost, quality, risk, communication, procurement, etc. EXECUTIVE SUMMARY The motive of this paper is to provide information and justify the implementation of automatic baggage system project in Denver International Airport and its failure or success. As we go through the case study we will analysis the activities of the project to consider and identify the aspects of the project which had led this project to failure. The recommendations from various elements had also been mentioned that should be taken place for the project to be a successful by using some of the project management measures and techniques. This project of Denver Automatic Baggage system project was analyzed with the point of view of project management and project approach. . ISSUE IDENTIFICATIONS As we gone through the case it has been noticed that there were many issues which took place during the initiation of the project throughout the process of implementation...
Words: 1147 - Pages: 5
...DENVER INTERNATIONAL AIRPORT AUTOMATED BAGGAGE HANDLING SYSTEM- PROJECT FAILURE ANALYSIS MSc Project Management Abstract The purpose of this study is to critically analyse the Denver International Airport Baggage Handling System project in order to detail the underlying reasons for the perceived failures in the project and to provide recommendations on how effective project management could have helped to avoid the problems the project encountered. A thorough analysis of the activities of the project from nature of project, contracting, design, construction, testing, stakeholder management, risk management, project controls, as well as the overall project leadership was carried out and failure causal factors were identified. A recommendation was also made on how the project should have been managed to ensure project success. The analysis viewed the project from both project management and project perspectives. Student: @00380661 25-Feb-14 Number of words: 2558 Table of Contents 1. 1.1 2. 2.1 Introduction ................................................................................................................. 2 Project Failure .......................................................................................................... 2 Discussion .................................................................................................................... 3 Failure Modes of the Project .............................................
Words: 4266 - Pages: 18
...1.0 Executive Summary Air Africa is an establishing private limited African budget airline based on passenger and cargo air transportation service linking the whole southern and northern African region. We provide cheap and fast routes service to destinations within Africa with the aim to ease pressure on the middle and low income earners and give them an experience of also flying than resorting to bus and trains. Air Africa has healthy projected sales by the third year hopefully the market entrant would have been accepted and plans to transport 40 000 people monthly. It was started to provide and add and ease the transportation gap in the regional market. From our research we saw that there are some African routes which are not served or underserved so our Airline has targeted such destinations. Our customers are business executives and women who are involved in round tables were they sell products in different parts of the region to enhance cultural diversification. School children travelling within Africa to further education will not have the hassle of travelling by bus for long distances for example from Zimbabwe to Namibia which is a two day journey by road and will cost around US dollars 100. Tourist travelers who will be on the search of the African passion and wild life, Africa is well known for the BIG 5 and also possessing some wonders of the world and that’s the most rewarding trip of Africa to meet its people. Air Africa will cut the gap between the...
Words: 7621 - Pages: 31
...Term paper on “The Airline Industry in Bangladesh : A management Colosseum” Faculty of Business Studies Bangladesh University of Professionals (BUP) The Airline Industry in Bangladesh : A management Colosseum Submitted to Major General (Retired ) Professor Alauddin M A Wadud,BP Course Instructor, Strategic Management Faculty of Business Studies Bangladesh University of Professionals (BUP) Submitted by 1. Priodarshine Auvi (EV1202026) 2. Mohammad Abdul Momin (EV1202027) 3. Kazi Kamrul Alam (EV1202029) 4. Mahbubur Rahman (Ev 1202028) 5. Maruf Hossain (Ev 1202014) LETTER OF TRANSMITAL Aug 27, 2013 Major General (Retired ) Professor Alauddin M A Wadud,BP Course Instructor Strategic Management Faculty of Business studies Bangladesh University of Professionals (BUP) Subject: Submission the term paper of “The Airline Industry in Bangladesh: A management Colosseum” Dear Sir, With due respect and humble to inform you that it is my pleasure to submit this report on“The Airline Industry in Bangladesh: A management Colosseum”. As your valuable suggestions and guidance, we have tried my best to prepare the report properly. There may be some shortcomings. We would be grateful if you consider those as excusable points and we like to thank you for your kind cooperation. Despite the limitations, we sincerely believe that you...
Words: 12444 - Pages: 50
...ePAPER ON “SUPPLY CHAIN MANAGEMENT IN AEROSPACE INDUSTRY” By- GROUP A3 PGPM1013-006- Anshul Maheshwari PGPM1013-043- Rashmi Ranjan Padhi PGPM1013-060- Vamsi Korlepara PGPM1013-082- Keshav Mishra TABLE OF CONTENTS 1. Cover Page………………………………………………………………………………………………….………….………………………………...1 2. Table of Contents………………………………………………………………………………………….…………………………………………..2 3. Executive Summary………………………………………………………………………………………….……………………………………… 3 4. Introduction……………………………………………………………………………………………………….………………………………………4 5. Aerospace Supply Chain Process………………………………………………………………………….…………………………………….5 6. Description of 5 stages………………………………………………………………………………………….…………………………………..6 7. Global Aerospace Supply Chain……………………………………………………………………………….…………………………………7 8. Sourcing in Aerospace Industry………………………………………………………………………………………………………………8-9 9. Need for Supply Chain in Aerospace Industry……………………………………………………………………………………..10-11 10. Major Aircraft components………………………………………………………………………………………………………………………12 11. Supply chain of Boeing components world wide………………………………………………………………………………………15 12. Criterion for adopting Supply Chain strategies…………………………………………………………………………………….17-18 13. Who does it?.......................................................................................................................................19-20 14. What technology enablers are used?........................................................................................
