Free Essay

Investigation Report

In:

Submitted By qczhang
Words 13395
Pages 54
U.S. CHEMIC AL S AFETY

AND

H AZ ARD INVESTIG ATION BOARD

INVESTIGATION REPORT
LPG FIRE AT VALERO – MCKEE REFINERY
(Four Injured, Total Refinery Evacuation, and Extended Shutdown)

Photo: Associated Press

VALERO ENERGY CORPORATION
SUNRAY, TEXAS
FEBRUARY 16, 2007

KEY ISSUES:
• FREEZE PROTECTION OF DEAD-LEGS
• EMERGENCY ISOLATION OF EQUIPMENT
• FIREPROOFING OF SUPPORT STEEL
• FIRE PROTECTION FOR HIGH PRESSURE LPG SERVICE
• CHLORINE RELEASE

REPORT NO. 2007-05-I-TX
JULY 2008

Valero - Sunray

July 2008

Contents
EXECUTIVE SUMMARY ..........................................................................................................................6
1.0

INTRODUCTION .........................................................................................................................10
1.1
1.2

2.0

Background....................................................................................................................... 10
Investigative Process......................................................................................................... 10

VALERO ENERGY CORPORATION.........................................................................................11
2.1
2.2

McKee Refinery................................................................................................................ 11

2.3
3.0

Company History .............................................................................................................. 11

Propane Deasphalting (PDA) Unit.................................................................................... 12

INCIDENT DESCRIPTION..........................................................................................................15
3.1
3.2

Injuries .............................................................................................................................. 16

3.3

Emergency Response and Refinery Evacuation ............................................................... 16

3.4

Aftermath .......................................................................................................................... 17

3.5
4.0

The Incident ...................................................................................................................... 15

Near-Miss Events.............................................................................................................. 18

INCIDENT ANALYSIS................................................................................................................20
4.1
4.2

Dead-Leg Freeze Protection ............................................................................................. 25

4.3

Fireproofing ...................................................................................................................... 29

4.4
5.0

Incident Sequence ............................................................................................................. 21

Emergency Isolation and Shutdown ................................................................................. 33

NEAR-MISS ANALYSIS .............................................................................................................35
5.1
5.2

6.0

Chlorine Release ............................................................................................................... 36
Butane Sphere Deluge Valves .......................................................................................... 38

PROCESS HAZARD ANALYSIS (PHA) ....................................................................................41

2

Valero - Sunray

7.0

July 2008

REGULATORY ANALYSIS........................................................................................................43
7.1
7.2

EPA Risk Management Program (RMP) .......................................................................... 43

7.3
8.0

OSHA Process Safety Management ................................................................................. 43

Regulatory Enforcement History ...................................................................................... 44

ROOT AND CONTRIBUTING CAUSES....................................................................................45
8.1

Root Causes ...................................................................................................................... 45

8.2

Contributing Causes.......................................................................................................... 45

9.0

RECOMMENDATIONS...............................................................................................................46

10.0

REFERENCES ..............................................................................................................................49

APPENDIX A.

FLOW DIAGRAM .....................................................................................................51

APPENDIX B

INCIDENT TIMELINE ..............................................................................................52

APPENDIX C

PIPING ELBOW FAILURE ANALYSIS ..................................................................54

APPENDIX D.

INITIAL PROPANE RELEASE RATE.....................................................................57

APPENDIX E.

RESPONSE OF STRUCTURAL STEEL TO FIRE HEATING................................59

APPENDIX F:

EVENT TREE.............................................................................................................61

3

Valero - Sunray

July 2008

Figures
Figure 1. PDA unit location in McKee Refinery ........................................................................................ 13
Figure 2. No. 1 Extractor simplified process flow diagram....................................................................... 14
Figure 3. Approximately 90 seconds after ignition (from surveillance video) .......................................... 16
Figure 4. Aerial photograph of damage from the PDA fire ....................................................................... 19
Figure 5. Propane mix control station schematic (not to scale) ................................................................. 21
Figure 6. Crack in the 10” diameter propane mix control station inlet elbow ........................................... 23
Figure 7. Downstream view of propane mix control station inlet block valve .......................................... 24
Figure 8. Damaged 10” propane inlet on Extractor No. 1 ......................................................................... 25
Figure 9. Pipe bridge support fireproofing................................................................................................. 30
Figure 10. Extractor towers (upper right) and collapsed pipe rack............................................................ 31
Figure 11. Distances between the E-W pipe rack supports and the extractors .......................................... 32
Figure 12. Insurer-recommended locations for ROSOVs.......................................................................... 33
Figure 13. Ruptured one-ton chlorine container ......................................................................................... 38
Figure 14. Heat-damaged coating on sphere and location of sphere deluge valves................................... 39

4

Valero - Sunray

July 2008

Acronyms and Abbreviations
AIChE

American Institute of Chemical Engineers

API

American Petroleum Institute

BPD

barrels per day (100 BPD = 2.92 gallons per minute)

CCPS

Center for Chemical Process Safety

CFR

Code of Federal Regulations

CSB

U.S. Chemical Safety and Hazard Investigation Board

DAGO

DeAsphalted Gas Oil

DCS

distributed control system

EIV

emergency isolation valve

EHS

extremely hazardous substance

EOC

Emergency Operations Center

EPA

U.S. Environmental Protection Agency

EPCRA

Emergency Planning and Community Right-to-Know Act

ERPG

Emergency Response Planning Guideline

IChemE

Institute of Chemical Engineers (UK)

IDLH

immediately dangerous to life or health

LPG

liquefied petroleum gas

MOC

Management of Change

NPRA

National Petrochemical and Refiners Association

NWS

National Weather Service

OSHA

Occupational Safety and Health Administration

PDA

Propane DeAsphalting Unit

PEL

permissible exposure limit

PHA

Process Hazard Analysis

psi

pounds per square inch (1 psig = 6.89 kPa)

PSM

Process Safety Management (OSHA)

RMP

Risk Management Program (EPA)

ROSOV

Remotely Operable Shut-Off Valve

TCEQ

Texas Commission on Environmental Quality

UDS

Ultramar Diamond Shamrock

5

Valero - Sunray

July 2008

EXECUTIVE SUMMARY
On February 16, 2007, a liquid propane release from cracked control station piping resulted in a massive fire in the propane deasphalting (PDA) 1 unit at Valero’s McKee Refinery near Sunray, Texas, injuring three employees and a contractor. The fire caused extensive equipment damage and resulted in the evacuation and total shutdown of the McKee Refinery. The refinery remained shut down for two months; the PDA unit was rebuilt and resumed operation nearly one year after the incident. Direct losses attributed to the fire were reported to exceed $50 million. 2
The following are key findings of the Chemical Safety Board’s (CSB) investigation:
1. The propane release was likely caused by the freeze-related failure of high-pressure piping at a control station that had not been in service for approximately 15 years. The control station was not isolated or freeze-protected but left connected to the process, forming a dead-leg. 3
Water in the propane accumulated in the low point formed by the control station and froze during cold weather prior to the incident, cracking an inlet pipe elbow. Ice sealing the failed pipe from the process melted as the air temperature rose on the day of the incident, releasing
4,500 pounds per minute of liquid propane, which ignited.
2. The refinery did not conduct a management of change 4 review when the control station was removed from active service in the 1990s. Consequently, the freeze-related hazards of the

1

The McKee propane PDA unit uses liquid propane as a solvent to separate gas oil from asphalt. The gas oil is fed to other units in the refinery for further processing. The asphalt is sold as paving material.

2

RMP submittal, December 2007.

3

A dead-leg is a section of piping connected to the process that has no flow through it.

4

Management of change is a systematic method for reviewing the safety implications of modifications to process technology, facilities, equipment, chemicals, organizations, policies, and standard operating practices and procedures.

6

Valero - Sunray

July 2008

dead-leg formed by the control station were not identified or corrected when the change was made. 3. The McKee Refinery’s freeze protection practices did not ensure that process units were systematically reviewed to identify and mitigate freezing hazards for dead-legs or infrequently used piping and equipment.
4. American Petroleum Institute (API) 5 -recommended safety practices for oil refineries do not provide detailed guidance on freeze protection programs, nor do they sufficiently stress freeze protection of dead-legs, or of infrequently used piping and equipment.
5. The rapidly expanding fire prevented field operators from closing manual isolation valves or reaching local pump controls to isolate the high-pressure propane being vented to the atmosphere. Control room operators were unable to shut off the flow of propane because remotely operable shut-off valves (ROSOVs) 6 were not installed in the PDA. The lack of remote isolation significantly increased the duration and size of the fire, resulting in extensive damage to the PDA, the main pipe rack, and an adjacent process unit.
6. API provides safety guidance for the use of ROSOVs in LPG storage installations, but does not address their use in refinery process units handling large quantities of flammable materials. Valero internal standards require the use of ROSOVs in such process units, but the
McKee Refinery had not retrofitted them in the PDA unit.

5

The API, an industry trade group, publishes recommended practices and standards widely used in the refining industry. 6

ROSOVs, also called emergency isolation valves (EIVs), are equipped with actuators and are configured to be quickly and reliably operated from a safe location, such as a well-sited control room.

7

Valero - Sunray

July 2008

7. Flame impingement on a non-fireproofed structural support caused a pipe rack to collapse, significantly increasing the size and duration of the fire, and led to the evacuation and extended shutdown of the refinery.
8. API-recommended practices and Valero standards for fireproofing do not provide sufficiently protective guidance for fireproofing distance for pipe racks near process units containing high-pressure flammables.
9. The exposure of three one-ton chlorine containers to radiant heating from the fire led to the release of approximately 2.5 tons of highly toxic chlorine, 7 which was used as a biocide in an adjacent cooling tower. Biocides that are inherently safer than chlorine are available.
10. A butane storage sphere was exposed to radiant heating that blistered its paint. The manual firewater deluge valve for the butane sphere was located too close to the PDA unit and could not be opened during the fire.
11. API-recommended practices do not require the evaluation of hazards posed by adjacent process units when specifying the design, operation, or location of firewater deluge valves.
12. The McKee Refinery’s Process Hazard Analysis was ineffective in identifying and addressing the •

risk of pipe failure due to freezing,



need for ROSOVs in the PDA unit to rapidly isolate LPG releases, and



hazards posed by fire exposure to neighboring equipment, including the chlorine ton containers and the butane storage sphere.

7

Chlorine has a permissible exposure limit (PEL) of 1.0 ppm, and is listed by the Environmental Protection Agency
(EPA) as an extremely hazardous substance (EHS).

8

Valero - Sunray

July 2008

This CSB report identifies root and contributing causes, and makes recommendations to Valero Energy
Corporation, Valero–McKee Refinery, the API, the United Steelworkers Union, and Steelworkers Local
13-487.

9

Valero - Sunray

July 2008

1.0 Introduction
1.1

Background

At 2:09 p.m. on Friday, February 16, 2007, liquid propane under high pressure was released in the
Propane De-Asphalting (PDA) 1 unit of Valero’s McKee Refinery, 50 miles north of Amarillo in the
Texas panhandle, near the town of Sunray. The resulting propane vapor cloud found an ignition source, and the subsequent fire injured workers, damaged unit piping and equipment, and collapsed a major pipe rack. The fire grew rapidly and threatened surrounding units, including a Liquefied Petroleum Gas (LPG) storage area. Fire-fighting efforts were hampered by high and shifting winds and the rapid spread of the fire. A refinery-wide evacuation was ordered approximately 15 minutes after the fire ignited.
Three of the four workers injured were seriously burned, including a contractor. The refinery was completely shut down for just under two months, and operated at reduced capacity for nearly a year.
Because of the serious nature of this incident, the U.S. Chemical Safety and Hazard Investigation Board
(CSB) launched an investigation to determine root and contributing causes and to make recommendations to help prevent similar incidents.

