Free Essay

Measurement Documentation and Estimation

In:

Submitted By Grinaliu
Words 3722
Pages 15
BRE345 Measurement, Documentation & Estimating —TOPIC7

BRE345 Measurement, Documentation & Estimating —TOPIC7

2

Content 1. QUESTION(a) .................................................................................................... 3 1.1Provisional Quantities .......................................................................................... 3 1.2Preambles ............................................................................................................. 3 1.3Specification.......................................................................................................... 4 2. QUESTION(b) .................................................................................................... 6 2.1 Reason for Prequalification ................................................................................. 6 2.2Prequalification Criteria ...................................................................................... 6 3. QUESTION(c) .................................................................................................. 10 3.1What is Prime Cost Sum? ................................................................................... 10 3.2 When we use the PC sum? ................................................................................. 10 3.3 Main items in Prime Cost Sum........................................................................... 11 3.3Example............................................................................................................... 11 3.4The benefits of adopting PC sums....................................................................... 11 3.5The Potential Problems....................................................................................... 12 3.6 The situation in Hong Kong ............................................................................... 12 3.7 The Evaluation ................................................................................................... 13

2

BRE345 Measurement, Documentation & Estimating —TOPIC7

3

1. QUESTION(a)
Give the definitions and state the purpose of the following terms: Ø Provisional Quantities Ø Preambles Ø Specifications Illustrate your answer with examples

1.1Provisional Quantities
1.1.1Definition ‘Provisional Quantites are the quantities included in the BQ whose nature and scope cannot be entirely foreseen or defined when the bills of quantities are prepared.’
(- Quoted from http://wiki.answers.com)

They are usually quantities included in the BQ for work which may or may not be encountered but which will be required if it is encountered. 1.1.2Purpose Its purpose is to allow the employer to include within the tenders a facility to include am as yet precisely undefined scope of work, and ensure the bidders are aware of the likely requirement that such work will be required. 1.1.3Example A problem occurs when billing rock which may be suspected but whose incidence is not known – as also in the case of a long pipeline where it is impracticable to sink enough borings in advance to discover the depth and extent of rock everywhere. So sometimes a provisional quantity is put in for rocks in excavation.

1.2Preambles
1.2.1Definition ‘Preamble is a section which contain the description relating to: Ø The Quality and performance of materials Ø The standard of workmanship Ø The testing of materials and workmanship Ø Samples of materials and workmanship’
(- Quoted from slides from Dr. Johnny Wong)

1.2.2Purpose It is n order to inform the contractor’s estimator about changes in the method of measurement. Though the building measurement is standarized, based on HKSMM4. It is a definition of principle rather than an inflexible document. The QS hast the flexibility to change the method of measurement

3

BRE345 Measurement, Documentation & Estimating —TOPIC7

4

1.2.3Example

1.3Specification
1.3.1 Definition The specification is a section, prepared by the designer, which describes: Ø Quality of materials Ø Standard of workmanship Ø Tests that are required
(- Quoted from slides from Dr. Johnny Wong)

It should be notice that there are General and Particular specification. 1.3.2Purpose Ø Describe the quality and quantity of materials required. Ø Specify the workmanship and the method. Thus serves as a guide to supervising Ø Provide the rate for a contractor to calculate in tender. Ø Specify the equipment tools and plants to be engaged and thus enables to 4

BRE345 Measurement, Documentation & Estimating —TOPIC7

5

procure them beforehand. Ø Verify the strength of materials involved in a project. 1.3.3Example

5

BRE345 Measurement, Documentation & Estimating —TOPIC7

6

2. QUESTION(b)
As a QS for a local consultant firm, you are required to prepare a list of specific prequalification criteria for contractor selection for a large scale hotel development project in Macau. Please state the criteria and explain.

2.1 Reason for Prequalification
Prequalification criteria are used for the selection of the competent contractors. The criteria favor both the contractors and purchaser side. It list out the requirement that the project need. Those who might not be sufficiently qualified would be able to avoid the expense of Bidding including both the pecuniary and non-pecuniary cost. It also make the price competition more efficient since those contractors engaging in the bidding are all qualified bidders which can provide qualified services. It also allowed the purchaser to compare the interest generated by different qualified firms and reduce the cost in evaluate bids from unqualified potential contractor. Moreover, it can reduce the problems caused by low price bidding with uncertain quality and capability. Last but not least, it encourages the company to form joint ventures. Companies with different advantages can cooperating each other and it may have better chance for the project to success.

