Free Essay

Engineering

In:

Submitted By 915nik915
Words 4499
Pages 18
Executive Summary
This report provides an analysis and evaluation of a fleet of trucks and loaders to meet the production requirements of an open pit mine. The method of analysis was first to determine the cycle time for each truck which led to calculating the amount of each dump truck necessary to meet the waste removal requirement of 70 Mt/pa. Secondly, an expected cost for ten years was conducted on each Komatsu dump truck and cross analysed to determine the most cost efficient option. It was found that the Komatsu 930E-4 had the least expected cost over the ten years. Then cross analysing, each loader with the Komatsu 930E-4 truck, it was determined that the Hitachi EX8000-6 was the most efficient loader for a fleet of Komatsu 930E-4 trucks. Once these were completed, a full haul truck cycle time and expected cost analysis for each year was calculated. It revealed that thirty four Komatsu 930E-4 dump trucks were needed for a single Hitachi EX8000-6 loader. However, the above analysis was limited by the fact that it didn’t account for truck and loader break downs. By taking into account a 10% threshold on the number of trucks and loaders needed it gave some costs accounting for time where not all trucks are operational. This analysis yielded that a fleet of thirty seven Komatsu 930E-4 dump trucks and two Hitachi EX8000-6 loaders would be best suited for the Kangaroo Mining Corporation. The expected costs for both loaders and dump trucks were calculated (refer to table 1.9) and showed that the average expected cost per year of hauling and loading would be $142 613 457/pa and $11 869 288/pa respectively. Furthermore, the average expected cost per tonne of hauling and loading would be $2.04/t and $0.17/t respectively.

Table of Contents

Executive Summary 2 Introduction 4 Parameters 4 Assumptions and Calculations 7 Analysis 10 Conclusion 11 Appendix 12 References 22

Introduction
This short report will discuss the best fleet choice for loaders and haul trucks to meet the waste removal target for an open pit mine of Kangaroo Mining Corporation. Furthermore, it will provide an insight to the cost of loading and hauling waste per year as well as the cost per tonne. It will demonstrate an analysis of expected costs per year for the ten year life cycle of the project and how the sensitivity of fuel cost will affect the overall expected costs if it changes.

Parameters
The Kangaroo Mining Corporation provided the following data: Data Received | Operator Salary (plus 9.5% Super) | $100 000 | $9 500 (Super) | Working roster | 14 days on, 7 days off | Rate of Waste | 70 Mt/pa | Powder Factor | 0.6 kg/m3 | Explosive cost | $1 000/t | Swell Factor | 25% | Road Gradient | 10% | Road Maintenance | Haul road will be well maintained, and watered daily to reduce dust | Waste Rock | Granite (UCS 100 MPa) | Fuel Cost (± 10%) | $1.40/L | $1.26/L | $1.54/L | Loader Lubrication cost | 10% of Maintenance cost for loaders | Truck Lubrication cost | 7.5% of Maintenance cost for trucks |

Figure 1: Planned open pit design for Kangaroo Mining Corporation
Figure 1: Planned open pit design for Kangaroo Mining Corporation

The following Hitachi loader specifications are parameters in calculations and can be justified by referring to table 1.1 (Hitachi Construction Machinery 2004). Hitachi Loaders | Model | Purchase Cost ($) | Maintenance Parts And Labour ($/hr) | Travel Speed (km/hr) | Fuel Capacity (L) | Engine Power (kW) | EX1200-5D | 1000000 | 120 | 3 | 1400 | 567 | EX1200-6 | 1000000 | 120 | 3 | 1470 | 567 | EX1900-6 | 2000000 | 150 | 2.5 | 4140 | 810 | EX2500-6 | 4000000 | 180 | 2 | 5000 | 1044 | EX2600-6 | 5000000 | 190 | 2 | 5300 | 1119 | EX3600-6 | 7000000 | 210 | 2 | 7450 | 1450 | EX5500-6 | 9000000 | 230 | 2 | 11300 | 2088 | EX5600-6 | 9000000 | 230 | 2 | 11300 | 2238 | EX8000-6 | 11000000 | 280 | 2 | 14900 | 2900 |

Hitachi Loaders | Model | Loading Capacity (m3) | Loading Capacity (tonnes) | EX1200-5D | 6.5 | 11.7 | EX1200-6 | 6.5 | 11.7 | EX1900-6 | 12 | 21.6 | EX2500-6 | 15 | 27 | EX2600-6 | 15 | 27 | EX3600-6 | 21 | 37.8 | EX5500-6 | 27 | 43.3 | EX5600-6 | 29 | 46.4 | EX8000-6 | 40 | 64 |

The following Kotmatsu trucks specifications are parameters in calculations and can be justified by referring to table 1.2 (Komatsu Australia n.d). Komatsu Trucks | Model | Purchase Cost ($) | Maintenance Parts and Labour ($/hr) | Travel Speed (km/h) | Fuel Capacity (L) | HD325-7 | 1000000 | 80 | 70 | 484 | HD405-7 | 2000000 | 90 | 70 | 780 | HD465-7E0 | 3000000 | 100 | 70 | 780 | HD785-7 | 3500000 | 100 | 65 | 1308 | HD1500-7 | 4000000 | 130 | 58 | 2120 | 730E 7 | 4500000 | 140 | 55.7 | 3217 | 730E 8 | 4500000 | 170 | 64.5 | 3217 | 830E 1AC | 5000000 | 190 | 64 | 4542 | 860E 1K | 5500000 | 210 | 64.5 | 4542 | 930E 4 | 6000000 | 220 | 64.5 | 4242 | 930E 4SE | 6500000 | 240 | 64.5 | 5300 | 960E 1 | 7000000 | 260 | 64.5 | 5300 | 960 2K | 7000000 | 260 | 64.5 | 5300 |