1.2

Investigative Process

The CSB investigators arrived at the McKee Refinery the morning of Sunday, February 18, 2007. The
CSB interviewed Valero and contractor personnel, reviewed company documents and data from the PDA unit’s computerized control system, examined physical evidence, and tested valves and piping components. The CSB investigation team was aided by experts in metallurgical analysis and highpressure flow testing. The investigation focused on the refinery’s programs to identify and address

1

The McKee PDA unit uses liquid propane as a solvent to separate gas oil from asphalt. The gas oil is fed to other

10

Valero - Sunray

July 2008

process hazards, and on the fire protection measures used in and around the PDA unit. Investigation activity was coordinated with the U.S. Occupational Safety and Health Administration (OSHA); the U.S.
Environmental Protection Agency (EPA); and the Texas Commission on Environmental Quality (TCEQ).

2.0 Valero Energy Corporation
2.1

Company History

Valero Energy Corporation was formed in 1980 as a natural gas-gathering company 2 based in San
Antonio, Texas. In the early 1980s, the company began expanding into the refining industry, and in 1997, separated its refining and marketing businesses into an independent company under the Valero name.
Valero Energy expanded rapidly in the late 1990s and early 2000s, as it acquired 16 U.S. refining facilities, as well as plants in Quebec, Canada; and Aruba. Valero Energy became North America’s largest refiner in 2005, operating 18 refineries 3 with capacity of approximately 3.3 million barrels per day
(bpd). In 2006 the company had assets of approximately $33 billion; annual revenues of $91.8 billion; and 21,800 employees. 4

2.2

McKee Refinery

The McKee Refinery in Sunray, Texas, was built in 1933 by Shamrock Oil and Gas Company. 5 Major unit upgrades were made in the 1950s, 1990s, and, most recently, in 2004. The refinery became part of

units in the refinery for further processing. The asphalt is sold for use in paving materials.
2

Gathering companies consolidate gas production from many natural gas wells into one or more large production pipelines for treating and distribution.

3

This number includes two separate plants (east and west) at one physical location. Since the February 2007 incident, Valero has divested its Lima, Ohio, refinery, bringing Valero’s total to 17.

4

Dunn & Bradstreet, Directory of Corporate Affliations, s.v. “Valero Energy Corporation,” dated Dec. 11, 2007, accessed Dec. 13, 2007.

5

Handbook of Texas Online, s.v. "Diamond Shamrock." http://www.tshaonline.org/handbook/online/articles/DD/hed6.html, accessed Jan. 2, 2008.

11

Valero - Sunray

July 2008

Valero in late 2001 when Ultramar Diamond Shamrock (UDS), the previous owner, merged with Valero
Energy.
On July 29, 1956, the McKee Refinery experienced a tragic workplace accident when a light hydrocarbon storage vessel failed catastrophically during a fire, resulting in the deaths of 19 emergency responders.
The refinery processes 170,000 barrels of crude oil per day, and distributes its products by pipeline to customers in Texas, New Mexico, Arizona, Colorado, and Oklahoma.

2.3

Propane Deasphalting (PDA) Unit

The PDA unit (Figure 1) recovered fuel feedstock and paving-grade asphalt from the heavy bottoms
(pitch 6 ) produced in the refinery’s vacuum crude oil fractionator. In the McKee PDA process, two liquid/liquid extraction towers used liquid propane as a solvent to extract gas oil 7 from the pitch under approximately 500 pounds per square inch (psi)(3,447 kPa) pressure. The recovered gas oil was processed into gasoline in another refinery unit. The asphalt produced was sold for use in paving materials. Figure 2 is a simplified process flow diagram for the No. 1 Extractor, including the location from which the propane was initially released.

6

Pitch is the heavy, viscous material discharged from the bottom of the vacuum fractionator after the lighter fractions have been removed – the heaviest hydrocarbon mixture produced from crude oil in the refinery.

7

Gas oil is a hydrocarbon mixture with molecular weight and viscosity somewhat higher than diesel.

12

Valero - Sunray

July 2008

Figure 1. PDA unit location in the McKee Refinery

The relatively dense pitch entered an upper section of the extractor and flowed to the bottom of the tower.
Less dense liquid “wash” propane entered a lower section and flowed to the top of the extractor. Internal structures in the tower promoted effective contact between the two streams. DeAsphalted Gas Oil
(DAGO) extracted from the pitch flowed out of the top of the tower with much of the propane. This liquid flowed through a series of flash drums 8 to remove propane from the gas oil. The DAGO was sent elsewhere in the refinery for processing.
A mixture of asphalt and propane flowed from the bottom of the extractor. This stream was also heated and flashed to remove entrained propane, and the asphalt sent to storage.

8

This is referred to as “flashing,” in which the pressure of a liquid mixture is suddenly reduced, causing light materials to vaporize, or “flash off,” separating them from heavier liquid components.

13

Valero - Sunray

July 2008

Figure 2. No. 1 Extractor simplified process flow diagram

Propane from the various flashing steps was condensed and sent to either the low- or high-pressure accumulators. Propane from both accumulators was pressurized by pumps, blended for temperature control, and recycled to the extractors. A small amount of makeup propane (about 0.5 percent of the circulating propane rate) entered the low-pressure accumulator to replace losses. Operators told the CSB investigators that the makeup propane contained a variable amount of entrained water, which was regularly drained from the low points on the accumulators. 9 Appendix A contains a more detailed process flow diagram of the PDA unit showing the major process flows and drainage points.

9

Many refinery streams normally contain small amounts of water.

14

Valero - Sunray

3.0

Incident Description

3.1

July 2008

The Incident

On Friday, February 16, 2007, at approximately 2:09 p.m., 10 plant personnel and contractors working in the PDA unit heard a “pop,” and saw what appeared to be steam blowing from a control station near ground level at the No. 1 Extractor tower. Plant personnel quickly determined that the escaping cloud was propane and directed workers in the area to evacuate.
The propane escaping from the high-pressure system formed a vapor cloud that traveled downwind toward the boiler house, where it likely ignited. 11 The flames flashed back to the leak source.
Surveillance video (Figure 3) shows the fire developing rapidly as flames impinged on piping around the
No. 1 Extractor, releasing additional propane.
A steel support column on the east/west (E-W) pipe rack was impacted by a high-pressure propane jet fire. The column, which was not protected by fireproofing insulation, buckled, collapsing the rack and causing multiple pipe failures. Liquid petroleum products discharged from the damaged pipes, contributing to the rapid spread of the fire and the damage caused to surrounding equipment, such as the
No. 2 Cooling Tower and No. 4 Naphtha Column.

10

The time of 2:09 p.m. is based on control system records examined after the incident.

11

Nearby fired heaters were another possible source of ignition.

15

Valero - Sunray

July 2008

Figure 3. Approximately 90 seconds after ignition (from surveillance video)

3.2

Injuries

Two Valero employees, who have since returned to work, and one contractor were seriously burned in the initial flash fire. The injured contractor continued to receive medical treatment for over a year after the incident. A member of the fire brigade received minor burn injuries while setting up fire-fighting equipment early in the response. Ten other Valero employees and contractors were treated for minor injuries and released. There were no fatalities and no reported off-site injuries.

3.3

Emergency Response and Refinery Evacuation

According to Valero’s incident response records, the fire alarm was activated at 2:10 p.m., about one minute after employees heard the “pop” of the initial release. The refinery’s emergency response team approached the fire, staging from the south. They attempted to activate stationary fire water monitors, but

16

Valero - Sunray

July 2008

the high and shifting winds and the rapid growth of the fire hampered their efforts.
Fifteen minutes after the fire erupted, managers at the Emergency Operations Center (EOC) ordered a total refinery evacuation. Refinery alarm records show that the evacuation alarm sounded at 2:26 p.m.
The EOC tactical operations director later stated that the main concerns driving the evacuation decision were the number of pressurized pipes rupturing as the pipe rack collapsed and the proximity of the responders to the liquid propane filled extractor vessels, which were engulfed in flames and possibly at risk of failing catastrophically. This decision pulled responders and workers away from a rapidly deteriorating situation that could have endangered many lives.
The refinery was shut down by isolating main feeds and the fuel gas supply. Emergency response teams later entered to isolate fuel sources, gradually shrinking the fire. Valero planned to stage a joint entry with responders from the nearby Conoco Phillips refinery 12 to extinguish the fire the following day; however, chlorine and sulfuric acid leaks 13 made this entry too hazardous. The fire was extinguished by Valero personnel on Sunday afternoon, February 18, 2008, approximately 54 hours after it ignited.

3.4

Aftermath

The refinery remained completely shut down for nearly two months. Media reports indicated spot shortages of reformulated gasoline in Denver, Colorado, 14 in the weeks immediately following the fire.
This incident occurred during a period when unplanned refinery outages kept approximately 480,000 bpd

12

Refineries often establish mutual aid agreements to increase the resources available for responding to large emergencies. 13

The chlorine and sulfuric acid were used to treat water circulating in a nearby cooling tower.

14

Reformulated gasoline contains a specified content of oxygenated fuels to meet EPA requirements for automotive emissions in certain regions. Valero’s McKee Refinery is located approximately 400 miles from Denver, and typically supplies, via pipeline, much of the gasoline consumed in the Denver market.

17

Valero - Sunray

July 2008

of capacity offline nationwide, of which 170,000 bpd was attributed to the McKee fire. 15 Operations resumed at reduced throughput roughly two months after the fire.
The PDA unit was heavily damaged (Figure 4). Much of the piping, control wiring, and heat exchange equipment in the area of the extractors was destroyed and major equipment items, including the extractor towers, required extensive evaluation to determine if they were safe for continued use. Valero restarted the rebuilt PDA unit in January 2008, nearly one year after the fire, restoring the refinery to full production capacity.

3.5

Near-Miss Events

The Center for Chemical Process Safety 16, 17 (CCPS) defines a near-miss as “an extraordinary event that could reasonably have been expected to result in negative consequences, but actually did not” (1992).
Two events during the February 16 fire could have resulted in serious, or even catastrophic, consequences if the wind direction had been different or if personnel had been nearby.

3.5.1

Butane Sphere Heat Exposure

At the time of the initial propane release, the wind was blowing from the west-northwest, pushing the fire in the general direction of the boiler house. Interviews, records, and security camera video footage indicate that the wind shifted several times during the fire, forcing the EOC to relocate.
Radiant heat from the intense PDA fire blistered the paint on a 10,000 barrel (420,000 gallon) capacity butane storage sphere located 270 feet northwest of the No. 1 Extractor (Figure 4). Fortunately, the wind

15

http://tonto.eia.doe.gov/oog/info/twip/twiparch/080221/twipprint.html; accessed Feb 2008.

16

The CCPS, an industry-sponsored affiliate of the American Institute of Chemical Engineers, publishes widely recognized process safety guidelines.

17

CCPS defines process safety as a “discipline that focuses on the prevention of fires, explosions and accidental chemical releases at chemical process facilities.” Process Safety Management (PSM) applies management principles and analytical tools to prevent major accidents (CCPS, 1992).

18

Valero - Sunray

July 2008

tended to move the flames away from the sphere; strong winds from the southeast might have greatly exacerbated the sphere’s thermal exposure. Even with favorable winds, heat from the fire kept responders from reaching the fire water deluge system valve for the sphere, preventing them from establishing a protective flow of water over its surface. During interviews, emergency responders indicated that they were concerned for the safety of the butane sphere, in light of a recent commemoration of the 1956 incident in which the failure of a vessel in similar service caused 19 fatalities.

