...Table of Contents Part 1 1) The network diagram 2) Gantt chart 3) The Effect on the duration of the whole project. 4) The purpose of Network diagrams. Part 2 1) The Management Report-Jones LTD 2) Appendix 3) Reference PART 1 1) Draw the network diagram (use activity on the node). (8 marks) Please refer to the appendix. 2) If the project starts on the Monday 6 September 2010 , what is the earliest date it can be completed using a 5 day working week? Assume no other holidays (explain how you calculated the figure). (4 marks) . If the project needs to start on 6th September and it has a constraint using only 5 days This shows that in each week 2 days needs to be cancelled. The earliest date which the project can be completed is 22nd of September as there are no calculation formula so we will use the Gantt chat Please refer to appendix for the diagram 3) If the following happened what would be the effect on the duration of the whole project? Explain the reasons. (6 marks) a) A 1 day delay during activity C. There wont be any delay on activity C as Activity B has more day than C so even if the C is delayed by one day There wont be any problems in the project. b) Activity G is delayed 1 day. There wont be any delay on the activity G as...
Words: 2555 - Pages: 11
...goal for this project - at the right time and scope. All these elements are interrelated. Each must be managed effectively. All must be managed together and carefully integrated together in order to be a success. In this scenario, the new crisis emerged by having slashed almost ¾ of the original budget and reduced the initial plan budget from $1.2 million down to $280.000. In the light of this new information, the budget has created a tough road ahead to carry on this project, but as a successful manager, one has got to “make it work”. Resources – People, equipment and material required. The new plan will require the manager to move around the resources available and regroup people. Time – Task durations, dependencies, and critical path. A new lay out plan to project a new time schedule for a newly slashed budget. Money – Costs, contingencies, profit (if applicable). New budget has been reduced from original $1.2 million down to $280.000. Options include finding some donors to carry on the initial plan or reduce the size of the entire plan? Decision, decision, decision. Scope – Project size, goals, objectives and requirements. New goal and priority. Question 5 – New Work Breakdown Structure (WBS) using the new budgeting parameters which slash almost ¼ of the original budget....
Words: 2402 - Pages: 10
...Welcome to Week 1! Project Scope Definition and WBS In this course, we will explore project cost and schedule control! The focus of this week is developing the scope and the work breakdown structure (WBS). We will use the WBS to specifically detail the tasks required to complete any project. The scope is the starting document of a project. It defines the project. The WBS is created from the scope and is the basis on which several other project documents, such as the budget and schedule, will be derived from. Because the WBS is one of the foundations to our planning effort, it is critical to know and understand this tool. Shortcomings in the scope or WBS will translate to the rest of our planning documents resulting in real failures during project execution to attain goals in scope, cost, and schedule. It is, therefore, of primary importance that the scope and WBS are inclusive and detailed. Just remember that as a project manager, your family comes first but the project scope and WBS are not far behind. Introduction Cost and schedule form two sides of the iron triangle of project management with the third side being the collection of scope, quality, and performance. This makes cost and schedule paramount concerns to a project manager. Cost and schedule control on a project are vital to a successful project. As you know, this course is named Project Schedule and Cost Control, which may imply that the project is underway and it's time to go to work. However, the process...
Words: 14442 - Pages: 58
...COST AND VALUE MANAGEMENT IN PROJECTS Ray R. Venkataraman and Jeffrey K. Pinto John Wiley & Sons, Inc. This book is printed on acid-free paper. Copyright 2008 by John Wiley & Sons, Inc. All rights reserved. Published by John Wiley & Sons, Inc., Hoboken, New Jersey. Published simultaneously in Canada. No part of this publication may be reproduced, stored in a retrieval system, or transmitted in any form or by any means, electronic, mechanical, photocopying, recording, scanning, or otherwise, except as permitted under Section 107 or 108 of the 1976 United States Copyright Act, without either the prior written permission of the Publisher, or authorization through payment of the appropriate per-copy fee to the Copyright Clearance Center, Inc., 222 Rosewood Drive, Danvers, MA 01923, 978-750-8400, fax 978-646-8600, or on the web at www.copyright.com. Requests to the Publisher for permission should be addressed to the Permissions Department, John Wiley & Sons, Inc., 111 River Street, Hoboken, NJ 07030, (201) 748-6011, fax (201) 748-6008, or online at http://www.wiley.com/go/permissions. Limit of Liability/Disclaimer of Warranty: While the publisher and author have used their best efforts in preparing this book, they make no representations or warranties with respect to the accuracy or completeness of the contents of this book and specifically disclaim any implied warranties of merchantability or fitness for a particular purpose. No warranty may be created...