Komatsu Trucks | Model | Loading Capacity (m3) | Carrying Capacity (tonnes) | Tyres | Tyre Cost ($) | Engine Power (kW) | HD325-7 | 24 | 36.5 | 18.00 R33 | 2000 | 371 | HD405-7 | 40 | 63 | 24.00 R35 | 3500 | 371 | HD465-7E0 | 34.2 | 55 | 24.00 R35 | 3500 | 533 | HD785-7 | 60 | 91 | 27.00 R49 | 4500 | 879 | HD1500-7 | 78 | 144.1 | 33.00 R51 | 17250 | 1109 | 730E 7 | 111 | 183.73 | 37.00 R57 | 20000 | 1491 | 730E 8 | 111 | 181.4 | 37.00 R57 | 20000 | 1492 | 830E 1AC | 147 | 221.6 | 40.00 R57 | 22500 | 1865 | 860E 1K | 221 | 253.3 | 50/80 R57 | 35000 | 2014 | 930E 4 | 211 | 291.8 | 53/80 R63 | 50000 | 2014 | 930E 4SE | 211 | 290.4 | 53/80 R63 | 50000 | 2611 | 960E 1 | 214 | 326.58 | 56/80 R63 | 50000 | 2610 | 960 2K | 214 | 326.58 | 56/80 R63 | 50000 | 2610 |

Assumptions and Calculations
To determine the best choice of haul trucks and loaders the calculations were split up into determining which haul truck would be best to use and the loader to best suit the selected haul truck. Before starting the costs analysis and calculations certain assumptions were made. The first assumptions that were made were: * The open pit mine is operational 365 days a year, 12 hours a day. * The explosive cost per year is the same for each truck and loader.

Given that the waste rock is granite with a UCS of 100 MPa the density of the rock can be found to be 2700 kg/m3 (Afrouz 1992). It is possible to calculate the density of the blasted rock:

Density of blasted waste rock= Density of rockswell factor
Density of blasted waste rock= 27001.25
Density of blasted waste rock= 2160 kg/m3

Furthermore from the parameters the calculation of the explosive cost per year is the following:
Explosive cost per year=Exposive cost per tonne ∙Rate of wasteDensity of rock ∙Powder factor
Explosive cost per year=1000 ∙70 000 0002700 ∙0.6
Explosive cost per year=$15 555 555.55/pa
However, as this explosive cost per year is constant throughout all trucks, it does not need to be considered in the calculations of the open pit mine.

The haul truck that has the lowest expected cost was determined by assuming that that each truck had a loader that takes 4 buckets to load each truck with the exact same amount of time. The time taken for the loader to load the first bucket was assumed to be 20 seconds and each one after 30 second. Furthermore, the availability, utilisation of availability and operator efficiency are assumed to be 85%, 88% and 87% respectively (Durham 2014). For a haul truck cycle time to be completed the rolling resistance, speeds reach, unload time and time taken for truck to get into position to be loaded must be known. From Durham (2014) the rolling resistance for a well maintained haul road has a value of 3% for the ramp and 5% for pit floor and surface. An assumption for the open pit mine was that speed limits of 20 km/hr on the pit floor and 40 km/hr elsewhere were enforced. Given that the maximum speeds for all the trucks are similar it led to the assumption that on flat ground (pit floor and surface) the maximum speed limit of 40 km/hr was reached. Additionally, the speeds reached by the haul trucks were assumed to be a maximum going down the open pit ramp and only 30 km/hr going up the ramp with a gradient of 10%. Additionally, the assumption for the unload time and position time are 40 seconds and 30 seconds respectively (Durham 2014). After the above assumptions were made, a haul truck cycle time (see table 1.5) was employed for each truck to see how many trucks would be needed each year as the depth increased to meet the goal of 70 Mt/pa of waste removal. Then using the number of trucks, fuel cost, maintenance cost, tyre cost, employee cost and lubrication cost it is possible to determine the expected cost. An analysis was conducted between all the haul trucks expected costs over the 10 year life cycle. It demonstrated that the cheapest haul truck over 10 years would be Komatsu 930E-4 (see table 1.3 and 1.4).

The following equations were used to calculate the expected cost.
Expected cost=Number of trucks∙cost of truck+Maintenance cost+Fuel cost+Tyre Cost+Employee Cost+Lubrication Cost

The number of trucks was determined by a haul truck cycle time analysis which was stated earlier (Refer to table 1.5 in appendix for number of trucks of Komatsu 930E-4).

Calculating maintenance cost
Maintenance cost=Number of opertional hours ∙Maintenance cost per hour

Calculating fuel cost
Fuel cost=Fuel consumption per hour ∙Number of operational hours∙Fuel cost per litre

Calculating fuel consumption per hour
Fuel consumption per hour=Z ∙Engine Power
Where Z is assumed to be 0.19 (Karrech 2014).

An assumption was made when calculating tyre cost that 4 sets of tires are used per year and each truck needs 6 tyres to function.
Calculating tyre cost
Tyre cost=Number of tyres used∙cost per type

Calculating employee cost
Employee Cost=Number of employees ∙(Salary Per Year+Super)

Calculating number of employees
Number of employees= Number of trucks ∙Number of employeees needed per truck

Calculating number of employees per truck is determined by the work roster. In this case the work roster is 14 days on, 7 days off. Analysing this yields that 3 employees are needed for every two trucks or loaders.

Calculating lubrication cost for trucks
Lubrication cost=0.1∙Maintenance cost of trucks

Calculating lubrication cost for loaders
Lubrication cost=0.075∙Maintenance cost of loaders

In the case of choosing the best loader for the Komatsu 930E-4 a cross analysis of loader bucket capacity and truck capacity was conducted. It demonstrated that the Hitachi EX8000-6 loader is best suited for a fleet of Komatsu 930E-4 dump trucks (refer to table 1.6). It shows that the original assumption that the loader will only take four buckets to load the haul truck was incorrect. Instead the Hitachi EX8000-6 will take five buckets to full load the Komatsu 930E-4. Thus illustrating that the calculations for the number of trucks needed to meet the rate of waste removal requirement was incorrect. Recalculating the haul truck cycle time with five loading buckets and only one Hitachi EX8000-6 yields that at the end of the ten years, 34 Komatsu 930E-4 haul trucks are needed (see table 1.7).