2.2Prequalification Criteria
2.2.1 Past Performance (E.g. Quality standards, variations, final cost, target performance level etc.) The purchaser may focus on the quality standards and the target performance level performed by the potential contractor before. The reason behind a large scale hotel development project in Macau is probably a famous hotel brand, they may desire to have higher quality standard to improve their reputation or image for their customers. For example, the purchaser may consider whether the potential can meet the details of quality assurance registration to ISO 9001 or equivalent schemes In the case, relevant experience is preferred. The potential contractor has done a project before similar with the bidding project would certainly convince the purchaser to believe that they are capable to deal with the job. The prequalification should seek for the potential contractor which has completed the work at a magnitude similar before. It means a potential contractor that has completed a project with similar value to the proposed project over a specified period is preferred. 6

BRE345 Measurement, Documentation & Estimating —TOPIC7

7

According to the date shown by the North American Development Bank, the individual value of such previous contracts should around 80% of the estimated cost which the contingencies are included. The prequalification should also seek for the potential contractor which has completed the work at a volume and quality similar before. It means a potential contractor that has completed a project with similar tasks like tunneling, earth moving and concrete placing is preferred. According to the date shown by the North American Development Bank, the potential contractor should perform at a rate to meet 80% of the peak annual rate required for the project. 2.2.2 Technical Ability (E.g. Technical expertise, possessed plant and equipment and experience etc.) In order to develop a large scale project, it requires a lot of construction machines and equipment. The availability of those items is crucial for the development project since efficiency can greatly improve if the task on site is action by an appropriate construction machine. In this case of a large scale hotel development project in Macau, it is not uncommon that there is not many competent potential bidders will have an inventory of high value construction equipment, since it means a high capital cost overhead to a contractor. In such cases, most of the contractor tend to lease or hire those equipment from the specialist subcontractor or equipment hire firms. The verification of the availability of specialist subcontractor and the equipment hire firms should be provided by the potential contractor at the time of prequalification. Therefore, the criteria should be limited to those bulky or specialized items that are critical for the project or which those items which cannot be obtained in a short period of time. Apart from the inventories of existing equipment and plant and the availability of specialist subcontractor and the equipment hire firms, the purchaser may also take the capacity of the potential contractor into consideration. For example, the capacity to handle new projects considering ongoing assignment and the ability to mobilize sufficient resources within the timescale required. The reason behind that the purchaser may wish to make sure the potential contractor has enough resources and ability to finish the project on schedule. It should be noticed that a delay in schedule may be very costly to a hotel development project since in general the hotel would prefer to finish the project before the tourist season. 2.2.3 Personnel Capability (E.g. Project management organization, experience of technical personnel etc.) Existence of skilled technical and managerial labor of the potential contractor is 7

BRE345 Measurement, Documentation & Estimating —TOPIC7

8

another criteria included in the consideration of prequalification. For example, the purchaser of the development project in Macau may consider the number of direct staff and the number of subcontract staff proposed and also the degree of direct service proposed (Level of directly employed labor plant and technical services, indicate from where additional services staff will be recruited). It should be noticed that only those labors having critical operational or technical skill should be considered. For example, key personnel like project manager, superintendents specialized in piling, earthworks or dredging etc. A company with a group of experience managerial member (experienced management system) is especially preferred. Since those experience members are more likely to run an effective managerial system for the development project in Macau. Hence, the wastage, variation or cost is more likely to be minimized, in some case, the total length require for the project may also reduce. For example, the purchaser of the development project in Macau may consider the proposed project organization and structure to determine whether it is a quality management system which can be employed on the project. It is Important to list it in the prequalification criterion because personnel resources is not a resource that can be obtained by the potential contractor easily in a short period of time. Even a higher salary may be able to recruit a skilled labor, however, there is cost involved in familiar the procedure of the company etc. Ø Ø Criteria should based on: Minimum number of year of experience in similar position Minimum number of comparable projects carried out in a specified number of preceding years. It should be noticed that an individual have sufficient knowledge of the applicant’s management policy procedures, and practices to act with the confidence and authority in the executive site position shall also be viewed as a key staff. For example, 3 years work with the applicant. 2.2.4 Financial Consideration (E.g. Financial Stability, Financial Status, Bank Arrangement, Bonding Capacity and Cash Flow Capability Requirement) Lastly, although the purchaser of the large scale hotel development project probably have selected certain dominated contractor with strong financial power in the city to invite them to make tender. However, the financial consideration shall still be the factor in the prequalification. The reason behind is that even a big contractor may have a chance to suffer from cash shortage because of ongoing assignment may have drown lots of resources away. TThe purchaser may wish to make sure the potential contractor has enough resources and ability to finish the 8