Words: 94122 - Pages: 377
...EXECUTIVE SUMMARY Parks Corporation is a company that concentrated mainly on R&D business, doing projects for the Department of Defense. Parks Corporation has changed it’s focus over the years from predominantely R&D business to a low-cost production facility. The recession resulted in the company retrenching a number of employees, the staff compliment going from 6700 to 2200. In 1975, the corporate strategy changed again with the upturn of DoD spending. Parks began to beef up it’s R&D engineering staff. Owing to the salaries that Parks was offering their access to experienced engineers was limited so they opted to employing mainly young inexperienced engineers, straight out of college, like Gary Anderson. Gary was an outstanding production engineer and was promoted to senior scientist responsible for all R&D acitivities performed in the Mechanical Engineering department. In January 1978, Parks Corporation decided to bid for Phase I on the Blue Spider Project, with Lord Industries as the prime contractor for the Army’s Spartan Program. The project was to improve structural capabilities and the age life of the short range tactical missile, which was exhibiting fatigue failure after 6 years in the field. The criteria for a subcontractor was not only a low bid, but technical expertise and management performance. Parks Corporation felt that they had a distinct advantage over most competitors, as they had worked on other successful projects for Lord Industries. From the...
Words: 6399 - Pages: 26
...Principles of Project Management Course Outline Volume I About the Microsoft Project Screens .........................................................................iv Segment 1. The Background of Project Management (Includes PMBOK® Guide Chapter 1 & 2) ....................................................................................................... 1 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 1.9 1.10 Introductions, course materials, housekeeping & homework Definition, examples and characteristics of projects About Project Management Institute & other PM organizations Projects and emerging industries Programs & portfolios and project management office Environmental enterprise factors and organizational process assets Project & product life cycles Stakeholders Organizational structures & influences Segment 1 questions......................................................................... 22 Segment 2. The Gospel According to PMBOK® Guide (Includes PMBOK® Guide Chapter 3) ........................................................................................................... 27 2.1 2.2 2.3 2.4 2.5 2.6 2.7 2.8 3.1 PMBOK® Guide Organization Initiation processes Planning processes Execution processes Monitoring & controlling processes Closing processes Course Guide Exercise: Memorize the process matrix ............................................... 46 Project Assessment 3.1.1 Benefit Measurement Methods 3.1.1.1 Life Cycle Costing & Net Present Value 3.1.1.2 Internal Rate of Return...
Words: 67153 - Pages: 269
...Project Management Achieving Competitive Advantage Chapter One • Introduction: – Why Project Management? What is a Project • Two definitions of project: – A project is a unique venture with a beginning and end, conducted by people to meet established goals within parameters of cost, schedule, and quality – Projects are goal-oriented, involve the coordinated undertaking of interrelated activities, are of finite duration, and are all, to a degree, unique • Difference between process and project – Process refers to ongoing, day-to-day activities in which an organization engages while producing goods or services; process uses existing system, properties, and capabilities in a continuous, fairly repetitive manner – Projects take place outside the normal, process-oriented world of the firm What is a Project (con’t) • A project can be considered to be any series of activities or tasks that: – Have a specific objective to be completed within certain specifications – Have defined start and end date – Have funding limits – Consume human and nonhuman resources – Are multifunctional What is a Project (con’t) • Various elements of projects: – Projects are complex, one-time process: a project arises for a specific purpose or to meet a stated goal; they are complex because they typically require the coordinated inputs of numerous members of the organization – Projects are limited by budget, schedule, and resources: project work requires that members work with limited...
Words: 17331 - Pages: 70
...RISK MANAGEMENT GUIDE FOR DOD ACQUISITION Sixth Edition (Version 1.0) [pic] AUGUST, 2006 Department of Defense Preface The Department of Defense (DoD) recognizes that risk management is critical to acquisition program success (see the Defense Acquisition Guidebook (DAG), Section 11.4). The purpose of addressing risk on programs is to help ensure program cost, schedule, and performance objectives are achieved at every stage in the life cycle and to communicate to all stakeholders the process for uncovering, determining the scope of, and managing program uncertainties. Since risk can be associated with all aspects of a program, it is important to recognize that risk identification is part of the job of everyone and not just the program manager or systems engineer. That includes the test manager, financial manager, contracting officer, logistician, and every other team member. The purpose of this guide is to assist DoD and contractor Program Managers (PMs), program offices and Integrated Product Teams (IPTs) in effectively managing program risks during the entire acquisition process, including sustainment. This guide contains baseline information and explanations for a well-structured risk management program. The management concepts and ideas presented here encourage the use of risk-based management practices and suggest a process to address program risks without prescribing specific methods or tools....