Figure 4. Aerial photograph of damage from the PDA unit fire

19

Valero - Sunray

3.5.2

July 2008

Chlorine Release

Post-incident examination revealed that three one-ton chlorine containers in a cooling tower water treatment shed were subjected to radiant heating due to their proximity to the PDA unit (100 feet to No. 2
Extractor) and pipe rack (20 feet). All three containers vented when their fusible plugs, installed to prevent container rupture, melted as designed. One container ruptured despite the operation of its fusible plugs, and another vented completely. The third developed a leak through a partially melted plug that was repaired by emergency responders using self-contained breathing equipment for protection against the toxic vapor. More than 2.5 tons of chlorine, an extremely toxic material, were released. 18
Fortunately, emergency responders and other refinery personnel had pulled back from the area before the major chlorine release likely occurred. 19 There is no evidence that personnel on- or off-site were exposed to hazardous levels of chlorine gas. However, if responders had been nearby when the cylinders released their contents, significant exposures could have occurred.

4.0 Incident Analysis
This section provides detailed analysis of the sequence of events and causal factors leading to the origin and spread of the February 16, 2007, fire and its impact on adjacent equipment.

18

Chlorine has an OSHA PEL of 1.0 ppm; an NFPA toxicity rating of 4, the highest possible; and is listed by the
EPA as an EHS.

19

The CSB investigators could not precisely determine the time of release, but it was likely shortly after the collapse of the main E-W pipe rack, when a large pool fire burned just south of the chlorine container storage pad.

20

Valero - Sunray

4.1

July 2008

Incident Sequence

In this incident, water settling out of a propane stream likely leaked through a 10” NPS 20 (250 DN) inlet block valve and accumulated in the low point formed by a control station (Figure 5). The control station was connected to the process, but had not been used for approximately 15 years. A period of cold weather likely froze the water, fracturing the pipe elbow upstream of the control valve. Warmer weather then melted the ice, resulting in a release of highly pressurized liquid propane through the fractured elbow. Appendix B contains a detailed time line of the incident.

Figure 5. Propane mix control station schematic (not to scale)

4.1.1

February Cold Weather

National Weather Service records indicate that the Texas panhandle typically experiences periods of below-freezing weather during the winter, often in February. The 2007 cold snap began four days before the fire at the Valero-McKee Refinery, when temperatures dropped below 32°F and stayed below freezing for 87 hours. The average temperature in nearby Dumas, Texas, on February 14, 2007, was 26°F. A low temperature of 6°F was reached early in the morning of February 15. The temperature did not rise above

20

NPS refers to U.S. Nominal Pipe Size. Dimensions of NPS pipe and fittings are specified in the American Society of Mechanical Engineers (ASME) standard B36.10. The metric equivalent is given in millimeters, nominal diameter (DN).

21

Valero - Sunray

July 2008

freezing until the morning of February 16, approximately five hours before the incident (Weather
Underground, 2007).

4.1.2

Propane Mix Control Station Inlet Elbow Freezing and Failure

The 6” NPS (150 DN) propane mix control valve originally mixed liquid propane into the pitch fed into the No. 1 Extractor. Due to a change in extractor control in the 1990s, use of the control valve was discontinued; however, this subsection of the No. 1 Extractor was left connected to the process under high pressure. 21 The block valves around the control valve were closed, but the subsection was not removed or positively isolated from the process using slip blinds. 22 The refinery conducted no formal process safety management of change (MOC) review of this idled control station. 23
The station’s configuration made it a dead-leg: a section of piping connected to the process with no flow through it. Water in the propane likely sank into the dead-leg, leaked by the inlet block valve, and accumulated in the control station piping. 24
The extended period of cold weather and the lack of freeze protection on the control station allowed the water to freeze and expand, cracking the elbow upstream of the control valve. The crack propagated along the inner radius of the elbow, the line of highest stress (Timoshenko , 1958), opening wider as it developed (Figure 6). Appendix C contains a more detailed discussion of the CSB’s analysis of crack formation and propagation. The damage to the inlet elbow and the post-incident leak rate determined for the inlet block valve are consistent with the estimated initial propane release rate during the incident.

21

Senior operators in the PDA unit could not recall the exact time the control valve was last used. The change in extractor control occurred approximately 15 years before the incident.

22

Slip blinds are solid pieces of metal inserted between flanges to positively isolate piping or equipment.

23

MOC requires that changes to equipment, process, or design intent be reviewed for safety implications. It is a required element of OSHA’s Process Safety Management regulation, promulgated in 1992, and an element of API
Recommended Practice 750, Management of Process Hazards, published in 1990.

24

Water, which is insoluble (immiscible) in and denser than liquid propane, was known to be present in the propane.
Water droplets entrained in propane can accumulate in the bottom of piping and vessels.

22

Valero - Sunray

July 2008

Figure 6. Crack in the 10” diameter propane mix control station inlet elbow

4.1.3

Thaw and Propane Release

On February 16, 2007, shortly after 9:00 a.m., ambient temperatures rose above freezing and the ice inside the elbow began to thaw. Post-incident examination of the control station inlet block valve (Figure
7) revealed that a foreign object was jamming the valve, 25 creating a leak path. When tested in a laboratory after the incident, this valve allowed over 1,025 gpm (233 m3/hour) of water to leak through at process pressure. At approximately 2:09 p.m., melting ice opened the leak path, releasing liquid propane at 500 psig (3,447 kPa) pressure through the cracked elbow. A flammable vapor cloud rapidly formed.
Based on recorded data from the PDA unit’s computerized control system, the CSB estimated an initial propane leak rate of 4,500 pounds (2,040 kg) per minute (Appendix D describes the propane mass balance calculations used to develop this figure).

23

Valero - Sunray

July 2008

Figure 7. Downstream view of propane mix control station inlet block valve

The wind blew the propane cloud toward the boiler house, where it likely ignited. 26 The flames flashed back to the release point. The size and intensity of the resulting fire blocked access to manual shut-off valves and pump on-off switches that might otherwise have been used to control the propane discharge.
Within minutes, the fire damaged piping and pipe rack supports, spreading the fire (Figures 4, 8, 9).

25

In gate valves, a circular gate slides against metallic seat rings, providing a leak-tight seal when the valve is closed. The foreign object in the inlet gate valve prevented a tight fit between the gate and the seat rings.

26

While the boiler house was the most likely source of ignition, nearby fired heaters could not be ruled out.

24

Valero - Sunray

July 2008

Figure 8. Damaged 10” propane inlet on Extractor No. 1

4.2

Dead-Leg Freeze Protection

The initial release of propane was due to the McKee Refinery’s failure to recognize and address the freezing hazard posed by the propane mix valve control station dead-leg.

4.2.1

Dead-Leg Not Recognized or Addressed

The McKee Refinery had not identified the station as a dead-leg. A piping and instrumentation drawing
(P&ID) update project for the PDA unit, completed in 2006, identified only dead-legs that were visually apparent, such as one formed when a control valve was physically removed and its flanged connections slip-blinded. However, the P&ID update did not detect the propane mix control station dead-leg, which was formed by closing block valves in the piping.

25

Valero - Sunray

July 2008

A Process Hazard Analysis (PHA) 27 performed on the PDA unit in 2006 did not examine freezing as a threat to piping integrity. Furthermore, the McKee Refinery’s freeze protection program did not periodically survey process units for potentially freeze-prone dead-legs.

4.2.1.1

Inherently Safer Approach

According to safety guidance by the CCPS in Inherently Safer Processes, A Life Cycle Approach (1996), the preferred way to control hazards is to eliminate them where possible. According to Lee’s Loss
Prevention (2005), the best approach for managing dead-legs, such as the propane mix control station, is to remove them. If removing them is impractical, other approaches, in order of decreasing protective value, could include 1) positively isolating the dead-leg by installing slip blinds; 2) freeze-protecting them; or 3) procedures to regularly monitor and drain water from low points.

4.2.2

McKee Refinery Freeze Protection Program

Sunray, Texas, is in the north Texas panhandle, an area where below-freezing temperatures are common in February. Valero’s McKee Refinery protected piping and equipment from freezing by insulating and
“tracing” with steam-filled tubing or electric heat tape. 28 It was an unwritten practice to review and repair freeze protection components every fall. However, these activities focused on maintaining existing freeze protection measures, not on periodically reviewing units for dead-legs or other idle/infrequently used piping systems, or surveying process units for areas where water could collect.
The refinery’s inspection program contained provisions for more frequent inspection of identified deadlegs, but these focused on identifying long-term corrosion issues, not acute freeze hazards. Freeze

27

OSHA defines a PHA as a “thorough, orderly, systematic approach for identifying, evaluating, and controlling the hazards of processes involving highly hazardous chemicals.” PHAs must be updated and revalidated at least every five years under the Process Safety Management regulation 29 CFR 1910.119.

28

Heat tracing involves providing a source of heat along the length of a pipe, usually by attaching or wrapping steam tubing or heating tape to or around the piping, and then insulating the protected piping.

26

Valero - Sunray

July 2008

protection is both a mechanical integrity (inspection) and operational issue, and requires an integrated approach. 4.2.3

Valero Corporation Freeze Protection Survey

Following the McKee fire, Valero surveyed the freeze protection programs at its US refineries. Most of the refineries in freeze-prone areas had informal programs similar to McKee’s, while several had legacy freeze protection guidelines from previous owners. Valero did not have a corporate policy for freeze protection to set minimum standards for freeze protection programs at its facilities.

4.2.4

Other Dead-Leg and Freeze-Related Incidents

In a 2002 brochure, Understanding the Hazard: Freeze, FM Global 29 cited “151 freeze incidents in industry with an average estimated gross loss of about $115,000 per incident from 1991 to 2000.” The following is a sampling of specific incidents identified by the CSB:


January 1962, Texas City, TX: An entire refinery was crippled and major process units shut down when the area experienced temperatures below freezing for 66 hours: “Dead-end water lines and steam lines froze, causing valves to break and some pipes to split”(API Publication 758,
1983).



March 1979, Exxon, Linden, NJ: Seven injured when butane and propane released from a deadleg formed a large vapor cloud and exploded (Garrison, 1985).



February 1996, Total Petroleum, Denver, CO: Abandoned pump gland oil piping under process pressure froze and then burst above a vacuum bottom pump, causing a fire (Denver Post, June 28,
1996).

29

FM Global, a large process industry insurer, has developed widely used guidance documents.

27

Valero - Sunray



July 2008

February 2001, Bethlehem Steel, Burns Harbor, IL: Freezing in a dead-leg condensate line near a coke oven led to two fatalities and four injuries (CSB 2001-02-I-IN , 2002).



January 2008, Chevron, Pascagoula, MS: A freeze-related fire was reported at the refinery. This fire is an example of incidents where freezing temperatures occur occasionally, but not consistently during the winter (AP, January 3, 2008).

The IChemE 30 BP Process Safety Series publication, Hazards of Water, also lists numerous examples of process incidents related to water freezing.

4.2.5

Available Industry Guidance

FM Global’s Freeze brochure (2002) describes the risk and provides guidance for evaluating susceptible piping systems, with particular emphasis for facilities in regions where the risk of freezing weather is intermittent. The brochure provides general guidance for mitigating the hazard, but does not describe the specifics of freeze protection programs. However, FM Global has also published a Property Loss
Prevention Data Sheet, Prevention of Freeze-Ups, (2007, latest edition) that does give guidance for establishing and maintaining freeze protection programs.
Zurich, another major insurer, has published a cold weather checklist that tells users to “drain the vessels and piping of idle equipment”(Zurich, 2003).
The CSB reviewed available publications by the API, an industry group that publishes voluntary standards, and found no detailed guidance for refineries on establishing effective freeze protection programs. 31

32

30

The Institute of Chemical Engineers (IChemE) is a UK engineering professional organization that publishes widely referenced process safety guidance.

31

API publication Safety Digest of Lessons Learned, Section 9, Precautions Against Severe Weather Conditions, which provided general guidance for preparing a refinery for extreme cold weather, is no longer in print.