BRE345 Measurement, Documentation & Estimating —TOPIC7

9

project on schedule. The development of a large scale hotel development project involves a large amount of capital investment. It causes serious burden for the contractor in short term. Therefore, it is important to ensure the financial condition of the contractor is capable and suitable to due with the development project. According to the North American Development Bank, the financial condition over the last 5 years and the projection for the coming 2 years shall remain positive. If the contractor is found that they are suffering from consistent losses or a risk of insolvency shown in account, they probably are being rejected. Cash flow capability is also another crucial criteria. Otherwise, it will be very costly if the development is delayed by the shortage of cash flow. The potential contractor should able to finance fully the purchaser’s estimate of cash flow for both the local and foreign currency requirement for a specified “critical period”. For example in a monthly periodic payment system, the assessment of cash flow should based on a straight line month cash flow for the contract. Calculating form the beginning of the month invoiced, the “critical period” is determined by adding a contingency period of 1 or 2 months to cumulative time period required for issuing the interim certificate and the time required for the purchaser to pay the amount due. According to the North American Development Bank, 1 month for contingency is enough for cumulative time period of 3 months or less and 2 months contingency for a longer period. The Contractor should provide: Ø The audited annual financial statement for the last 5 years which is supported by tax returns or audit statements. (Including the access to liquid assets, line of credit, unencumbered assets etc.) Ø The name and address of the applicant’s banker which familiar with their financial standing.

9

BRE345 Measurement, Documentation & Estimating —TOPIC7

10

3.QUESTION(c)
‘PC Sums have been widely used in Hong Kong’s construction industry but it is not good practice to some extent’. Discuss this statement.

3.1What is Prime Cost Sum?
HKSMM4 defines the term PC sum as ‘ A sum provided for work or services to be executed by a Nominated Sub-contractor or for materials or goods to be obtained from a Nominated Supplier.’ (Section II clause 15.1b) Here we can see that two key words involved with PC sum, the Nominated Sub-contractor and the Nominated Supplier. Sub-contractors can be classified as Domestic sub-contractors, Named sub-contractors and Nominated sub-contractors. By industry definition, Nominated Sub-contractors are contractors selected by the employer who then sign the contract directly with the Main contractor to perform a specific kind of works. They are usually specialist trade contractors who may provide both the design and construction services. It is common practice for the employer to source and invite prospective Nominated Sub-contractors to participate in some form of procurement or bidding exercise. The employer will negotiate the commercial and legal terms with the successful sub-contractor, who will then enter into a sub-contract with a main contractor based upon those pre-agreed terms.

3.2 When we use the PC sum?
As we can see from the definition of PC sum, it is a must thing along the exist of the Nominated Sub-contractor (or the Nominated Supplier). Then the time we use PC sum is certainly the time when we have Nominated Sub-contractor. Nomination is often adopted in the conditions as below: 1. In construction, there may be some long delivery items where design and manufacturing times could not wait for the appointment of a main contractor. Then the employer needs to nominate sub-contractor himself before the tender in order to avoid the potential. 2. There may be some specialist design input required in the early stages of design development. As mentioned above, some specialist trade contractors provide both the design and construction services so they need to participate in the design process before the appointment of the main contractor. 3. The Employer may have developed a long-term business relationship with an Nominated Sub-contractor with a proven track record for good work. Though the employer can state his requirement to the main contractor in specific details, he still has the risk that what the sub-contractor will do has big difference with his expectation. And a safer way here is to choose a sub-contractor who has worked for the employer before and known his flavor 10

BRE345 Measurement, Documentation & Estimating —TOPIC7

11

well.

3.3 Main items in Prime Cost Sum
As we know, PC sum items are sometimes special design items for the construction. Besides the special things, there some common items that usually adopt Nominated Sub-contractor, such as Electrical Installations, MATV, CCTV and PA System, Air-Conditioning and Mechanical Ventilation System, Fire Fighting System, Hot Water System, and Lift and Escalator System.