Analysis
Analysing Table 1.8 in appendix of the calculated data for expected costs demonstrates that the majority of the costs, over the ten years, are in the last few years where a large number of haul trucks are needed to meet the production requirement. However, this calculation does not account for times when the trucks or loader are not operational. To account for this limitation it is suggested that a 10% threshold be used for the number of Hitachi EX8000-6 and Komatsu 930E-4. Accounting for this in the calculations yields that the average expected cost; for loading per year is $11 869 288/pa, for loading per tonne is $0.17/t, for hauling per year $142 613 457/pa, for hauling per tonne is $2.04/t. Table 1.9 illustrates the expected costs for each year considering the 10% threshold. The trend of the expected cost shows that as the pit depth increases the expected cost per year increases over the ten year period which can be emphasized in figures 2 and 3. Furthermore, it is apparent that as the price of fuel changes it causes a change in the expected cost. The effect of fuel price varying with a ± 10% of the original fuel cost assumption on the expected cost per year is shown in figures 2 and 3. It is evident from these figures that the sensitivity of fuel cost has a significant effect as the number of dump trucks increases which increases as pit depth increases.ow

Conclusion
To conclude, the most cost efficient and cost effective removal of waste rock is a fleet of thirty seven Komatsu 930E-4 dump trucks and two Hitachi EX8000-6 loaders. It indicated through the analysis that the average expected cost per year of hauling and loading would be $142 613 457/pa and $11 869 288/pa respectively. Additionally, the averaged expected cost per tonne of hauling and loading would be $2.04/t and $0.17/t respectively. The analysis revealed that the costs per year and tonne increases as the depth of the open pit mine increases. However, as with any model analysis it is limited by the assumptions made. If the assumptions are wrong or can change in any way it will affect the final results of which fleet of vehicles are needed to achieve the most cost efficient and effect to meet the removal requirements.

Appendix
Table 1.1: All specifications for Hitachi loaders can be found on these pages Hitachi Loaders | Model | | EX1200-5D | http://www.hitachi-c-m.com/au/products/excavator/large/ex1200-5d/ | EX1200-6 | http://www.hitachi-c-m.com/au/products/excavator/large/ex1200-6/ | EX1900-6 | http://www.hitachi-c-m.com/au/products/excavator/large/ex1900-6/ | EX2500-6 | http://www.hitachi-c-m.com/au/products/excavator/large/ex2500-6/ | EX2600-6 | http://www.hitachi-c-m.com/au/products/excavator/large/ex2600-6/ | EX3600-6 | http://www.hitachi-c-m.com/au/products/excavator/large/ex3600-6/ | EX5500-6 | http://www.hitachi-c-m.com/au/products/excavator/large/ex5500-6/ | EX5600-6 | http://www.hitachi-c-m.com/au/products/excavator/large/ex5600-6/ | EX8000-6 | http://www.hitachi-c-m.com/au/products/excavator/large/ex8000-6/ |

Table 1.2: All specifications for Komatsu Dump trucks can be found on these pages

Komatsu Trucks | Model | | HD325-7 | http://www.komatsu.com.au/Equipment/Pages/Dump%20Trucks%20-%20Rigid/HD325-7.aspx | HD405-7 | http://www.komatsu.com.au/Equipment/Pages/Dump%20Trucks%20-%20Rigid/HD-405-7.aspx | HD465-7E0 | http://www.komatsu.com.au/Equipment/Pages/Dump%20Trucks%20-%20Rigid/HD465-7EO.aspx | HD785-7 | http://www.komatsu.com.au/Equipment/Pages/Dump%20Trucks%20-%20Rigid/HD785-7.aspx | HD1500-7 | http://www.komatsu.com.au/Equipment/Pages/Dump%20Trucks%20-%20Rigid/HD1500-7.aspx | 730E 7 | http://www.komatsu.com.au/Equipment/Pages/Dump%20Trucks%20-%20Rigid/730E-7.aspx | 730E 8 | http://www.komatsu.com.au/Equipment/Pages/Dump%20Trucks%20-%20Rigid/730E-8.aspx | 830E 1AC | http://www.komatsu.com.au/Equipment/Pages/Dump%20Trucks%20-%20Rigid/830E-1AC.aspx | 860E 1K | http://www.komatsu.com.au/Equipment/Pages/Dump%20Trucks%20-%20Rigid/860E-1K.aspx | 930E 4 | http://www.komatsu.com.au/Equipment/Pages/Dump%20Trucks%20-%20Rigid/930E-4.aspx | 930E 4SE | http://www.komatsu.com.au/Equipment/Pages/Dump%20Trucks%20-%20Rigid/930E-4SE.aspx | 960E 1 | http://www.komatsu.com.au/Equipment/Pages/Dump%20Trucks%20-%20Rigid/960E-1.aspx | 960 2K | http://www.komatsu.com.au/Equipment/Pages/Dump%20Trucks%20-%20Rigid/960E-2K.aspx |

Table 1.3: Expected cost analysis for each dump truck TRUCKS | Cost of Fleet ($) | Maintenance Cost ($) | Fuel Cost ($) | Fuel Cost -10% ($) | Fuel Cost +10% ($) | HD325-7 | 206000000 | 611798400 | 754699211.3 | 679229290.2 | 830169132.4 | HD405-7 | 240000000 | 399718800 | 438296105.5 | 394466495 | 482125716.1 | HD465-7E0 | 411000000 | 508518000 | 720966650 | 648869985 | 793063315 | HD785-7 | 290500000 | 307476000 | 718921934.6 | 647029741.2 | 790814128.1 | HD1500-7 | 212000000 | 255660600 | 580141100.3 | 522126990.3 | 638155210.3 | 730E 7 | 184500000 | 215233200 | 609734132.3 | 548760719.1 | 670707545.5 | 730E 8 | 189000000 | 265077600 | 618834572.2 | 556951114.9 | 680718029.4 | 830E 1AC | 170000000 | 242170200 | 632306392.2 | 569075753 | 695537031.4 | 860E 1K | 165000000 | 235468800 | 600696606.7 | 540626946 | 660766267.4 | 930E 4 | 156000000 | 214882800 | 523263059.8 | 470936753.8 | 575589365.7 | 930E 4SE | 169000000 | 234417600 | 678371325.2 | 610534192.7 | 746208457.8 | 960E 1 | 161000000 | 226621200 | 605130901.2 | 544617811.1 | 665643991.3 | 960 2K | 161000000 | 226621200 | 605130901.2 | 544617811.1 | 665643991.3 |