28

Valero - Sunray

4.3

July 2008

Fireproofing

A non-fireproofed structural support for a pipe bridge 33 spanning a 90-foot wide open area north and east of the PDA unit (Figure 9) collapsed early in the incident, greatly increasing the magnitude of the fire.
The support was located on a major E-W pipe rack north of the unit, outside the fireproofing distances recommended by API guidance and Valero internal standards. The collapse opened multiple lines carrying flammable and combustible materials from other areas of the refinery, contributing significantly to the damage experienced by adjacent units, and extending the time that the refinery was down for repairs. Fireproofed pipe rack support steel columns inside the PDA unit and at the No. 4 Naphtha
Column all survived the fire without collapsing (Figure 10).
Fireproofing is “fire resistant insulating material applied to steel to minimize the effects of fire exposure by flame impingement, to reduce the steel’s rate of temperature rise, and to delay structural failure”(API
Publication 2510A, 1996). Without fireproofing, exposed structural steel members, such as pipe rack support columns, can rapidly lose their strength and fail, possibly within minutes (API 2218, 1999; CCPS,
2003). Jet fires, such as the pressurized LPG release in this incident, can cause very rapid heating and failure of unprotected structural steel (Appendix E).

32

API 570, Piping Inspection Code, mentions a variety of hazards associated with dead-legs, including freezing.
API Recommended Practice 2001, Design and Construction of LPG Installations, discusses the importance of winterization and prevention programs in verifying that out-of-service piping and dead-legs are freeze-protected.
However, neither document addresses freeze protection management systems, such as requirements for a formal written program or the need for periodic inspections to identify freeze hazards, which pertain to this incident.

33

A pipe bridge is a reinforced section of a pipe rack that carries piping over a longer than normal span.

29

Valero - Sunray

July 2008

Figure 9. Pipe bridge support fireproofing
Fireproofing is a passive defense that can maintain the integrity of protected structures until a fire is controlled. According to Nolan (1996), “The primary value of fireproofing is obtained in the very early stages of a fire when efforts are primarily directed at shutting down [the] process, isolating fuel supplies to the fire…and conducting personnel evacuations.”
Key guidance for fireproofing in refineries is API Publication 2218, Fireproofing Practices in Petroleum and Petrochemical Processing Plants. API Publications 2510, Design and Construction of LPG
Installations, and 2510A, Fire-Protection Considerations for the Design and Operation of Liquefied
Petroleum Gas (LPG) Storage Facilities, provide additional information on fireproofing in LPG 34 storage facilities. 35 These publications recommend fireproofing pipe rack support steel that is 20 to 40 feet from fuel sources for general refinery service, and up to 50 feet from LPG vessels.

34

LPG includes the following light hydrocarbons and mixtures: propane, propylene, normal and iso-butane, and butylenes (API Standard 2510, 2001). These materials are all commonly handled as liquefied gases under pressure. 35

LPG storage facilities are commonly found in refineries, including the McKee Refinery, which had four storage spheres northwest of the PDA unit.

30

Valero - Sunray

July 2008

Valero Energy Corporation’s SP-00-04, Fire Proofing Specifications, calls for fireproofing pipe racks within 30 feet of equipment with the potential to cause a serious fire, but makes no special provisions for processes handling LPG. A loss-prevention report produced for the McKee Refinery listed fireproofing of pipe rack support steel, including the E-W pipe rack north of the PDA unit, as a top priority for the site fireproofing program, but the rack had not been fireproofed at the time of the incident.

Figure 10. Extractor towers (upper right) and collapsed pipe rack

A failed inlet flange to the No.1 Extractor, located 77 feet away from the buckled pipe bridge support, was the most likely source of the jet fire that collapsed the pipe bridge (Figure 11). The closest major process vessel (the No. 2 Extractor) was 51 feet away from the support. These distances exceed both
API’s and Valero’s recommended fireproofing distances.

31

Valero - Sunray

July 2008

Figure 11. Distances between the E-W pipe rack supports and the extractors

API 2218 references the API 2210/2210A LPG fireproofing distance of 50 feet, developed for pool fires in LPG storage units. Neither standard addresses fireproofing for LPG processes or jet fire scenarios, even though process unit conditions, including pressure, can be more extreme than those found in storage facilities. In this incident, the high operating pressure of the extractors (500 psig, 3,447 kPa) likely produced a jet fire with a range and intensity beyond that anticipated in the API standards for LPG storage releases. In the Formosa–Point Comfort, Texas, propane/propylene fire in October 2005 that the CSB investigated, non-fireproofed steel columns supporting a critical structure also collapsed while adjacent fireproofed supports survived without damage (CSB 2006-01-I-TX, 2006). If the E-W pipe rack support columns in

32

Valero - Sunray

July 2008

this incident had been fireproofed, the severity and duration of the fire would likely have been greatly reduced. 36

4.4

Emergency Isolation and Shutdown

Although the PDA unit contained large inventories of high-pressure propane, it was not equipped with remotely operable shut-off valves (ROSOVs) 37 to rapidly stop propane releases. ROSOVs should be used in facilities, such as the PDA unit, where fast and effective isolation is needed to reduce the impact of major hazardous releases (HSE, 1999).

Graphic based on FM Global Property Loss Prevention Data Sheet 7-14, 2004

Figure 12. Insurer-recommended locations for ROSOVs

36

Jet fire scenarios may require the use of fireproofing rated for longer fire exposure and greater resistance to erosion than might be required for protection in pool fire scenarios.

37

ROSOVs, also referred to as EIVs, are equipped with actuators and configured to be quickly and reliably operated from a safe location, such as a well-sited control room.

33

Valero - Sunray

July 2008

Figure 12 shows insurer-recommended ROSOV locations for a typical process unit. ROSOVs should be installed on large inventories of highly flammable materials, 38 especially when downstream pumps are present that could produce pressurized releases. Such pumps should be interlocked to shut down when
ROSOVs are closed.

4.4.1

American Petroleum Institute (API) Guidance

API’s Recommended Practice 2001, Fire Protection in Refineries and API 2030, Application of Fixed
Water Spray Systems for Fire Protection in the Petroleum Industry, discuss the use of isolation valves in emergencies, including considering access to valves during fires. However, while these recommended practices briefly reference remotely operable isolation valves, they focus on fire- and heat-actuated valves and their limitations. The 2007 release of API 521, Pressure-relieving and Depressuring Systems, addresses the limitations of pressure relief systems in protecting against jet fires, and states that “unlike a pool fire, a jet fire can, in essence, be ‘turned off” through isolation and depressurization of the jet fire source...” 39 However, none of these guidance documents provide specific guidance on the design, location, and use of ROSOVs for the rapid isolation of LPG processes during emergencies.

4.4.2

Valero Corporate Emergency Isolation Valve (EIV) Standard

Valero’s Emergency Isolation Valve Standard (SP-40-01) requires evaluation and installation of ROSOVs during new construction projects, and application of the standard during PHA revalidations in existing

38

Guidance varies on appropriate threshold quantities for installing ROSOVs. Valero’s corporate procedure gives highest priority to installing ROSOVs on vessels containing more than 10,000 pounds of LPG-like materials
(NFPA Class 4 flammables), such as propane. One insurer recommends ROSOV use on flammable inventories greater than 4 m3 (4,225 gallons) in volume. The UK’s Health and Safety Executive (HSE) recommends installing the capability to physically isolate “large” inventories of hazardous substances.

39

API 521 (5th ed.) also highlights the need for an integrated approach to mitigating jet fire hazards, including fireproofing and other measures in addition to emergency isolation capability. However, it does not provide detailed guidance.

34

Valero - Sunray

July 2008

process units, such as the PDA. 40 The standard specifies giving the highest priority to installing EIVs on vessels containing 10,000 pounds or more of National Fire Protection Association 41 (NFPA) Class 4 materials, such as propane. 42 The CSB confirmed that both the high- and low-pressure accumulators (as well as the extractors) could contain well over 10,000 pounds of propane under normal operating conditions, 43 yet neither was equipped with ROSOVs nor was SP-40-01 applied as required during the
2006 PDA unit PHA revalidation. A UDS PHA in 1996 had identified the need for ROSOVs in the PDA unit; however, they were never installed, and the action item was incorrectly closed out as having been completed. 4.4.3

Formosa–Point Comfort, Texas, Incident

In a similar incident in 2005 involving an uncontrolled release of LPG (CSB-2006-I-TX), operators were also unable to reach locally operated valves to isolate the fuel source of the fire. The resulting fire extensively damaged Formosa Plastics Corporation’s Point Comfort, Texas, Olefins 2 unit. In both the
Formosa and Valero incidents, the use of ROSOVs would have enabled operators to quickly control the initial releases, prevent the rapid spread of the fires, and mitigate the serious damage that occurred.

5.0 Near-Miss Analysis
Near-misses are extraordinary events that could reasonably have been expected to result in negative consequences, but actually did not. Examples of near-misses include releases of flammable vapors that

40

OSHA’s PSM regulation requires PHAs to be periodically “updated and revalidated.” CCPS (2001) states that
PHAs are revalidated to “produce an updated PHA that adequately identifies, evaluates, and proposes controls for the hazards of the process, as they are currently understood.”

41

The NFPA develops widely recognized consensus fire protection codes and standards.

42

The NFPA classifies the degree of hazard of a material on a scale of 0-4, with 4 the most hazardous or “severe.”
Class 4 flammable materials are defined as either gases or materials that will flash to a gas at ambient temperature, such as LPG. The 10,000 pound criterion in the Valero standard applies to either the mass of a single Class 4 material or to the Class 4 components of a mixture.

43

Based on control system data and field measurements of the vessel diameters.

35

Valero - Sunray

July 2008

dissipate without igniting, activation of safety protective and shutdown systems, and process conditions that exceed predefined control limits (CCPS, 1992).
In this incident, two near-misses resulted from the exposure of nearby equipment to radiant heating by the fire. While no injuries or serious damage resulted, under slightly different circumstances the consequences could have been much more serious, even catastrophic.

5.1
5.1.1

Chlorine Release
Damage to Chlorine Containers

Three one-ton containers of highly toxic 44 liquid chlorine, used in cooling tower water treatment, were located in a shed approximately 100 feet from the PDA unit (Figure 4). The fire exposed the containers to radiant heating, rupturing one (Figure 13) despite the melting of its fusible plugs, and causing the other two to vent chlorine through their melted plugs. 45 Valero reported to the Texas Commission for
Environmental Quality (TCEQ) that 5,332 pounds of chlorine were released (see Section 7.2).
Fortunately, responders had pulled back from the area prior to the release and no injuries were attributed to chlorine exposure.

44

The NFPA rates chlorine’s health risk as a “4,” the most hazardous rating.

45

Fusible plugs are safety devices that use metal alloys that melt at comparatively low temperatures, in this case roughly 155oF (68oC) to vent containers exposed to excessive heating. The one-ton container that ruptured was likely exposed to an extremely high radiant heat flux, causing the container wall to weaken due to overtemperature and fail before its contents could be vented through the fusible plugs.

36

Valero - Sunray

July 2008

The cooling tower water treatment shed served the No. 2 Cooling Tower, directly to the north; however, the shed did not need to be located next to the PDA unit and pipe rack. Furthermore, the PHA for this system had not examined the hazards of locating the chlorine containers close to the PDA unit.
Following the incident the refinery rebuilt the treatment system, using bleach as the biocide, on the north side of the cooling tower.
Chlorine was used at the McKee Refinery to prevent microbial growth in cooling water; however, its toxicity made it an inherently hazardous material to work with. 46 The release of the contents of a single one-ton container of chlorine can create toxic effects up to three miles away, presenting a serious risk to workers and the public. 47

5.1.2

Inherently Safer Alternatives

In applying inherent safety principles, 48 the preferred approach to control hazards is to eliminate them.
However, if elimination is not feasible, replacing hazardous materials with less dangerous ones
(substitution) should be examined (CCPS, 1996). This basic principle was described by noted process safety expert Trevor Kletz, who stated that “what you don’t have can’t leak” (1998).