3.3Example

3.4The benefits of adopting PC sums
There are several benefits when adopting PC sum, or to say when using the Nominated Sub-contractor. We can see them from different perspectives. 1. A key benefit for the employer is to control over the choice of, and performance required from, Nominated Sub-contractor. The employer can also, if he wishes, control the terms of the subcontractor, including the price and quality benefits. 2. As adopting the Nominated Sub-contractor can also be appointed after the main contractor has started work, one of the employer benefits is that specialist design can continue after work has commenced on site. This kind of design may can not be easily determined when the main contractor has already appointed the domestic sub-contractor. 3. Another benefit is the possibility of reduction of the procurement times. Some specialist subcontract work requires a longer lead time than the construction program. This may require this specialist work must be started before the 11

BRE345 Measurement, Documentation & Estimating —TOPIC7

12

main contractor has been appointed. Nomination now allows for continuity when a specialist sub-contractor has been selected before the main contractor is in place. 4. As we know, some employers choose to adopt Nominated Sub-contractor not for specialist work, but because the long-term business relationship they have before. And this Nominated Sub-contractor can give the employer a comparatively high ensurement of employer’s expectation. Just think about a big scale chain hotel. It may has a long business relationship with a sub-contractor who does the work of the bathroom in every their hotel. Then appointing this old partner allows the employer do not need say more about their standard and every specific requirement, meanwhile get the better satisfication.

3.5The Potential Problems
1. The financial risk for the main contractor. It is entirely possible that the prime cost item performed by Nominated Sub-contractor exceeds the stated amount of item. And usually it is unlikely a variation order will be required unless there has been significant change. Often the contractor will be compensated through the payment mechanism, in particular, through the percentage uplift for overheads and profit. 2. This mixing of responsibilities between the employer and main contractor for the performance of a Nominated Sub-contractor leads to frequent disputes. In principle, the contractor should allow prime cost works in his programme. In practice, particularly where Nominated Sub-contractor are involved, the contractor may have inadequate information or control to perform the task. This applies most obviously when the identities and the timing requirements of Nominated Sub-contractors are not known until after the works start. 3. Because there is no contractual bond between the Employer and the Nominated Sub-contractor, in case there is any delay, the contractor is entitled to an extension of time. But the employer is not able to recover the damages from the Nominated Sub-contractor. 4. Further, if the sub-contractor’s work proves unsuitable or not fit for its purpose, the main contractor will deny responsibility (unless he was expressly charged in the terms of the sub-contract to take such responsibility – which is unlikely) since he had no choice in the selection of the sub-contractor or the product. The extensive disputes which have arisen over the years on these matters, more particularly in building work with its wider use of nominated subcontractors, has led many engineers to take the view that use of Nominated Sub-contractors in civil engineering should be avoided wherever possible.

3.6 The situation in Hong Kong
According to Electrical & Mechanical Contractor Magazine, 2005, most forms of 12

BRE345 Measurement, Documentation & Estimating —TOPIC7

13

contract allow the contractor to claim an adjustment of completion date for delay caused by Nominated Sub-contractor, which the contractor has taken all reasonable measures to prevent. In this situation, contractor is easy to make a claim and very difficult to refute. To overcome the difficulties, the government of HKSAR makes s a list of specialist contractors and suppliers. This new specialist sub-contractor appointment procedure has the advantage of availability, that provides expertise in the construction of specialist works, and yet now pass on the risk of appointing sub-contractors to the contractor.

3.7 The Evaluation
To judge whether the use of PC Sum, which means whether adopting the Nominated Sub-contractor was a good practice, or to foresee the prospective of PC sum, I think we have to think from 2 different situations. First, when the Nominated Sub-contractor is appointed for special works or in special stages. This need for Nominated Sub-contractor sometimes cause a lot of practical problems from the mix responsibilities between the employer, the contractor and the sub-contractor, leading to delay, non-efficiency and un-performance. And this need for Nominated Sub-contractor can now be substituted by the new specialist sub-contractor appointment procedure. So I think using for Nominated Sub-contractor to do special work in the past was a practical way but did cause some dispute, and might not be the solution in future. On the other hand, not all the Nominated Sub-contractor is chosen for specialist work need, while quite of them are from the employer’s profit perspective. As we mentioned before, it can be from the long-term business relationship between the employer and the sub-contractor or some more direct profit relate. In this condition, I think the existent of Nominated Sub-contractor, and then the PC sum can be said to be a must whenever in the past or the future. Though the employer does have some risk from this, we can understand in the way that he is already acquiescent with all the possibility of loss compared with the profit and benefit he may gain.