Table 1.4: Expected cost analysis for each dump truck TRUCKS | Tyre Cost ($) | Employee Costs ($) | Lubrication Cost ($) | TOTAL ($) | TOTAL -10% fuel ($) | TOTAL +10% fuel ($) | HD325-7 | 83808000 | 286780500 | 45884880 | 1988970991 | 1913501070 | 2064440912 | HD405-7 | 85176000 | 166549500 | 29978910 | 1359719316 | 1315889705 | 1403548926 | HD465-7E0 | 97524000 | 190694250 | 38138850 | 1966841750 | 1894745085 | 2038938415 | HD785-7 | 75816000 | 115303500 | 23060700 | 1531078135 | 1459185941 | 1602970328 | HD1500-7 | 185886000 | 73748250 | 19174545 | 1326610495 | 1268596385 | 1384624605 | 730E 7 | 168480000 | 57651750 | 16142490 | 1251741572 | 1190768159 | 1312714986 | 730E 8 | 170880000 | 58473000 | 19880820 | 1322145992 | 1260262535 | 1384029449 | 830E 1AC | 157140000 | 47796750 | 18162765 | 1267576107 | 1204345468 | 1330806746 | 860E 1K | 215040000 | 42048000 | 17660160 | 1275913567 | 1215843906 | 1335983227 | 930E 4 | 267600000 | 36627750 | 16116210 | 1214489820 | 1162163514 | 1266816126 | 930E 4SE | 267600000 | 36627750 | 17581320 | 1403597995 | 1335760863 | 1471435128 | 960E 1 | 238800000 | 32685750 | 16996590 | 1281234441 | 1220721351 | 1341747531 | 960 2K | 238800000 | 32685750 | 16996590 | 1281234441 | 1220721351 | 1341747531 |

Table 1.5: Haul time cycle analysis for Komatsu 930E-4 Komatsu 930E-4 | Year | 1 | 2 | 3 | 4 | 5 | Seconds: | | | | | | Loading Time 1 | 20 | 20 | 20 | 20 | 20 | Loading Time 2-4 | 90 | 90 | 90 | 90 | 90 | Haul to dump | 36 | 36 | 36 | 36 | 36 | | 30 | 90 | 180 | 240 | 300 | | 54 | 54 | 54 | 54 | 54 | Unload | 40 | 41 | 42 | 43 | 44 | Haul to load | 54 | 54 | 54 | 54 | 54 | | 22.5 | 67.5 | 135 | 180 | 225 | | 36 | 36 | 36 | 36 | 36 | Position Time | 30 | 30 | 30 | 30 | 30 | Total Seconds | 412.5 | 518.5 | 677 | 783 | 889 | Mins | 6.875 | 8.641666667 | 11.28333333 | 13.05 | 14.81666667 | Tonnes Per Cycle | 292 | 292 | 292 | 292 | 292 | Tonnes Per Hour | 2546.618182 | 2025.998071 | 1551.669129 | 1341.609195 | 1181.642295 | Hours Per Shift | 12 | 12 | 12 | 12 | 12 | Tonnes Per Shift | 30559.41818 | 24311.97686 | 18620.02954 | 16099.31034 | 14179.70754 | Shifts Per Year | 365 | 365 | 365 | 365 | 365 | Availability | 85% | 85% | 85% | 85% | 85% | Utilisation Of Availability | 88% | 88% | 88% | 88% | 88% | Operator Efficiency | 87% | 87% | 87% | 87% | 87% | Tonnes Per Year | | Tpa Per Truck | 7258699.146 | 5774760.652 | 4422767.205 | 3824027.328 | 3368069.064 | No Of Trucks For 70Mtpa | 10 | 13 | 16 | 19 | 21 |

Komatsu 930E-4 | 6 | 7 | 8 | 9 | 10 | | | | | | 20 | 20 | 20 | 20 | 20 | 90 | 90 | 90 | 90 | 90 | 36 | 36 | 36 | 36 | 36 | 360 | 420 | 480 | 540 | 600 | 54 | 54 | 54 | 54 | 54 | 45 | 46 | 47 | 48 | 49 | 54 | 54 | 54 | 54 | 54 | 270 | 315 | 360 | 405 | 450 | 36 | 36 | 36 | 36 | 36 | 30 | 30 | 30 | 30 | 30 | 995 | 1101 | 1207 | 1313 | 1419 | 16.58333333 | 18.35 | 20.11666667 | 21.88333333 | 23.65 | 292 | 292 | 292 | 292 | 292 | 1055.758794 | 954.1144414 | 870.3231152 | 800.0609292 | 740.2959831 | 12 | 12 | 12 | 12 | 12 | 12669.10553 | 11449.3733 | 10443.87738 | 9600.73115 | 8883.551797 | 365 | 365 | 365 | 365 | 365 | 85% | 85% | 85% | 85% | 85% | 88% | 88% | 88% | 88% | 88% | 87% | 87% | 87% | 87% | 87% | | | | | | 3009259.696 | 2719539.871 | 2480707.04 | 2280436.708 | 2110086.961 | 24 | 26 | 29 | 31 | 34 |

Table 1.6: Number of loader buckets needed for each truck LOADERS - NUMBER OF BUCKETS NEEDED FOR EACH TRUCK | Model | HD325-7 | HD405-7 | HD465-7E0 | HD785-7 | HD1500-7 | 730E 7 | 730E 8 | EX1200-5D | 3.120 | 5.385 | 4.701 | 7.778 | 12.316 | 15.703 | 15.504 | EX1200-6 | 3.120 | 5.385 | 4.701 | 7.778 | 12.316 | 15.703 | 15.504 | EX1900-6 | 1.690 | 2.917 | 2.546 | 4.213 | 6.671 | 8.506 | 8.398 | EX2500-6 | 1.352 | 2.333 | 2.037 | 3.370 | 5.337 | 6.805 | 6.719 | EX2600-6 | 1.352 | 2.333 | 2.037 | 3.370 | 5.337 | 6.805 | 6.719 | EX3600-6 | 0.966 | 1.667 | 1.455 | 2.407 | 3.812 | 4.861 | 4.799 | EX5500-6 | 0.843 | 1.455 | 1.270 | 2.102 | 3.328 | 4.243 | 4.189 | EX5600-6 | 0.787 | 1.358 | 1.185 | 1.961 | 3.106 | 3.960 | 3.909 | EX8000-6 | 0.570 | 0.984 | 0.859 | 1.422 | 2.252 | 2.871 | 2.834 | Model | 830E 1AC | 860E 1K | 930E 4 | 930E 4SE | 960E 1 | 960 2K | 830E 1AC | EX1200-5D | 18.940 | 21.650 | 24.940 | 24.821 | 27.913 | 27.913 | 18.940 | EX1200-6 | 18.940 | 21.650 | 24.940 | 24.821 | 27.913 | 27.913 | 18.940 | EX1900-6 | 10.259 | 11.727 | 13.509 | 13.444 | 15.119 | 15.119 | 10.259 | EX2500-6 | 8.207 | 9.381 | 10.807 | 10.756 | 12.096 | 12.096 | 8.207 | EX2600-6 | 8.207 | 9.381 | 10.807 | 10.756 | 12.096 | 12.096 | 8.207 | EX3600-6 | 5.862 | 6.701 | 7.720 | 7.683 | 8.640 | 8.640 | 5.862 | EX5500-6 | 5.118 | 5.850 | 6.739 | 6.707 | 7.542 | 7.542 | 5.118 | EX5600-6 | 4.776 | 5.459 | 6.289 | 6.259 | 7.038 | 7.038 | 4.776 | EX8000-6 | 3.463 | 3.958 | 4.559 | 4.538 | 5.103 | 5.103 | 3.463 |