Words: 12584 - Pages: 51
...N14C31 Managing Projects 01.10.2012 Lecture 1: Introduction to Project Management & WBS Dr Christos Braziotis Christos.Braziotis@nottingham.ac.uk Module Convenor Dr Christos Braziotis Lecturer in Supply Chain and Operations Management Nottingham University Business School, Room B37, South Building Tel: 115 9514026 Email: Christos.Braziotis@nottingham.ac.uk N14C31 – Managing Projects © Christos Braziotis, 2012-2013 – Nottingham University Business School Slide 2 Agenda • Introduction to the Module: – Aims – Resources – Assessment • Introduction to Project Management: – Aspects to consider in Project Management – Work Breakdown Structure N14C31 – Managing Projects © Christos Braziotis, 2012-2013 – Nottingham University Business School Slide 3 Introduction to Project Management N14C31 – Managing Projects © Christos Braziotis, 2012-2013 – Nottingham University Business School Slide 4 • The word “Project” is frequently used N14C31 – Managing Projects © Christos Braziotis, 2012-2013 – Nottingham University Business School Slide 5 • The word “Project” is frequently used N14C31 – Managing Projects © Christos Braziotis, 2012-2013 – Nottingham University Business School Slide 6 What is a Project? – Definitions • A temporary endeavor undertaken to create a unique product or service (US Project Management Institute) • Unique process, consisting of a set of coordinated and controlled activities with start and...
Words: 3914 - Pages: 16
...and performance specifications designed to meet customer needs. Like most organizational effort, the major goal of a project is to satisfy a customer’s need,” (Gray & Larson, 2006, p. 4). This paper will identify the issues and opportunities faced by RPD as well as provide instructions for successful project execution. It will dictate the impact that proper project planning, budgeting, risk evaluation, resource management, and the utilization of the proper project management tools will have on the success of the eRPD project. Restructuring the focus of the project committee and the management team to realign its activities with the long term objectives of RPD will be of great benefit to the parties involved. By identifying and executing the major characteristics of a project RPD will be able to create a precise vision of what a project consists of. Some of the characteristics of a project that will be identified throughout this paper are the abilities to “establish an objective, define a life span with a beginning and an end, the involvement of several departments and professionals, completing new tasks, and implementing...
Words: 6503 - Pages: 27
...FACULTY OF MEDIA, INFORMATION & COMMUNICATIONS TECHNOLOGY BACHELOR OF SCIENCE IN INFORMATION TECHNOLOGY IT PROJECT MANAGEMENT YEAR 3 SEMESTER 1 1 Registered with the Department of Higher Education as a Private Higher Education Institution under the Higher Education Act, 1997. Registration Certificate No. 2000/HE07/008 FACULTY OF MEDIA INFORMATION AND COMMUNICATION TECHNOLOGY QUALIFICATION TITLE BSc INFORMATION TECHNOLOGY LEARNER GUIDE MODULE: IT PROJECT MANAGEMENT (1ST SEMESTER) PREPARED ON BEHALF OF PC TRAINING & BUSINESS COLLEGE (PTY) LTD AUTHOR: Miss. Nkosikhona Msweli EDITOR: Mr. Sahil Sahue FACULTY HEAD: Isaka Reddy Copyright © 2015 PC Training & Business College (Pty) Ltd Registration Number: 2000/000757/07 All rights reserved; no part of this publication may be reproduced in any form or by any means, including photocopying machines, without the written permission of the Institution. TABLE OF CONTENTS TOPICS SECTION A: PREFACE PAGE NO. 4-11 1. Welcome 4 2. Title of Modules 4 3. Purpose of Module 5 2 4. Learning Outcomes 5 5. Method of Study 5 6. Lectures and Tutorials 5 7. Notices 5 8. Prescribed & Recommended Material 5 9. Assessment & Key Concepts in Assignments and Examinations 6 10. Specimen Assignment Cover Sheet 9 11. Work Readiness Programme 10 12. Work Integrated Learning (WIL) 10 SECTION B: IT PROJECT MANAGEMENT (2ND SEMESTER) 12-101 1. Introduction to Software Project Management 15-20 2. Traditional Project Management ...