46

The EPA’s toxic endpoint for chlorine release modeling (the Emergency Planning Response Guideline-2 concentration) is 3 ppm. The National Institute for Occupational Safety and Health (NIOSH)-recommended exposure limit is 0.5 ppm.

47

Based on the CSB runs of the EPA’s “RMP Comp” software, v. 1.07, 2,000 pound release, RMP worst case, rural area (appropriate for the McKee Refinery’s location).

48

“A chemical manufacturing process is inherently safer if it reduces or eliminates the hazards associated with materials and operations used in the process, and this reduction or elimination is permanent and inseparable” (CCPS,
1996).

37

Valero - Sunray

July 2008

Figure 13. Ruptured one-ton chlorine container

Safer materials for controlling biological growth in cooling towers are available, and Valero has identified replacing chlorine in cooling water treatment at all its refineries as a safety goal in its 2008-2012 Strategic
Plan. The plan noted that 10 of its 18 refineries (as of May 2007) used ton container quantities of gaseous chlorine as a cooling water biocide. The McKee Refinery substituted sodium hypochlorite (bleach) for chlorine in its No. 2 Cooling Tower during PDA unit reconstruction. Bleach essentially stores chlorine in a form that presents a much lower inhalation hazard, an example of the inherently safer principal of attenuation (Kletz, 1998). 49, 50

5.2
5.2.1

Butane Sphere Deluge Valves
Heat Damage to Butane Sphere

Four 10,000 barrel (420,000 gallon, 1590 m3) spherical tanks storing LPG were located northwest of the
PDA unit (see Figure 4, page 19). At the time of the incident, the tank closest to the PDA unit contained

49

Kletz states, “The worst that can happen with hypochlorite is far less than the worst effects of chlorine, and on balance the change seems justified.”

38

Valero - Sunray

July 2008

approximately 3,600 barrels (151,000 gallons, 572 m3) of liquid butane under pressure, and was exposed to radiant heat from the fire. Figure 14 shows heat damage to the white protective coating on the tank’s exterior. Figure 14. Heat-damaged coating on sphere and location of sphere deluge valves

Analysis of the overall effects of the fire revealed significant vessel damage as far as several hundred feet away from the PDA unit, generally downwind from the initial release, and including the insulated No. 4
Naphtha Column. Although the wind shifted several times during the fire, it never blew strongly from the southeast, which would have directed the flames toward the uninsulated butane sphere. Exposure to direct flame impingement or to significant heating over a prolonged period might have resulted in a vessel failure with potentially catastrophic consequences.

50

Using bleach requires chlorine handling at the bleach production facility.

39

Valero - Sunray

July 2008

Emergency responders were unable to reach the fire water deluge valves intended to protect the butane sphere (Tank 195) from excessive heating due to fire exposure. These manual valves were located under a pipe rack north of the PDA unit (Figure 14), and were too close to the fire to be safely approached.
While the butane sphere was equipped with pressure relief devices, these primarily protect against the effects of pool fires on the liquid filled (wetted) portion of the sphere. In a pool fire, the liquid butane boils, cooling the wall of the sphere and generating vapor that would vent through the relief system. 51
The vapor-filled section of the sphere facing the PDA fire had no liquid to provide cooling, and could be protected against excessive heating only by applying water to the external surface via the deluge system.
Without deluge protection, the sphere was vulnerable to possible failure through loss of metal strength due to over-temperature. While favorable winds limited the sphere’s thermal exposure during this incident, the inability of operators to reach the deluge valves to establish water flow over the sphere was nonetheless a serious failure of the butane sphere’s fire protection system.
API standards do not require refineries to evaluate hazards from nearby units when locating fire water deluge valves, and Valero’s PHA for the LPG spheres did not examine the possibility that a fire could block access to the valves. 52

5.2.2

Effective Deluge Valve Operation

API Standard 2510, Design and Construction of LPG Installations, provides guidance on the design of
LPG storage systems, and includes details on deluge system requirements for fire protection. API 2510 specifies the use of manual deluge valves, such as the ones used for the LPG spheres, and specifically

51

API 521, Pressure-relieving and Depressuring Systems, describes the design and application of pressure relief systems for pool fire scenarios.

40

Valero - Sunray

July 2008

allows the use of automatic or remotely operated valves 53 only if the tanks are unattended or partially attended, which was not the case at the McKee Refinery.
Had the butane sphere deluge valve been remotely operable from a safe location at the time of the incident, emergency responders could have activated the water deluge system, greatly reducing the likelihood of a catastrophic vessel failure in the event of an unfavorable shift in wind direction.

6.0 Process Hazard Analysis (PHA)
PHA is a formal method for identifying process hazards. The PDA unit PHA revalidation performed in
2006 did not address hazards that were causal to the February 16, 2007, incident. Furthermore, the PHAs performed on the water treatment system and the LPG storage spheres did not rigorously examine siting issues causal to the two near-miss incidents discussed in section 5.0.
The CSB identified several areas where the McKee Refinery’s 2006 PDA unit PHA was ineffective in identifying hazards that contributed to the February 16, 2007, incident:


As documented in section 4.2.1, the process safety information developed for the PDA unit
PHAs did not identify the propane mix control station as a dead-leg, which could be subject to freezing. Identifying and addressing this dead-leg could have prevented the propane release. •

The node size selected for the “HAZOP” PHA method 54 used was too large, which can lead to inadequate review of node components. In this case, the large node size likely led to the propane mix control station not being reviewed.

52

However, OSHA’s PSM compliance directive (CPL2-2.45A, Appendix B) addresses automating deluge valves to improve protection when process units are closely spaced.

53

Automatic deluge valves are opened by a control system based on sensor input, such as high temperature or the presence of flammable concentrations of LPG. Remotely operated valves can be opened by facility personnel from a safe location.

41

Valero - Sunray



July 2008

According to CSB interviews, the 2006 PHA did not effectively engage the operators in the review process; rather, the contract facilitator performed most of the analysis. Involving the operating staff directly in the PHA process is a key to performing an effective PHA.



As documented in section 4.4.2, the 2006 PHA did not apply Valero Emergency Isolation
Valve standard SP-40-01 to identify locations requiring ROSOVs. Installing these valves on the propane accumulator vessels would likely have greatly reduced the severity of the incident. •

The PHA did not revisit recommendations from earlier PHAs to confirm that they had been properly implemented. As a result, the 1996 recommendation that ROSOVs be installed in the PDA unit was not reviewed.

Furthermore, as discussed in sections 5.1 and 5.2, the PHAs for the water treatment system and the
LPG storage spheres did not address the potential for fire exposure from the adjacent PDA unit. The
OSHA PSM regulation specifically requires consideration of siting issues when performing PHAs.
Exposure of chlorine containers and LPG storage tanks to heating from fires is a well-recognized hazard. PHAs are an important component of a PSM system. Guidance on performing effective PHAs is available; examples include Guidelines for Hazard Evaluation Procedures, (2nd ed.), and
Revalidating Process Hazard Analyses, both from CCPS, and HAZOP Guide to Best Practice from the European Process Safety Center, among others.

54

For the HAZOP (hazard and operability study) PHA methodology used in this PHA, a “node” is a section of equipment with definite boundaries (e.g., a line between two vessels) within which process parameters are investigated for deviations (CCPS, 1992).

42

Valero - Sunray

July 2008

7.0 Regulatory Analysis
The OSHA PSM (29 CFR 1910.119) and the EPA Risk Management Program (RMP - 40 CFR Part 68) regulations both aim to reduce the risk of catastrophic releases of hazardous chemicals. The PSM standard addresses employer requirements to implement effective PSM programs to protect workers.
RMP incorporates the elements of PSM and adds requirements for evaluating off-site consequences, emergency response, and community outreach. These regulations apply to processes containing hazardous materials above specified threshold quantities. The PDA and LPG storage areas were covered under both regulations, as they contained more than the specified threshold quantity (10,000 pounds) of flammable propane or butane. The cooling water treatment system was also covered under both, as it contained an above threshold quantity (1,500 pounds for PSM; 2,500 pounds for RMP) of chlorine gas.

7.1

OSHA Process Safety Management

The PSM regulation is performance-based and requires companies with covered processes to implement programs addressing 12 key elements, many of which are mutually supporting. As discussed in section
4.0, the CSB investigation found causal deficiencies in several elements of the McKee Refinery’s PSM program, including:


Process safety information – the propane mix control station was not identified as no longer in use or as a dead-leg freeze hazard.



PHA – the PDA unit piping was not reviewed for freeze rupture, Valero’s ROSOV procedure was not applied, and chlorine container siting issues were not considered.

7.2

EPA Risk Management Program (RMP)

The RMP regulation requires that covered facilities implement an RMP that includes hazard assessment, prevention program, and coordinated emergency response elements. Facilities such as Valero’s McKee

43

Valero - Sunray

July 2008

Refinery must prepare an RMP, submit it to the EPA, and periodically update it.
The McKee RMP included an estimate of the worst-case scenario for a toxic chemical release; a release of one ton of pressurized chlorine gas (a single one-ton container) from the water treatment facility with a toxic endpoint distance of three miles. Slightly over 2.5 tons of chlorine were estimated to have been released from the three co-located containers impacted by the fire. 55

7.3

Regulatory Enforcement History

Federal OSHA administers and enforces worker safety and health standards in Texas. OSHA had inspected the McKee Refinery twice under Valero’s ownership; however, neither inspection was PSMoriented. 56 Based on its investigation of this accident, OSHA issued three serious citations 57 to Valero for violating the PSM standard with proposed penalties of $21,000; one citation was related to the PHA, and two to the “Mechanical Integrity” elements of the PSM regulation. An informal settlement agreement 58 between Valero and OSHA resulted in one of the “serious” citations being reclassified as “other,” and a penalty reduction to $15,000, along with a stipulation that the refinery would, “as a voluntary hazard recognition measure[,]…adopt measures to manage `dead-legs’ within piping systems.”
The McKee Refinery had not been audited by the EPA prior to the February 2007 incident. While the
EPA responded to the fire, it did not investigate the refinery’s RMP compliance after the incident.

55

EPA guidance requires companies to consider releases from co-located vessels. General Guidance for Risk
Management Programs (40 CFR Part 68), Office of Solid Waste and Emergency Response, EPA-550-B-00-008,
May 2000, page I-8.

56

www.osha.gov/pls/imis.

57

OSHA, Citation and Notification of Penalty, Diamond Shamrock Refining Company, L.P., dba Valero - McKee
Refinery, Inspection Number 310690086, August 13, 2007.

58

OSHA, Informal Settlement Agreement, Diamond Shamrock Refining Company, L.P., dba Valero - McKee
Refinery, OSHA Inspection No. 310690086, September 4, 2007.

44

Valero - Sunray

8.0

July 2008

Root and Contributing Causes

The CSB’s investigation determined the following root and contributing causes 59 :

8.1

Root Causes

1. The McKee Refinery had no formal written program in place to identify, review, and freezeprotect dead-legs or infrequently used piping and equipment, such as the propane mix control station. 2. The McKee Refinery did not apply Valero’s mandatory Emergency Isolation Valve procedure when evaluating risks in the PDA unit to ensure that the large quantities of flammable materials in the unit could be rapidly isolated in an emergency.
3. API guidance and Valero’s corporate Fire Proofing Specifications standard do not specify sufficiently protective distances for fireproofing pipe rack support steel for processes handling high-pressure flammables, such as the LPG in the PDA unit.