Table 1.7: Haul time cycle analysis for Komatsu 930E-4 considering Hitachi EX8000-6 loader Komatsu 930E-4 | Year | 1 | 2 | 3 | 4 | 5 | Seconds: | | | | | | Loading time 1 | 20 | 20 | 20 | 20 | 20 | Loading time 2-5 | 120 | 120 | 120 | 120 | 120 | | 36 | 36 | 36 | 36 | 36 | | 30 | 90 | 180 | 240 | 300 | | 54 | 54 | 54 | 54 | 54 | | 40 | 41 | 42 | 43 | 44 | | 54 | 54 | 54 | 54 | 54 | | 22.5 | 67.5 | 135 | 180 | 225 | | 36 | 36 | 36 | 36 | 36 | | 30 | 30 | 30 | 30 | 30 | TOTAL Seconds | 442.5 | 548.5 | 707 | 813 | 919 | mins | 7.38 | 9.14 | 11.78 | 13.55 | 15.32 | tonnes per cycle | 292 | 292 | 292 | 292 | 292 | tonnes per hour | 2373.97 | 1915.19 | 1485.83 | 1292.10 | 1143.07 | hours per shift | 12 | 12 | 12 | 12 | 12 | tonnes per shift | 28487.59 | 22982.24 | 17829.93 | 15505.24 | 13716.82 | shifts per year | 365 | 365 | 365 | 365 | 365 | availability | 85% | 85% | 85% | 85% | 85% | utilisation of availability | 88% | 88% | 88% | 88% | 88% | operator efficiency | 87% | 87% | 87% | 87% | 87% | tonnes per year | | | | | | Tpa per truck | 6766583.95 | 5458912.302 | 4235096.744 | 3682919.309 | 3258121.216 | No of trucks for 70Mtpa | 11 | 13 | 17 | 20 | 22 | | | | | | | Year | 6 | 7 | 8 | 9 | 10 | Seconds: | | | | | | Loading time 1 | 20 | 20 | 20 | 20 | 20 | Loading time 2-5 | 120 | 120 | 120 | 120 | 120 | | 36 | 36 | 36 | 36 | 36 | | 360 | 420 | 480 | 540 | 600 | | 54 | 54 | 54 | 54 | 54 | | 45 | 46 | 47 | 48 | 49 | | 54 | 54 | 54 | 54 | 54 | | 270 | 315 | 360 | 405 | 450 | | 36 | 36 | 36 | 36 | 36 | | 30 | 30 | 30 | 30 | 30 | TOTAL Seconds | 1025 | 1131 | 1237 | 1343 | 1449 | mins | 17.08 | 18.85 | 20.62 | 22.38 | 24.15 | tonnes per cycle | 292 | 292 | 292 | 292 | 292 | tonnes per hour | 1024.86 | 928.81 | 849.22 | 782.19 | 724.97 | hours per shift | 12 | 12 | 12 | 12 | 12 | tonnes per shift | 12298.30 | 11145.68 | 10190.59 | 9386.27 | 8699.63 | shifts per year | 365 | 365 | 365 | 365 | 365 | availability | 85% | 85% | 85% | 85% | 85% | utilisation of availability | 88% | 88% | 88% | 88% | 88% | operator efficiency | 87% | 87% | 87% | 87% | 87% | tonnes per year | | | | | | Tpa per truck | 2921183.803 | 2647403.535 | 2420544.38 | 2229496.201 | 2066399.86 | No of trucks for 70Mtpa | 24 | 27 | 29 | 32 | 34 |

Table 1.8: Expected cost calculation for Hitachi EX8000-6 & Komatsu 930E-4 Hitachi EX8000-6 & Komatsu 930E-4 | Year | 1 | 2 | 3 | 4 | 5 | Expected Cost for loading per year | 15806612 | 4806612 | 4806612 | 4806612 | 4806612 | Expected Cost for loading per tonne | 0.23 | 0.07 | 0.07 | 0.07 | 0.07 | Expected Cost for Hauling per year | 118477492.3 | 74018854.56 | 105101579 | 113413622.4 | 116954984.6 | Expected Cost for Hauling per tonne | 1.69 | 1.06 | 1.50 | 1.62 | 1.67 | | | | | | | Year | 6 | 7 | 8 | 9 | 10 | Expected Cost for loading per year | 4806612 | 4806612 | 4806612 | 4806612 | 4806612 | Expected Cost for loading per tonne | 0.07 | 0.07 | 0.07 | 0.07 | 0.07 | Expected Cost for Hauling per year | 126496346.9 | 146808390.2 | 150349752.5 | 170661795.8 | 174203158.1 | Expected Cost for Hauling per tonne | 1.81 | 2.10 | 2.15 | 2.44 | 2.49 |

Table 1.9: Expected cost calculation for Hitachi EX8000-6 & Komatsu 930E-4 considering 10% thresholds. Hitachi EX8000-6 & Komatsu 930E-4 | Year | 1 | 2 | 3 | 4 | 5 | Expected Cost for loading per year | 33159364 | 9503724 | 9503724 | 9503724 | 9503724 | Expected Cost for loading per tonne | 0.47 | 0.14 | 0.14 | 0.14 | 0.14 | Expected Cost for Hauling per year | 130325241.6 | 81420740.02 | 115611736.9 | 124754984.6 | 128650483.1 | Expected Cost for Hauling per tonne | 1.86 | 1.16 | 1.65 | 1.78 | 1.84 | | | | | | | Year | 6 | 7 | 8 | 9 | 10 | Expected Cost for loading per year | 9503724 | 9503724 | 9503724 | 9503724 | 9503724 | Expected Cost for loading per tonne | 0.14 | 0.14 | 0.14 | 0.14 | 0.14 | Expected Cost for Hauling per year | 139145981.6 | 161489229.3 | 165384727.7 | 187727975.4 | 191623473.9 | Expected Cost for Hauling per tonne | 1.99 | 2.31 | 2.36 | 2.68 | 2.74 |

Figure 2: Expected cost of Hauling with sensitivity of fuel cost

Figure 3: Expected cost of Loading with sensitivity of fuel cost

References

Afrouz, A 1992, Practical Handbook of Rock Mass Classification Systems and Modes of Ground failure, CRC Press Inc., USA.