13

BRE345 Measurement, Documentation & Estimating —TOPIC7

14

References Ø Ø Ø David Y. K. Leung , A Practical Approach to Conditions of Contracts for Civil Engineering Works Adetola F.O., Auditing of quantity surveyors billsof quantities, The Quantity Surveyor, V. 29,Oct/Dec, 1999, pp. 14-18. Brand, D., 2009. Contract nominations. [Online] 5 January. Available at: http://cmguide.org/archives/315 [Last accessed on 23 July 2009] Ø Brand, D., 2009. Contract nominations. [Online] 5 January. Available at: http://cmguide.org/archives/315 [Last accessed on 23 July 2009] Ø Ø Ø Ø Ø Ø Ø http://www.designingbuildings.co.uk/wiki/ http://lecture.civilengineeringx.com/project-managment/accuracy-of-quantities-pro visional-quantities/ Inne Johnson Ikpo, Variability Analysis of Prime Cost Sums http://lecture.civilengineeringx.com/project-managment/use-of-nominated-sub-c ontractors/ http://www.ukessays.com/essays/project-management/nominated-sub-contractor php http://www.longworthconsulting.co.uk/construction_contracts/nominated_sub-co ntractor.htm http://www.designingbuildings.co.uk/wiki/Nominated_sub-contractor

14

Similar Documents

Premium Essay

Quality Assurance

...Chapter 8 Quality Assurance and Quality Control 8 QUALITY ASSURANCE AND QUALITY CONTROL IPCC Good Practice Guidance and Uncertainty Management in National Greenhouse Gas Inventories 8.1 Quality Assurance and Quality Control Chapter 8 CO-CHAIRS, EDITORS AND EXPERTS Co-Chairs of the Expert Meeting on Cross-sectoral Methodologies f or Uncertainty Estimation and Inventory Quality Taka Hiraishi (Japan) and Buruhani Nyenzi (Tanzania) REVIEW EDITORS Carlos M Lòpez Cabrera (Cuba) and Leo A Meyer (Netherlands) Expert Group: Quality Assurance and Quality Control (QA/QC) CO-CHAIRS Kay Abel (Australia) and Michael Gillenwater (USA) AUTHOR OF BACKGROUND PAPER Joe Mangino (USA) CONTRIBUTORS Sal Emmanuel (IPCC-NGGIP/TSU), Jean-Pierre Fontelle (France), Michael Gytarsky (Russia), Art Jaques (Canada), Magezi-Akiiki (Uganda), and Joe Mangino (USA) 8.2 IPCC Good Practice Guidance and Uncertainty Management in National Greenhouse Gas Inventories Chapter 8 Quality Assurance and Quality Control Contents 8 QUALITY ASSURANCE AND QUALITY CONTROL 8.1 INTRODUCTION.................................................................................................................................8.4 8.2 PRACTICAL CONSIDERATIONS IN DEVELOPING QA/QC SYSTEMS ......................................8.5 8.3 ELEMENTS OF A QA/QC SYSTEM .................................................................................................. 8.6 8.4 INVENTORY AGENCY...

Words: 9065 - Pages: 37

Premium Essay

Draft Rts on Assessment Methodology for Irb Approach

...5- Assessment methodology for assignment of exposures to grades or pools 51 CHAPTER 6- Assessment methodology for definition of default 56 CHAPTER 7- Assessment methodology for rating systems design, operational details and documentation 60 CHAPTER 8- Assessment methodology for risk quantification 71 CHAPTER 9- Assessment methodology for assignment of exposures to exposure classes 90 CHAPTER 10- Assessment methodology for stress test used in assessment of capital adequacy 93 CHAPTER 11- Assessment methodology of own funds requirements calculation 96 CHAPTER 12- Assessment methodology of data maintenance 102 CHAPTER 13- Assessment methodology of internal models for equity exposures 106 CHAPTER 14- Assessment methodology for management of changes to rating systems 111 CHAPTER 15- Final provision 112 1. General Rules * Proportionality Principle: Competent authorities, to the extent appropriate, shall apply additional methods which are relevant to the nature, size and degree of complexity of the institution´s business and organizational structure. * Quality: * Is it approved at the appropriate management level? * Are there policies in place outlining specific standards to ensure high quality of internal documentation?...