8.2

Contributing Causes

1. API-recommended practices on locating and operating LPG firewater deluge valves do not address potential hazards from nearby processes.
2. Valero–McKee Refinery’s hazard assessment process did not recognize the risk of using chlorine in close proximity to equipment handling flammable hydrocarbons.

59

Appendix F contains an event tree used to help develop root and contributing causes.

45

Valero - Sunray

9.0

July 2008

Recommendations

American Petroleum Institute (API)
2007-05-I-TX-R1

Issue API-recommended practices for freeze protection in oil refinery process units that include, as a minimum:


the establishment of a written program;



periodic inspections to identify freeze hazards in dead-legs or infrequently used piping and equipment where water could collect;



specific approaches to eliminate or protect against such freeze hazards; and



identification of infrequently used piping or equipment subject to freezing as a trigger for Management Of Change (MOC) reviews.

2007-05-I-TX-R2

Revise API 2218, Fireproofing Practices in Petroleum and Petrochemical
Processing Plants, so that conformance with the standard addresses jet fire scenarios, and requires more protective fireproofing radii and other measures
(e.g., emergency isolation valves, depressuring systems) for pipe rack support steel near process units containing highly pressurized flammables.

2007-05-I-TX-R3

Revise API Recommended Practice 2001, Fire Protection in Refineries, and API
2030, Application of Fixed Water Spray Systems for Fire Protection in the
Petroleum Industry, so that conformance with these recommended practices includes the design, installation, and use of ROSOVs and interlocked equipment controls to enable the safe and rapid emergency isolation of process equipment containing highly pressurized flammables.

2007-05-I-TX-R4

Revise API Standard 2510, Design and Construction of LPG Installations,, and
API Publication 2510A, Fire-Protection Considerations for the Design and
Operation of Liquefied Petroleum Gas (LPG) Storage Facilities, to address effective deluge system activation during emergencies originating in nearby process units.

46

Valero - Sunray

July 2008

Valero Energy Corporation
2007-05-I-TX-R5

Identify all processes in this and other refineries where Valero’s mandatory
Emergency Isolation Valve standard is applicable, and ensure that Remotely
Operable Shut-off Valves (ROSOVs) are installed to control large accidental releases of flammable materials.

2007-05-I-TX-R6

Establish corporate requirements for written freeze protection programs at Valero refineries subject to freezing temperatures, including identification, mitigation,
MOC, and audit requirements.

2007-05-I-TX-R7

Revise Valero standards, including Fire Proofing Specifications, to require evaluation of jet fire scenarios and, as a minimum, ensure more protective fireproofing for pipe rack support steel near process units containing highly pressurized flammables.

2007-05-I-TX-R8

Audit PHA performance at its refineries to ensure adherence to company standards and good practice guidelines.

2007-05-I-TX-R9

Implement Valero’s strategic plan to replace chlorine used as a biocide in cooling water treatment with inherently safer materials, such as sodium hypochlorite, at all refineries.

Valero–McKee Refinery, United Steelworkers Union, and Local 13-487
2007-05-I-TX-R10

Work together to benchmark effective PHA methods and practices and implement improvements to the McKee Refinery PHA program, including:


involving the workforce in PHA preparation, performance, and follow-up;



training participants;



conducting PHA quality control checks; and



following up on recommendations for timely implementation and appropriate close-out. 47

Valero - Sunray

July 2008

By the
U.S. Chemical Safety and Hazard Investigation Board

John S. Bresland
Chair

Gary L. Visscher
Member

William B. Wark
Member

William E. Wright
Member

Date of Board Approval

48

Valero - Sunray

July 2008

10.0 References
American Petroleum Institute (API). Safety Digest of Lessons Learned. Section 9, Precautions Against
Severe Weather Conditions,Publication 758, Section 6; Washington DC, 1983.
API. Pressure-relieving and Depressuring Systems, ANSI/API Standard 521, with Addendum,
Washington, DC, 2008.
API. Fire Protection in Refineries, Publication 2001; Washington DC, 1998.
API. Application of Fixed Water Spray Systems for Fire Protection in the Petroleum Industry, Publication
2030; Washington DC, 1998.
API. Design and Construction of LPG Installations, Publication 2510; Washington DC, 2001.
API. Fire-Protection Considerations for the Design and Operation of Liquefied Petroleum Gas (LPG)
Storage Facilities, Publication 2510A; Washington, DC, 1996.
API.Fireproofing Practices in Petroleum and Petrochemical Processing Plants, Publication 2218;
Washington, DC, 1999.
Center for Chemical Process Safety (CCPS). Guidelines for Hazard Evaluation Procedure, 2nd ed;
American Institute of Chemical Engineers (AIChE), New York, 1992.
CCPS. Guidelines for Investigating Chemical Accidents, 1st ed; AIChE, New York, 1992.
CCPS. Inherently Safer Processes, A Life Cycle Approach, AIChE, New York, 1996.
Crawley, F., Preston, M., & Tyler, B., HAZOP: Guide to best practice; Institution of Chemical Engineers,
Warwickshire, UK, 2000.
The Chemical Safety and Hazard Investigation Board (CSB). Steel Manufacturing Incident; Washington,
DC, 2002.
CSB. Fire at Formosa Plastics Corporation: Evaluating Process Hazards; Washington, DC, 2006.
Energy Information Administration. Lost and Found Refinery Capacity. http://tonto.eia.doe.gov/oog/info/twip/twiparch/080221/twipprint.html (accessed Feb 2008).
Environmental Protection Agency (EPA), General Guidance for Risk Management Programs; Office of
Solid Waste and Emergency Response, EPA-550-B-00-008, Washington, DC, 2000.
EPA. General Guidance for Risk Management Program (40 CFR Part 68), RMP Series; EPA-550-B-00008, May 2000; p. I-8.
Frank, W. & Whittle, D. Revalidating Process Hazard Analyses; AIChE, New York, 2001.
FM Global. Evaluating the Hazard: Freeze; FM Global, Norwood, MA, 2002.
FM Global.Property Loss Prevention Data Sheet 9-18, 17-18: Prevention of Freeze-Ups; FM Global,
Norwood, MA, 2007.
Garrison, W., editor. One Hundred Largest Losses: A Thirty-Year Review of Property Damage Losses in the Hydrocarbon-Chemical Industries; Marsh, Inc., New York, 1985.
Handbook of Texas Online; Diamond Shamrock.
49

Valero - Sunray

July 2008

http://www.tshaonline.org/handbook/online/articles/DD/hed6.html, (accessed Jan 2, 2008).
Health and Safety Executive (UK). Emergency isolation of process plant in the chemical industry,
Chemicals Sheet No. 2; HSE Books, Sudbury, England, 1999.
Kletz, Trevor A., 1998. Process plants: A handbook for inherently safer design; Taylor & Francis,
Philadelphia, PA.
Directory of Corporate Affiliations, s.v. Valero Energy Corporation. Lexis Nexis (accessed Dec 2007).
Mannan, S., ed. Lee’s Loss Prevention in the Process Industries, 3rd ed.; Elsevier ButterworthHeinemann, Burlington, MA, 2005.
Marsh & McLennan, One Hundred Largest Losses, May 1985, incident # 63.

The Natural Gas Council. How Natural Gas Gets to Consumers. http://www.yankeegas.com/yankeegascommon/pdfs/gastoconsumers.pdf (accessed January 24,
2008).
Nolan, D., Handbook of Fire and Explosion Protection Engineering Principles for Oil, Gas, Chemical, and Related Facilities; Noyes Publications, Westwood, NJ, 1996.
Occupational Safety and Health Administration (OSHA). CPL 2-2.45A (REVISED) – Process Safety
Management of Highly Hazardous Chemicals -- Compliance Guidelines and Enforcement Procedure,
Appendix B. Washington, DC, 1992.
OSHA. Citation and Notification of Penalty, Diamond Shamrock Refining Company, L.P., dba Valero McKee Refinery, Inspection Number 310690086, August 13, 2007.
OSHA, 2007. Informal Settlement Agreement, Diamond Shamrock Refining Company, L.P., dba Valero McKee Refinery, OSHA Inspection No. 310690086, September 4, 2007.
OSHA. Inspection Data. www.osha.gov/pls/imis (accessed February 2008).
Riecher, A. Fateful 1956 Blast Still Remembered. Industrial Fire World, November-December 2006, p
5.
Timoshenko, S. Strength of Materials, Part II; Van Nostrand Reinhold, New York, 1958;. p. 123.
Valero Energy Corporation. Valero Through the Years. www.valero.com/aboutus/history.htm (accessed on November 13, 2007).
Zurich Risk Engineering. Zurich Risk Topics: Cold Weather Preparation, November 2003, 2-7-005. http://www.zurichna.com/zsc/reel.nsf/b777a8062cedf191c12571fe00467717/e5da540a6edd74998 6256adc006e5a84/$FILE/cold_weather_preparation_rt_2-7.005_20031113.pdf. (accessed March
2008).

50

Valero - Sunray

June 2008

Appendix A. Flow Diagram

51

Valero - Sunray

June 2008

Appendix B. Incident Timeline
Date

Time

Circa 1992

Event
Extractor control changed. Propane mixture control station idled

March 1, 1996

Initial PHA of the PDA included recommendations to install ROSOVs to shut off flow in event of pipe leak or rupture Action item inaccurately closed out as "complete"

July 13, 2001

PDA PHA revalidation did not verify actual status of recommendation to install ROSOVs

January 1, 2002

Valero takes ownership of McKee Refinery
PSM/RMP compliance audit identified that P&IDs had not been updated and that PHA recommendations were not being resolved in a timely manner

February 23-27, 2004

PDA HAZOP study did not identify the need for
ROSOVs due to deficiencies in study methodology
National Weather Service winter weather advisory in effect Sub-freezing temperatures began. Ambient temperatures drop below 32°F for 87 hrs

February 21-24, 2006
February 12-15, 2007
February 12, 2007
February 15, 2007
February 16, 2007

Minimum temperature recorded of 6°F in Dumas Texas
9:05 AM

Temperature rises above 32°F

1:30 PM

Team personnel sign in at PDA unit Control Room

1:35 PM

Board Operator issues work permit to Team personnel

2:09-2:10 PM

Process flow indicators swing sharply, consistent with an initial propane release of 4,500 pounds per minute
First signs of a release occurring on security camera

2:10--2:11 PM

Ignition of propane vapor cloud: one contractor and two
Valero workers burned. A fire brigade member is later burned during response activities

2:11 PM
2:12 -2:15 PM
2:15 PM
2:16 PM

2:19-2:22 PM

Fire alarm received at Dumas Fire Department
Multiple fireballs/ruptures
First wisps of smoke visible from burning No. 2 Cooling
Tower
Wind shifts from northwest to north affecting emergency response.
First water stream seen from due south
Security camera captures multiple large fireballs/ruptures in or near the pipe rack
Flames intensify

52

Valero - Sunray

June 2008

2:23 PM
~2:24-2:26 PM

• Dumas Fire Department arrives on scene
• Wind shifts slightly, coming from northwest
Multiple fireballs/ruptures captured on camera

2:26 PM
3:00 PM

Life Flight helicopter arrives

3:30 PM

Emergency Operations Center (EOC) relocated outside refinery fence

3:40 PM

EOC relocated to west of Tank 300 M3

3:50 PM

Evacuated employees directed to the Dumas
Community Center

4:00 PM

EOC relocated SW of Tank 300 M3

4:06 PM

EOC relocated east of the refinery due to wind shift.