Durham, R 2014, Productivity – Truck & Haul Roads, lecture notes distributed in Resource Extraction Technologies at The University of Western Australia, Crawley on 28 August 2014.

Hitachi Construction Machinery Co. Ltd 2004, Large Excavators / Loading Shovels. Available from: <http://www.hitachi‐cm.com/au/products/excavator/large/>. [14 September 2014].

Karrech, A 2014, Handling, lecture notes distributed in Resource Extraction Technologies at The University of Western Australia, Crawley on 14 August 2014.

Komatsu Australia n.d, Dump Trucks-Rigid. Available from: <http://www.komatsu.com.au/Equipment/Pages/Dump-Trucks-Rigid.aspx>. [14 September 2014].

Similar Documents

Free Essay

Engineering

...ENB100 - ENGINEERING & SUSTAINABILITY Progress Report (due in Wk12 Tutorial) ! Student Name: ! Student # Your task: Your role as a professional engineer will require you to assess multiple solutions for a single problem. Often, the suitability of the solution has little to do with the price or the provider but more to do with ‘fitness for purpose’. As such, it is vital that a structured process is used to identify the most appropriate solution. This process is called an evaluation matrix. ! Your task is two-fold. Firstly, in your own words, you need to define the term ‘evaluation matrix’. Make sure your definition relates to the engineering context and provide robust references. Secondly, you need to develop suitable criteria for use in your final project. Ensure you use clear and measurable criteria that take into account the client needs. ! ! ! 1. Definition An Evaluation matrices are used in the engineering profession as a tool to evaluate a number of different types of options against a prioritised criteria. If the design ideas do not meet the criteria then two different levels of the evaluation matrices can be used. The first level effectively acts as a filter with each different option evaluating it against the mandatory criteria. (UCLA, 1-2, 2014) para The design options that meed these mandatory criteria then go on to the second level with involves them being evaluated against prioritised criteria. This is vital this profession...

Words: 438 - Pages: 2

Premium Essay

Engineering

...• Why are you pursuing a degree in Engineering, Architecture, or Technology? As a child, I grew up playing with tools in my dad’s garage. Instead of puzzles, I put together ball bearings. I chose mechanical engineering because I’m a very visual and kinesthetic learner. I like creating things that I can see and hold in my hands. I have always been most interested in math and science, and engineering is a field in which you can apply your knowledge to real life situations. I love problem solving, and the feeling of accomplishment when I manage to find a solution. • Why do you want to be involved in CEAT Student Council? I do not believe in joining organizations or clubs just for the extra line on a resume. I would prefer to devote my time to one cause that matters to me. I believe CEAT Student Council contributes greatly to our environment on campus. In CEAT Student Council, I would have the opportunity to give back to the community, volunteer, and organize some great events for our campus; all with motivated people that share many of my interests. • What is your greatest strength and how could you use it to benefit CEAT Student Council? I am an extremely organized and efficient person. I am very good at time management, and I never overextend myself. I would have the time needed to devote to CEAT Student Council meetings, activities, and events. I would be an asset for organizing events that would provide our student body with new opportunities as well...

Words: 531 - Pages: 3

Free Essay

Engineering

...Why I want to be an Engineer There have been different reasons at different stages of my life why I developed a passion for the engineering profession. It started from a youthful age watching my father, who was a mechanical engineer and wanting to emulate him when I got to adulthood. I liked the way he talked about his occupation with great excitement. He tended to travel a lot but also had time to spend with his family. I was impressed with his knowledge of Mathematics, Physics and Chemistry. He was always helping my older brother with his calculus assignments even though he had been through school for a long time. The engineering profession afforded my father with the resources to provide for his family and to do some philanthropic work as well. There was always something technological being discussed with his friends. In my early years when I wanted to be an engineer, it was always because I just wanted to be like my father, not until I got into school. When I started school, I realized I was very interested in mathematics and the sciences. The tougher the subject, the greater satisfaction I had at the end of the term when I succeeded. I loved working in the science labs and learning how science works. I always wanted to challenge myself with an occupation that will keep me on my toes, so engineering being my first love was an obvious choice. I liked reading about the great inventors and scientists of our time like Sir Isaac Newton, Thomas Edison, The Wright...

Words: 912 - Pages: 4

Premium Essay

Engineering

...Civil Engineering has been an aspect of life since the beginnings of human existence. The earliest practices of Civil engineering may have commenced between 4000 and 2000 BC in Ancient Egypt and Mesopotamia (Ancient Iraq) when humans started to abandon a nomadic existence, thus causing a need for the construction of shelter. During this time, transportation became increasingly important leading to the development of the wheel and sailing. Until modern times there was no clear distinction between civil engineering and architecture, and the term engineer and architect were mainly geographical variations referring to the same person, often used interchangeably. The construction of Pyramids in Egypt (circa 2700-2500 BC) might be considered the first instances of large structure constructions. In the 18th century, the term civil engineering was coined to incorporate all things civilian as opposed to military engineering. The first engineering school, The National School of Bridges and Highways, France, was opened in 1747. The first self-proclaimed civil engineer was John Smeaton who constructed the Eddystone Lighthouse. In 1771, Smeaton and some of his colleagues formed the Smeatonian Society of Civil Engineers, a group of leaders of the profession who met informally over dinner. Though there was evidence of some technical meetings, it was little more than a social society. In 1818, world’s first engineering society, the Institution of Civil Engineers was founded in London, and in...