Words: 39099 - Pages: 157
...Chapter 1: * A 1995 Standish Group study (CHAOS) found that only 16.2% of IT projects were successful in meeting scope, time, and cost goals; over 31% of IT projects were canceled before completion Advantages of Using Formal Project Management: * Better control of financial, physical, and human resources * Improved customer relations * Shorter development times * Lower costs * Higher quality and increased reliability * Higher profit margins * Improved productivity * Better internal coordination * Higher worker morale What is project? A project is “a temporary endeavor undertaken to create a unique product, service, or result” Project Attributes: A project: * has a unique purpose * is temporary * is developed using progressive elaboration * requires resources, often from various areas * should have a primary customer or sponsor * The project sponsor usually provides the direction and funding for the project * involves uncertainty Program: group of related projects managed in a coordinated way to obtain benefits and control not available from managing them individually The triple constraint of project management: Scope, cost & time. Project management: is “the application of knowledge, skills, tools and techniques to project activities to meet project requirements” 10 knowledge areas (project management framework): 1. Scope management 2. Time management 3. Cost man. 4...
Words: 5230 - Pages: 21
...of Contents Task 1 4 What are the core principles/characteristics of a project and why are they important to Project Managers? 4 The core principles/characteristics of a project: 4 The importance of projects’ core principles/characteristics to Project Manger 4 How would you define the scope of a project, what benefits would this give to the successful completion of the project? 5 Using the information below, plot out a full project Gantt chart and identify the critical path? How many days does it take to complete the project? What are the benefits of using a Gantt chart? 6 Cost management is important for running successful projects. Identify four of the common sources of project costs. 7 Risk Management is an intrinsic part of project management, what would you include in your Risk Management plan for managing the risks in a project. 7 What quality methods (project evaluation, monitoring and control) would you introduce to ensure projects are completed successfully? 8 Task 2 9 Introduction 9 Project’s Scope 9 Project’s Objective 9 Work Breakdown Structure (WBS) 10 Schedule planning 10 Gantt chart: 10 Network diagram: 11 Cost planning 11 Human resource planning: 11 Cost baseline: 13 Project manager and team 13 Project team: 13 Project manager: 14 Project control 15 Time management 15 Cost management...
Words: 4148 - Pages: 17
...Edition ISBN 0-619-159847 Course Technology MIS Series Companion Web Site: www.course.com/mis/schwalbe Kathy Schwalbe, Ph.D., PMP Table of Contents CHAPTER 1 1 CHAPTER 2 3 CHAPTER 3 7 CHAPTER 4 9 CHAPTER 5 13 CHAPTER 6 18 CHAPTER 7 22 CHAPTER 8 27 CHAPTER 9 31 CHAPTER 10 35 CHAPTER 11 38 CHAPTER 12 41 APPENDIX A 44 APPENDIX B 49 APPENDIX C 51 List of solution files available with the Instructor Resource material: CHAPTER 1 Introduction to Project Management Discussion Questions 1. Why is there a new or renewed interest in the field of project management? More and more projects are being done by a variety of organizations. The projects are more complex and often involve the use of new technologies. Organizations are struggling to find better ways to manage their projects. 2. What is a project? How is it different from what most people do in their day-to-day jobs? A project is “a temporary endeavor undertaken to create a unique product or service” (PMBOK( Guide, 2000, p. 4). Projects are different from day-to-day activities primarily because they have focused goals and definite beginning and ending dates. 3. What is project management? Briefly describe the project management framework. Project management is “the application of knowledge, skills, tools, and techniques to project activities in order to meet project requirements” (PMBOK( Guide, 2000, p. 6). The project management framework graphically shows the process of beginning with stakeholders’...
Words: 31210 - Pages: 125
...evaluation, and presentation. Lately, there has been little success of projects. Pundits believe that haphazard planning, inadequate implementation, relaxed control, and lack of project evaluation bring this about. This paper shows how the project manager that was assigned this task went about these procedures to record major success in major fronts. 1.0 Introduction Project management is quite a popular topic in the world of management today. This is occasioned by the fact that it is the center of growth in business. A company will have an ongoing project at any one time. Hence, the skills associated with this subject come in handy. In this paper, we analyze the implementation and evaluation of Golden Source International Ltd’s launch of a new product. Borrowing from project management principles, the author outlines a number of procedures...
Words: 3345 - Pages: 14