4:15 PM

EPA notified

4:25 PM
February 17, 2007

Total evacuation of refinery

EOC relocated to ammonia plant (north of refinery)

~1:00 PM

Fire declared out

53

Valero - Sunray

June 2008

Appendix C. Piping Elbow Failure Analysis
The fracture in the inlet elbow of the No. 1 Extractor propane mix control station initiated in the exterior surface (cap) welding pass of the girth weld that joined the 10” NPS inlet flange to the 10” elbow, on the intrados (the inner radius) of the elbow (Figure C- 1). No flaw was observed at the initiating site, and the elbow and flange materials were within specification for tensile properties and chemical composition. 1

Figure C- 1. Fractured inlet elbow

1

ASTM A105 for the flange material and ASTM A234 for the elbow.

54

Valero - Sunray

June 2008

The fracture propagated parallel to the pipe axis in both directions, with the surface exhibiting brittle fracture propagation features (Figure C-2).
Charpy V-notch (CVN) toughness tests were performed on the elbow and flange materials. Based on a 50 percent shear-area appearance, ductile to brittle transition temperatures were determined to be 95oF and
70oF (35oC and 21oC), respectively. Given that this piping was exposed to temperatures as low as 6oF (14oC), brittle propagation behavior could be expected in these components.

Figure C- 2. Origin and brittle propagation markers

The deposited weld metal and heat-affected zone of the girth weld were CVN-tested. However, insufficient material was available to determine the complete ductile-brittle transition. Testing at -20oF (29oC) gave from 20 to 85 percent shear area appearance, consistent with a brittle-ductile transition temperature near -20oF (-29oC). However, based on the observed grain structure, the cap weld likely had lower toughness (higher transition temperature) than the underlying weld metal, which had likely been annealed by heat from subsequent welding passes. Because the thickness of the cap was on the order of

55

Valero - Sunray

June 2008

the depth of the CVN specimen notch, it was not possible to measure these differences with standard or subsized CVN specimens.
Correction of the weld metal and heat-affected zone samples for the difference in thickness of the specimens and the actual pipe wall, based on the method of Rosenfeld, 2 shifts their transition temperatures 25oF (14oC) warmer, again implying reduced toughness at low temperatures.
The probable reduced toughness of the cap weld, combined with a relatively high transition temperature, likely promoted brittle failure at a point along the line of highest stress along the intrados of the elbow.
Brittle initiation could possibly have been caused by dynamic loading of the elbow (e.g., an external impact), or by high internal pressures combined with low ambient temperatures. There was no evidence of impact, nor are there records of activities in the area during the likely period of failure that might have applied such a dynamic load. However, ambient temperatures were as low as 6oF (-14oC) prior to the release, and water in the piping could easily have generated very high internal pressures as it froze and expanded. 3 The CSB concluded that the failure likely resulted from water trapped in the propane mix control station dead-leg freezing due to low ambient temperatures.

2

Rosenfeld, M.J., Procedure Improves Line Pipe Charpy Test Interpretation, Oil & Gas Journal, April 14, 1997.

3

Atypically, water expands (its density decreases) as it freezes.

56

Valero - Sunray

June 2008

Appendix D. Initial Propane Release Rate
Background
Witness statements were consistent with the initial release originating from either of two control stations.
Physical examination and flow-testing of components, as described in the body of this report, demonstrated conclusively that the release was from the cracked inlet elbow on the No. 1 Extractor propane mix flow control station. Recovered control system data supported the mix control station as the location of the leak, and allowed the CSB investigators to estimate the propane release rate during the first minute of the incident. The fire damaged the instrumentation in the area of the release almost immediately after the fire ignited.

Propane Release Estimate

Data from PDA unit propane flow meters indicated a significant increase in flow upstream, and a significant decrease in flow downstream, of the No. 1 Extractor propane mix flow control station at the time of the incident. 1 This is consistent with the leak occurring at the cracked inlet elbow of the mix control station.
Figure 1 plots the sum of the upstream and downstream flow meter readings, in bpd.2 The offset prior to the incident is due to an unmeasured process flow between the low- and high-pressure propane supplies upstream of the leak point. Assuming that this offset was fixed during the incident is conservative – the actual release rate was likely modestly higher than estimated here.

1

Data recovered from the PDA unit’s AspenTech IP21 datalogger, recorded at 30-second intervals.

2

Refining barrels hold 42 U.S. gallons; 100 bpd equal 2.917 gpm.

57

Valero - Sunray

June 2008

Propane release rate = [increase in upstream flow] + [decrease in downstream flow]
[21,900] + [19,500] = 41,400 bpd.
Based on a liquid propane density of 27.7 lb per cubic foot at process conditions, the CSB estimated an initial release rate of 4,500 lb/min.

Propane Flow, BPD

110,000
105,000
100,000
95,000
90,000
85,000
80,000
75,000
70,000
65,000
60,000
14:08:32

Sum Upstream
Sum Downstream
14:09:02

14:09:32

14:10:02

14:10:32

14:11:02

Time
Figure D- 1. Changes in propane flows upstream and downstream of the cracked elbow

58

Valero - Sunray

June 2008

Appendix E. Response of Structural Steel to Fire Heating
CCPS’ Guidelines for Fire Protection in Chemical, Petrochemical, and Hydrocarbon Processing
Facilities discusses the importance of fireproofing during the early stages of a fire, when “if nonfireproofed equipment and pipe supports fail due to fire related heat exposure, they could collapse and cause gasket failures, line breaks, and equipment failures, resulting in expansion of the fire.” This type of knock-on damage was a significant factor in the damage caused by the PDA unit fire. As Figure E-1 illustrates, exposure to a jet fire, as can occur in pressurized LPG fires, can lead to rapid heating and the failure of exposed steel within a few minutes. 1

Figure E-1. Time temperature curves for fire tests (CCPS, 2003)

1

The curves shown are based on standardized tests and are illustrative only.

59

Valero - Sunray

June 2008

CCPS describes key factors to consider when specifying the required duration of fireproofing protection, including the


time required to isolate fuel supplies;



availability and capacity of fire-fighting water;



time required to establish cooling from fixed fire monitors (as were installed at the
McKee Refinery), including personnel response time; and the



time required for drainage to remove hydrocarbon spills.

In this incident, the severity of the fire caused rapid knock-on damage before fuel supplies could be isolated or effective water sprays established. The use of ROSOVs, combined with fireproofed pipe rack supports, would likely have significantly reduced the damage caused by this fire.

60

Valero - Sunray

June 2008

Appendix F.

Event Tree

61

Valero - Sunray

June 2008

62

Valero - Sunray

June 2008

63

Valero - Sunray

June 2008

64

Valero - Sunray

June 2008

65

Similar Documents

Premium Essay

Report of Investigation

...REPORT OF INVESTIGATION BY THE SPECIAL INVESTIGATIVE COMMITTEE OF THE BOARD OF DIRECTORS OF WORLDCOM, INC. Dennis R. Beresford Nicholas deB. Katzenbach C.B. Rogers, Jr. Counsel Wilmer, Cutler & Pickering Accounting Advisors PricewaterhouseCoopers LLP March 31, 2003 I. SUMMARY AND CONCLUSIONS ................................................................................. 1 A. The Nature of the Accounting Fraud....................................................................... 9 1. 2. B. C. D. E. Reduction of Reported Line Costs .............................................................. 9 Exaggeration of Reported Revenues ......................................................... 13 WorldCom’s Culture ............................................................................................. 18 Compromising Financial Arrangements ............................................................... 24 Why WorldCom’s Auditors Did Not Discover the Fraud..................................... 25 WorldCom’s Governance...................................................................................... 29 1. 2. 3. 4. Board’s Lack of Awareness of Accounting Fraud .................................... 29 Adequacy of Board’s Oversight of Company ........................................... 30 Stock Sales ................................................................................................ 33 Lease of Airplane to Chairman of Compensation Committee ......

Words: 102110 - Pages: 409

Free Essay

Crj 320 Wk 6 Field Report Crime Scene Investigation

...WK 6 FIELD REPORT CRIME SCENE INVESTIGATION To purchase this visit here: http://www.activitymode.com/product/crj-320-wk-6-field-report-crime-scene-investigation/ Contact us at: SUPPORT@ACTIVITYMODE.COM CRJ 320 WK 6 FIELD REPORT CRIME SCENE INVESTIGATION CRJ 320 WK 6 Field Report Crime Scene Investigation - Murder Kicks Refer to the scenario Crime Scene Investigation – Murder Kicks, The Death of a Soccer Star, located in the online course shell. Write a three to four (3-4) page paper in which you: 1. Analyze the victim and physical evidence of the body as shown in the photograph. 2. Analyze the physical elements shown in the photographs of the inside of the house, noting how these elements connect to the crime. 3. Analyze the physical evidence from photographs of the exterior of the house, noting what might be the escape route. 4. Analyze the photo taken by a neighbor of a truck the week prior to the crime. 5. Propose a list of evidence that should be preserved and provide a rationale for each item on the list. 6. Propose a chain of preservation for the evidence. CRJ 320 WK 6 FIELD REPORT CRIME SCENE INVESTIGATION To purchase this visit here: http://www.activitymode.com/product/crj-320-wk-6-field-report-crime-scene-investigation/ Contact us at: SUPPORT@ACTIVITYMODE.COM CRJ 320 WK 6 FIELD REPORT CRIME SCENE INVESTIGATION CRJ 320 WK 6 Field Report Crime Scene Investigation - Murder Kicks Refer to the scenario Crime Scene Investigation – Murder Kicks...

Words: 765 - Pages: 4

Premium Essay

Chromatography Investigation Report

...Chromatography-Experimental investigation report. Aim:To export the method of separating different coloured dyes(chromatography) and to relate this to real-world in society. Materials: 6 filter paper strips 3coloured felt-pens Pencil 250ml beaker Packet of "M and M's" 2 paddle pop stick 6 paper clips 3 matches Water Procedure: Step 1:On one end of a filter strip,wrote in pencil the brand name of colour of a felt-tip pen that was tested. Step 2: They used a felt-pen to draw a large dot about 1.5 from the other end of the filter paper strips. Step 3: It was repeated with the other felt-tip pens, using a separate filter paper strip for each. Step 4: They added about 1cm of water to the beaker. Step 5:They attached the filter paper strips...

Words: 1097 - Pages: 5

Free Essay

Crj 320 Wk 6 Field Report Crime Scene Investigation

...WK 6 FIELD REPORT CRIME SCENE INVESTIGATION To purchase this visit here: http://www.activitymode.com/product/crj-320-wk-6-field-report-crime-scene-investigation/ Contact us at: SUPPORT@ACTIVITYMODE.COM CRJ 320 WK 6 FIELD REPORT CRIME SCENE INVESTIGATION CRJ 320 WK 6 Field Report Crime Scene Investigation - Murder Kicks Refer to the scenario Crime Scene Investigation – Murder Kicks, The Death of a Soccer Star, located in the online course shell. Write a three to four (3-4) page paper in which you: 1. Analyze the victim and physical evidence of the body as shown in the photograph. 2. Analyze the physical elements shown in the photographs of the inside of the house, noting how these elements connect to the crime. 3. Analyze the physical evidence from photographs of the exterior of the house, noting what might be the escape route. 4. Analyze the photo taken by a neighbor of a truck the week prior to the crime. 5. Propose a list of evidence that should be preserved and provide a rationale for each item on the list. 6. Propose a chain of preservation for the evidence. CRJ 320 WK 6 FIELD REPORT CRIME SCENE INVESTIGATION To purchase this visit here: http://www.activitymode.com/product/crj-320-wk-6-field-report-crime-scene-investigation/ Contact us at: SUPPORT@ACTIVITYMODE.COM CRJ 320 WK 6 FIELD REPORT CRIME SCENE INVESTIGATION CRJ 320 WK 6 Field Report Crime Scene Investigation - Murder Kicks Refer to the scenario Crime Scene Investigation – Murder Kicks...