Words: 589 - Pages: 3

Premium Essay

Women and Engineering

...Women in the Engineering World Engineering is a field dominated by men in today's society. When people think about engineering they think about men with glasses and never does a woman come to mind. However, there have been many studies on the skills that keep women out of engineering as a career yet there is no proof that women cannot or do not possess the skills needed to be a successful engineer. Therefore, it is thought and stereotyped that women do not have the skills to have an engineering career. Women are stereotyped as being dumb just because they are pretty, but many women have proven that stereotype wrong. These women who do have the skills to enter into the field face bias everyday in the field because they are women, not because they lack in the required skills. There have been organizations that spend their time encouraging women to enter into engineering. The Organizations and societies have become so strong and so persuasive that even the company that makes Barbie is coming out with a computer engineering Barbie to attract young girls into the field. The push from the organizations and the drive of the women for success has helped some women to make a breakthrough in the field. Those few women who have overcome many challenges and obstacles in the field have to prove themselves to be looked at with even the slightest bit of respect. These women who make a breakthrough are making huge impacts on the field and improving it tremendously. Women are important to engineering...

Words: 1681 - Pages: 7

Premium Essay

Engineering Society

...matter with Hambali himself? as an engineer I think what Daniel do is right because he need to act professionally because it is mentioned in the engineering canons where engineers shall act In such a manner as to uphold and enhance the honor integrity and dignity of the profession. But then it doesn’t mean that Daniel shouldn’t need to see Hambali personally to discuss the matter in fact it is a must, because of Daniel has to act professional he need to do it step by step. This is also Daniel’s duty as a engineer where he needs to tell the truth as mentioned by Immanuel Kant that duties are absolute and unconditional.. Should Daniel have a conversation with Hambali about his concerns? If so, what type of conversation should Daniel have with Hambali when he talks with him? In my opinion Daniel should have a conversation with Hambali about his concerns and Daniel should have a formal conversation with hambali because what he is done is against the codes of ethics of an engineer that is being honest and impartial and serving with fidelity the public their employers and clients. Then he need to explained all the ethics and fundamental canons of being an engineer because engineer serve for the society we all need to behave. Other than that by having a conversation with Hambali it will make he realize that practice the engineering ethics is very important and when Hambali admits his mistake he will get a lesson from it and slightly if not much improve his ethical judgement ...

Words: 608 - Pages: 3

Free Essay

Engineering

...Task 1 Why does engineering equipment fail, what happens when it does and what can we do about it? Equipment’s fails because certain parts of it fail first and that prevents the whole process from working. It is important to understand the problem before any maintenance. There are a lot of reasons it could fail because of the age of the equipment and parts need to be changed or if the equipment vibrates nuts and bolts can be loosen and parts can fall apart. When this happens the machine needs to be stopped and maintained. Age is very important if the machine has been used for a very long time the efficiency and the quality wouldn’t be as good as a new one, a machine has a certain life span for example on a car the timing belt must be replaced after every 50,000 miles. Wear could lead to a fault in a machine because parts come into contact with each other for example a cars break pad. Corrosion in certain materials takes longer than others like aluminium, when a part of a machine corrodes it degrade and can cause failures. Raw materials such as oil and compressed air can run equipment’s. If something different unwanted to the equipment is in it, it can affect the way the machine works. For example water in a petrol tank will cause a car to break down and this is a fouling. Lack of maintenance can cause a fail, routine maintenance such as cleaning and lubrication. This cause for example in a factory that is manufacturing can will stop the line and check the cars in that line to...

Words: 1288 - Pages: 6

Premium Essay

Engineering

...Construction Engineering This civil engineering branch deals with the planning, construction and maintenance of structures. Construction engineering is the planning and execution of designs from site development, environmental, structural, transportation and structural engineers. They must ensure that the plans that have been designed by other engineers are implemented to their exact specifications. Construction engineers will supervise field work during the entire project. They are in a sense a cross between an engineer and manager as they will oversee the project from start to finish and handle any problems that come up throughout the duration of the project. Structural Engineering This branch of civil engineering encompasses the structural analysis and design of structures. It is the responsibility of the structural engineer to analyze and design a structure that will safely bear or resist the stresses, forces and loads. The design must satisfy the project specifications while meeting all safety regulations. The structure must endure massive loads as well as natural disasters and climate changes. Geotechnical Engineering In geotechnical engineering the engineer studies soil, foundations and bearing capacities. The engineer will study the behavior of the earth materials and how they will affect a structure that is to be constructed. They will also evaluate pre-existing structures that are showing signs of problems with the earth materials under or near the structure. Transportation...

Words: 798 - Pages: 4

Premium Essay

Engineering

...2014. GATE 2014 score will be valid for a period of TWO YEARS from the date result announcement. What is New in GATE 2014 ? All the papers will be conducted online. On Line Exam Pattern: A computer based test (CBT) where the candidate have to enter the correct answers using computer mouse & virtual keypad displayed on the monitor. Numerical Data Type Questions : 15 to 35 marks. No Negative Marking for Numerical Data Type Questions. Exam Pattern: 3 hours, 65 questions, 100 marks. l Eligibility Bachelor’s degree holders in Engineering/ Technology/ Architecture. Master’s degree holders in any branch of Science/ l Mathematics/ Statistics/ Computer Applications or equivalent and those who are in the final year of such programs. Candidates in the second or higher year of Four-year l Integrated Master’s degree programs in Engineering /Technology. Candidates in the fourth or higher year of Five-year l Integrated Master’s or Dual Degree programs in Engineering/Technology. Candidates with qualifications obtained through l examinations recognized by UPSC/AICTE (e.g. AMIE by IE(I), AMICE(I) by the Institute of Civil Engineers (India)ICE(I)) as equivalent to B.E./B.Tech. Important Dates Commencement of Online Applicant Interface Last date for Submission of Online Application Receipt hard copy of application with supporting documents at GATE offices GATE 2014 Exam (Saturdays & Sundays) exact date will be updates on GATE website soon 2 Sep 2013 3 Oct 2013 10 Oct 2013 1 Feb 2014 to 2...