Words: 6892 - Pages: 28
...Current Market Outlook 2013 –2032 Current Market Outlook 2013 –2032 Outlook on a Page World regions Market growth rates 2012 to 2032 World economy (GDP) World regions Market value: $4,840 billion Share of fleet Delivery units 9% 13% 2% 6% 3.2% 100% 75% Number of airline passengers 4.1% 50% 25% Airline traffic (RPK) 5.0% 70% 0% 2012 Airplanes 20,310 2032 Airplanes 41,240 2013 to 2032 New airplanes 35,280 Cargo traffic (RTK) 5.0% • Regional jets • Single aisle • Small widebody • Medium widebody • Large widebody World regions Key indicators and new airplane markets Growth measures Regions World economy (GDP) % Airline traffic (RPK) % Cargo traffic (RTK) % Airplane fleet % Market size Deliveries Market value ($B) Average value ($M) Unit share % Value share % New airplane deliveries Large widebody Medium widebody Small widebody Single aisle Regional jets Total Market value (2012 $B, catalog prices) Large widebody Medium widebody Small widebody Single aisle Regional jets Total 2012 fleet Large widebody Medium widebody Small widebody Single aisle Regional jets Total 2032 fleet Large widebody Medium widebody Small widebody Single aisle Regional jets Total Asia Pacific 4.5 6.3 5.8 5.5 12,820 1,890 150 36 39 260 1,470 1,860 8,810 420 12,820 90 490 460 840 10 1,890 330 500 660 3,470 130 5,090 350 1,550 2,080 10,350 420 14,750 North America 2.5 2.7 3.8 1.5 7,250 810 110 21 17 30 390 760 5,000 1,070 7,250 10 130 170 460...
Words: 14996 - Pages: 60
...CONTENTS Section 1 - Industry Profile Overview Future Outlook European Industry Overview North America Overview Asia & Pacific Industry Overview India & Middle East Industry Overview Development of World Scheduled Air Traffic World Economic Growth and Airline Profits Rankings - Passenger services Rankings – Freight services Section 2 - British Airways Profile Overview Alliances LHR Air Transport Movements LGW Air Transport Movements Awards History Key Events (1987-2005) Board Members Leadership Team British Airways Management Team Employees Brands Departmental Analysis Section 3 - British Airways Fleet Aircraft Fleet Aircraft Delivery Schedule Mainline Fleet Profiles Regional Aircraft Fleet Maintenance Section 4 - British Airways Performance Summary Strategy Social and Environmental Performance Incentive Plans Summary Financial / Operating Statistics Principal Investments Shareholder Information Share Price History Section 5 - Global Partners Overview BA Connect Franchisees oneworld Aer Lingus American Airlines Cathay Pacific Finnair Iberia LanChile Qantas oneworld At A Glance Section 6 - Route Network British Airways Franchisees Section 7 - General Information Airport Three Letter Decodes Outside Advisors Abbreviations & Specialist Terms How To Contact Us 2 3 3 4 4 5 6 6 7 8 89 91 92 93 97 98 99 100 101 102 103 104 9 9 10 10 11 12 13 38 39 40 41 44 47 105 109 110 115 116 118 56 56 57 69 72 73 74 75 75 77 86 87 88 This document has been prepared solely...
Words: 59045 - Pages: 237
...Information Technology Strategic Plan My. X Strayer University Information Systems For Decision-Making CIS500 Dr. XYZ March 10, 2015 Abstract This article is focused on the format of a Business Plan strategy. It provides an overview of the company, financial, and other aspects of the business plan. The main components of business plan are: executive summary, company, products and services, market, strategy and implementation, financial plan, and financial plan. This article will show the plan for a successful corporate finance strategy, corporate finance and strategy functions that will work together and illustrate how to create shareholder value. Keywords: Writing Business Plans, SWOT analysis, Strategy plans, financial plans, sample business plans Introduction Many companies are using mobile (tablets, smartphones, and blackberries) technologies to enhance their customer service experience and internal job satisfaction for their employees. Companies like Delta Airlines, PayPal, a medical company, and a software security company, has shown that using mobile/wireless technologies are reaping its benefits. They’ve also have shown that they are in touch with social media platform and engaged customers to increase their understanding of what is needed to provide better products and services. “Indeed, many good business ideas have flopped before getting off the ground because they were not thought through fully” (Tusin, J, 2006, p. 226). A business plan enables...
Words: 3765 - Pages: 16