Words: 765 - Pages: 4

Premium Essay

Outbreak Investigation Summary Report

...Outbreak Investigation Summary Report Case Overview: In the college, the 4 main diseases that began to spread were Bacterial Meningitis, Infectious mononucleosis, Flu, and Strep Throat. One of the diseases that was spreading in college was Meningococcal Meningitis, which is caused by the bacteria Neisseria Meningitidis. This bacteria is very common and likely to spread within young adults. Meningococcal Meningitis is a severe disease in which although many recover, if not treated on time it can lead to serious complications, such as learning disabilities, brain damage, and hearing loss. Meningitis is an inflammation of the membranes that surround the brain and the spinal cord. This disease develops when bacteria enters the bloodstream making its way towards the brain. It is highly contagious and can be spread through the exchange of respiratory and throat secretions. Meningitis symptoms are easily developed within hours or 2 days. Symptoms include high fever, severe headache, stiff neck, confusion, vomiting, seizures, sleepiness, loss of appetite, and skin rash. The longer the disease goes without being treated, the greater the risk the patient is taking to suffer from permanent neurological damage, which includes: hearing and memory loss, learning disabilities, brain...

Words: 941 - Pages: 4

Premium Essay

My Foot Investigation Report

...Introduce and Read aloud How big I a foot. Questions after: • Boys and girls what do you think the problem was in the book? • Why was the queens bed not the right size? Explain: Today boys and girls we are going to measure different objects around the room using our foot. We are going to do this by tracing the bottom of our foot on to a piece of paper! I am going to give each of you a partner to help you do this. Model: I will show students how to help their partner trace their foot onto the piece of paper by having a student come up to help me. I will also have an already cut out traced teacher foot to use so that I do not take up extra time cutting. Now boys and girls we are going to practice using my foot to measure the...

Words: 302 - Pages: 2

Premium Essay

Dominant Hand Investigation Report

...The Investigation of the Response time of the Dominant and Non-Dominant Hand Introduction: The nervous system is made up of the central nervous system and the peripheral nervous system which work together to enable the body to respond to environmental stimuli, this response is done by motor control. Specialised receptors transform the stimuli to which they are specific to into electrical nerve impulses. Specialised cells known as nerve cells or neurons form the central nervous system, these cells come together to form nerve fibres. Neurons respond to and interpret the stimuli received and react appropriately, such reactions are carried out by effectors, as discussed by (Technologies, 1999-2018). Response to a stimulus is produced by effectors. When neurons are stimulated by stimuli,...

Words: 1540 - Pages: 7

Premium Essay

Eth Team Papper Week 2

...found. Mrs. Cooper found expenditures jumping from account to account. At first Mr. Malone did not see a reason to purse an investigation, but Mrs. Cooper decided that there was further investigation needed. Mrs. Cooper looked into the report and realized that something was wrong with the reports and confronted Mr. Bobbitt about the findings. Mr. Bobbitt in the audit committee would take a look and see if the findings that Mrs. Cooper were valid. After finding that the findings were valid she then contact Mr. Farrell and he did an external investigation. After further investigation that the mid-level accounting directors Mr. Normand had confessed to just going along with what Mr. Sullivan had explained to him about the reports because he was afraid to tell anyone and wanted to resign. He was afraid that if he told anyone that he would lose his job and had a family to support. When looking at WorldCom situation it was good that the internal auditor committee took charge of the situation when it was brought to them. That was very ethical and then to have the external auditors take over to review the matter was the right step. Now the fact that you had an accountant that your CFO making false reports and switching money around is not very ethical. Not only did your CFO bring another person into the fraudulent reports, but now an external investigation has to be done and reported. There will be hefty fines and jail time for people in the company that went along with unethical...

Words: 349 - Pages: 2

Free Essay

My Documents

...Chapter 9 Writing Short Reports Critical Thinking Questions 1. Discuss the effects of formality and problem length on report makeup as described in the chapter. (LO1) 2. Which of the prefatory pages of reports appear to be related primarily to the length of the report? Which to the need for formality? (LO1) 3. Describe the role and content of a transmittal message. (LO1) 4. Why is a personal style typically used in the transmittal message? (LO1) 5. Explain how to write the executive summary of a report. (LO1) 6. Why does the executive summary include key facts and figures in addition to the analyses and conclusions drawn from them? (LO1) 7. Explain why some routine report problems require little or no introduction. (LO2) 8. Why is the direct order generally used in the shorter reports? When is the indirect order desirable for such reports? (LO2) 9. Describe the organization of the conventional short report. (LO3) 10. What types of problems are written up as letter reports? As email reports? Explain the differences. (LO3) 11. What kinds of information might go into routine operational reports for different kinds of organizations? Why would these organizations need this information regularly? (LO4) 12. Given what you’ve learned about progress reports, suggest an appropriate structure for these reports. What might go into the beginning? What might the middle parts be? What would the conclusion do? (LO4) 13. How might an internal...

Words: 1030 - Pages: 5

Free Essay

Safety

...Appendix 18f The Hong Kong Polytechnic University Health, Safety and Environment Office HSE Form 2 (01/2009) For HSEO Use Case No.: 香港理工大學 健康安全及環境事務處 Accident/Incident Report Form 意外/事故報告表 Note: This report form should be completed and sent to the Health, Safety and Environment Office in sealed envelop through the Head of Department within 72 hours of the accident/incident. Please refer to Accident/Incident Reporting and Investigation Procedure (Section A400, Health and Safety Guide). The information provided herein will be used for investigation and compiling accident statistics. In case of work-related accident to employee of the University which results in death or partial incapacity, the concerned department should complete HR Form 67 instead of this form. The HR Form 67 should be filed with the Human Resources Office immediately after such an accident is known and a copy of the form be sent to the Health, Safety and Environment Office. 注意: 此表格須經部門主管於意外/事故發生後七十二小時內批注,以密封函件轉交健康安全及環境事務處。本表格內容只供意外調查及 統計之用。請參考理工大學安全健康指引中A400 號文件:事故及意外之報告及調查程序。 若為僱員因工遭遇意外而致死亡或喪失部份工作能力,有關部門應填寫人力資源處表格HR Form 67,並將副本呈送健康安全及環 境事務處。 1. General Information of Accident: 意外資料 Date 日期: Time 時間: Location of Incident/Accident Department in charge of the location 事發地點: 事發地點所屬部門: 2. Nature of Incident: 事故性質 i. Personal injury 個人損傷 ii. Damage to property/equipment 財物損失 iii. Spillage of chemicals 化學品洩漏 iv. Fire 火警 v. Incident of significant environmental...

Words: 403 - Pages: 2

Premium Essay

Haha

...ggrgegregrgregrg fefe A report or account is any informational work (usually of writing, speech, television, or film) made with the specific intention of relaying information or recounting certain events in a widely presentable form. Written reports are documents which present focused, salient content to a specific audience. Reports are often used to display the result of an experiment, investigation, or inquiry. The audience may be public or private, an individual or the public in general. Reports are used in government, business, education, science, and other fields. Reports use features such as graphics, images, voice, or specialized vocabulary in order to persuade that specific audience to undertake an action. One of the most common formats for presenting reports is IMRAD: Introduction, Methods, Results and Discussion. This structure is standard for the genre because it mirrors the traditional publication of scientific research and summons the ethos and credibility of that discipline. Reports are not required to follow this pattern, and may use alternative patterns like the problem-solution format. Additional elements often used to persuade readers include: headings to indicate topics, to more complex formats including charts, tables, figures, pictures, tables of contents, abstracts,and nouns summaries, appendices, footnotes, hyperlinks, and references. Some examples of reports are: scientific reports, recommendation reports, white papers, annual reports, auditor's reports, workplace...

Words: 947 - Pages: 4

Premium Essay

Incident Report Administration

...for adverse patient trends, patient safety issues, or other risks and hazards to be identified, and risk reduction programs implemented. In order to promote a culture that promotes patient safety, the hospital’s Incident Reporting Policy is based upon a foundation of nonpunitive approach to incident/occurrence reporting. The hospital leadership will encourage open and honest reporting of injuries and hazards to patients, visitors and staff, this process will be nonpunitive in nature for all persons reporting incidents throughout the organization. Incidence/occurrence investigations will be viewed as an opportunity for education/process improvement, and will focus on processes and systems, rather than human error. Disciplinary action will be limited to only those employees who engage in willful or malicious misconduct, or those occurrences in which the employee failed to report an incident or hazard to patients in a timely manner. II. Responsibility A. All hospital employees, medical staff members, volunteers, and contract service members will participate in the hospital-wide incident reporting program. All incidents such as those listed as follows will be reported to the department of quality management: 1. Incidents involving inconsistencies with written hospital policies and procedures—informed consent, bedrails, patient...

Words: 3611 - Pages: 15

Premium Essay

Business

...Preliminary Business Studies Assessment Task 3 Notification BUSINESS STUDIES PRELIMINARY ASSESSMENT TASK Assessment Task 3 Notification Assessment Task 3: A BUSINESS REPORT Date Issued: Wednesday 6th May, 2013. Subject: Preliminary Business Studies, Topics: 1-3 Title of Task: Business Report on an SME Weighting: 30% Due Date: Part 1 - This should be presented to your teacher by Friday 17th May (Wk 3). It may be presented as either one page of notes or a one page mind map. Part 2 - Tuesday 11 June 2013 (in your lesson), 2013 Term 2, Week 7 (PF- P4, MW-P3) Component: Inquiry & research, Communication of business information, ideas & issues in appropriate forms, Knowledge and understanding of course content Outcomes: P1 discusses the nature of the business, its role in society and its legal structure P2 explains internal and external influences on business P3 describes factors contributing to the success or failure of small to medium business enterprises P4 assesses the processes and interdependence of key business functions P6 analyses the responsibilities of business to internal and external stakeholders P7 plans and conducts investigations into contemporary business issues P8 evaluates information for actual business situations P9 communicates business information and issues in appropriate format Outcomes: P1 discusses the...

Words: 1119 - Pages: 5

Free Essay

Ip 4 Code of Conduct

...harassment, etc., which is a major reporting concern of code violations (Accounting Web, 2009). Another detail that should be addressed is the point that there is really no specific wording or standard for the structure of the policy, only that the company has to write the context in simply terms that everyone can understand. Then its trial and error from there once the policy is put into place. This is why it is important to update the company’s policies every year, so it can make room for improvements with the issues it has dealt with in the path. I can suggest to the company a few different ways it may want to take regarding steps to educate its employees on how to report a violation. Employees need to know first that there is no set standard, in regards to chain of commands so to speak, when wanting to report a difficult situation. And what is meant by is that...

Words: 787 - Pages: 4

Premium Essay

Guide for Report Writing

...What is a report? A report ‘reports’ on something in a concise, formal way using clearly defined sections presented in a standard format, which tell the reader what you did, why and how you did it and what you found. It is the formal writing up of a practical experiment, project or research investigation. A report is written in a way which presumes that the reader knows nothing about your experiment or research. It is usually written more concisely than an essay, with headings and sub-headings and perhaps bullet-point recommendations, etc. A research report must be written in sufficient detail so that someone reading it would be able to replicate your research exactly. It usually contains arguments and critical evaluation to support a proposed course of action, or to evaluate a business issue. BEFORE YOU START WRITING… • Firstly, check with your lecturer and the module handbook for precise instructions, i.e. the prescribed report structure, word count, deadline. All UHBS reports are module and assignment specific, so this guide only gives a very general idea of structure and content. • Be very detail minded. All UHBS reports will require accurate referencing, good clear English, professional presentation, i.e. clear structure, coherent, free of spelling, grammatical and punctuation errors. • If you are compiling a group report, assign roles. One person in the group could be assigned the role of ‘editor’ to finally ensure the report is put together...

Words: 4226 - Pages: 17