Words: 388 - Pages: 2

Free Essay

Engineering

...University of San Carlos Nasipit, Talamban, Cebu City, Philippines CERAMIC INSULATORS: AN IDEAL FOR ELECTRICAL SAFETY By: Kirby Emmanuel C. Oraiz Frank Joseph P. Ruiz Ramel Joseph A. Derecho University of San Carlos Talamban Campus Nasipit, Talamban, Cebu City, Cebu INTRODUCTION: Science and technology are in continuous development. This leads to ever more demanding and intelligent technology. The demands made on modern materials are increasing with the same dynamism. The features that are demanded include greater strengths for material-saving constructions, lighter components for energy saving, higher quality for more security and longer service life. After all, cost-effectiveness plays a crucial role. Ceramic materials have in the past made an important contribution to this process of innovation. Requirements for the successful application of ceramics include constructions that are appropriate to the materials and the manufacturing processes, as well as appropriate applications. The point is not that common materials can be displaced, but rather that customised products allow completely new solutions. In order to make intelligent and effective use of the properties of ceramics, it is not sufficient simply to take an existing structural component and to replace it in every detail with a ceramic part. A drawing of the component used so far, however, together with a great deal of supplementary information, can show the way to the mass-produced ceramic component...

Words: 2812 - Pages: 12

Free Essay

Quality Engineering

...QUALITY ENGINEERING DESIGN FOR WEB-BASED CATAPULT BY Mohammed Mujeeb Ahmed khan SUBMITTED TO PROFESSOR K. M. RAGSDELL FOR CREDIT IN EMGT-475: QUALITY ENGINEERING Contents 1. Introduction 1.1. An overview of Quality Engineering 1.2. Problem description  P diagram  Quality characteristics  Control factors  Noise factors  Mathematical Model of Crystal Ball 2. Method and Experimental plan  The static experiment  The dynamic experiment  Fast Diagram  Fault tree Diagram 3. Conclusions 4. References 5. Annexure  Static Experiment  Analysis of means  Analysis of Variance  Dynamic experiment  Confirmation Experiment 2 1. Introduction The Taguchi system of Quality Engineering is a philosophy and a set of tools and techniques to design and deliver high quality, low cost products in a short time. The foundation of this system was laid by Dr. Genichi Taguchi in Japan. In the decades that followed, Dr. Taguchi’s techniques were applied to an increasing number of applications to solve real world problems. The technique was introduced to the western world in the 1980s, and it quickly created a paradigm shift in the perception of quality. 1.1. An overview of Quality Engineering System: Product Parameter Design: Product parameter design is optimizing the product parameters to give the desired performance. A quality characteristic is chosen whose...

Words: 2020 - Pages: 9

Premium Essay

Redefining Engineering

...Gregory Alan Francisco, II Energy Science Laboratory Current Event 1 Professor Calamas September 11, 2014 Gregory Alan Francisco, II Energy Science Laboratory September 11, 2014 Groups of people composed of all types of majors are being implemented into groups to practice and develop their skills to help people in developing countries with accommodations they might not have the means to produce themselves. Engineers Without Boarders is one of the big organizations that is participating in the global impact form of engineering teams. The teams that they produce are very diverse; including business, biology, engineers and political science majors alike to accomplish the tasks they have been presented. These groups are given multiple tests to determine what their strengths are and weaknesses to more properly form them into the individual’s teams they will cooperate with. The teams are then on a 5 month voyage in which they are responsible for thinking outside the box to design, prototype, and build their idea to satisfy a problem definition. One of these teams are the ones responsible for creating the Tripod Pump Frame which holds an irrigation pump but for much cheaper than the previous model. This product, according to the school, became the biggest selling pump in Myanmar. Theses tripods can be used to help solve a global problem of access to clean drinking water particularly in underdeveloped areas where water is scarce and you have to sometimes walk several...

Words: 305 - Pages: 2

Premium Essay

Engineering Overview

...Engineering Overview The Field Engineers apply the theories and principles of science and mathematics to research and develop economical solutions to technical problems. Their work is the link between perceived social needs and commercial applications. Engineers design products, machinery to build those products, plants in which those products are made, and the systems that ensure the quality of the products and the efficiency of the workforce and manufacturing process. Engineers design, plan, and supervise the construction of buildings, highways, and transit systems. They develop and implement improved ways to extract, process, and use raw materials, such as petroleum and natural gas. They develop new materials that both improve the performance of products and take advantage of advances in technology. They harness the power of the sun, the Earth, atoms, and electricity for use in supplying the Nation's power needs, and create millions of products using power. They analyze the impact of the products they develop or the systems they design on the environment and on people using them. Engineering knowledge is applied to improving many things, including the quality of healthcare, the safety of food products, and the operation of financial systems. Engineers consider many factors when developing a new product. For example, in developing an industrial robot, engineers determine precisely what function the robot needs to perform; design and test the robot's components; fit the...

Words: 3066 - Pages: 13

Premium Essay

Tissue Engineering

...Tissue engineering is a branch of biomedical engineering that focuses on isolating and amplifying the natural ability of the human body to heal injuries. The paradigm of tissue engineering is composed of three major components: a tissue scaffold; biological factors; and cells. Among these three components, the source of the cells used in the medical device is the largest source of controversy. Not only can the origin of the cells affect the funding of an engineering project, but it can even lead to the overall rejection of the project by society if they feel that the source is morally objectionable. This essay will explore two common sources of pluripotent cells used in tissue engineering, the laws that are set in place in accordance with...

Words: 1410 - Pages: 6

Premium Essay

Software Engineering

...Computer machinery (2007, April 12). Computing Degrees & Careers » Software Engineering. Retrieved February 23, 2014, from http://computingcareers.acm.org/?page_id=12. Web This article discusses software engineering and the definition of basically what it is, it states that it is concerned with maintaining software systems and developing one that will work correctly and be very dependable for the user, they have to keep in mind as well that there projects need to be affordable and that they assure reliability and they meet all the users needs. The actual article states, “Software engineering (SE) is concerned with developing and maintaining software systems that behave reliably and efficiently, are affordable to develop and maintain, and satisfy all the requirements that customers have defined for them.” (computer machinery) The article talks about how critical it is for the application to be safe especially because of how expensive the software system are. Software Engineering integrates a significance of mathematics in computer science and practices the origins of engineering. This article give a good definition of what software engineering is about, it doesn’t give enough detail on what exactly they are doing everyday its very broad and doesn’t narrow it down. It begins to talk more about how to get into the job itself, instead of focusing on exactly what they do, it gives a description of all the step you need to take to get there. It strays away from what you’re...

Words: 1601 - Pages: 7