Words: 2498 - Pages: 10

Premium Essay

Report of Software Maintence

...INTRODUCTION Software Engineering is an engineering discipline which is concerned with all aspect of software production. It also concerned with all aspects of computer-based systems development including hardware, software, and process engineering. SOFTWARE MAINTENANCE Software development efforts result in the delivery of a software product that satisfies user requirements. Accordingly, the software product must change or evolve. Once in operation, defects are uncovered, operating environments change, and new user requirements surface. The maintenance phase of the life cycle begins following a warranty period or post implementation support delivery, but maintenance activities occur much earlier. Software maintenance is an integral part of a software life cycle. However, it has not received the same degree of attention that the other phases have. Historically, software development has had a much higher profile than software maintenance in most organizations. This is now changing, as organizations strive to squeeze the most out of their software development investment by keeping software operating as long as possible. The open source paradigm has brought further attention to the issue of maintaining software artefactsdeveloped by others. Software maintenance is defined as the totality of activities required to provide cost-effective support to software. Activities are performed during the pre-delivery stage as well as during the post-delivery stage. Pre-delivery activities...

Words: 4151 - Pages: 17

Free Essay

Operations Management

...Proceedings: Pacific Northwest Software Quality Conference, 2006 The Challenge of Productivity Measurement David N. Card Q-Labs, Inc dca@q-labs.com Biography- David N. Card is a fellow of Q-Labs, a subsidiary of Det Norske Veritas. Previous employers include the Software Productivity Consortium, Computer Sciences Corporation, Lockheed Martin, and Litton Bionetics. He spent one year as a Resident Affiliate at the Software Engineering Institute and seven years as a member of the NASA Software Engineering Laboratory research team. Mr. Card is the author of Measuring Software Design Quality (Prentice Hall, 1990), co-author of Practical Software Measurement (Addison Wesley, 2002), and co-editor ISO/IEC Standard 15939: Software Measurement Process (International Organization for Standardization, 2002). Mr. Card also serves as Editor-in-Chief of the Journal of Systems and Software. He is a Senior Member of the American Society for Quality. Abstract - In an era of tight budgets and increased outsourcing, getting a good measure of an organization’s productivity is a persistent management concern. Unfortunately, experience shows that no single productivity measure applies in all situations for all purposes. Instead, organizations must craft productivity measures appropriate to their processes and information needs. This article discusses the key considerations for defining an effective productivity measure. It also explores the relationship between quality and productivity...

Words: 4342 - Pages: 18

Free Essay

Estimating Vehicle Speed from Traffic Count and Occupancy Data

...for 20 or 30 second observational periods. However, for the purposes of traffic management it is frequently useful to have data on (mean) vehicle speeds, but this is not directly available from single loop detectors. While detector occupancy is related in a simple fashion to vehicle speed and length, the latter variable is not measured on the vehicles that pass. In this paper a new method for speed estimation from traffic count and occupancy data is proposed. By assuming a simple random walk model for successive vehicle speeds an MCMC approach to speed estimation can be applied, in which missing vehicle lengths are sampled from an exogenous data set. Unlike earlier estimation methods, measurement error in occupancy data is explicitly modelled. The proposed methodology is applied to traffic flow data from Interstate 5 near Seattle, during a weekday morning. The efficacy of the estimation scheme is examined by comparing the estimates with independently collected vehicle speed data. The results are encouraging. Key words: Bayesian inference, inductance loop, Metropolis-Hastings algorithm, measurement error, missing data. 1. Introduction Road traffic management is becoming increasingly reliant on the availability of real-time traffic flow data. In Melbourne, for example, SCATS (Sydney Coordinated Adaptive Traffic System) makes use of such data to optimize signals over the road network. Similar schemes operate in many other cities throughout...

Words: 4518 - Pages: 19

Free Essay

Daily English News Paper and National Daily

...1 Software Cost Estimation Hareton Leung Zhang Fan Department of Computing The Hong Kong Polytechnic University {cshleung, csfzhang}@comp.polyu.edu.hk Abstract Software cost estimation is the process of predicting the effort required to develop a software system. Many estimation models have been proposed over the last 30 years. This paper provides a general overview of software cost estimation methods including the recent advances in the field. As a number of these models rely on a software size estimate as input, we first provide an overview of common size metrics. We then highlight the cost estimation models that have been proposed and used successfully. Models may be classified into 2 major categories: algorithmic and non-algorithmic. Each has its own strengths and weaknesses. A key factor in selecting a cost estimation model is the accuracy of its estimates. Unfortunately, despite the large body of experience with estimation models, the accuracy of these models is not satisfactory. The paper includes comment on the performance of the estimation models and description of several newer approaches to cost estimation. Keywords: project estimation, effort estimation, cost models. 1. Introduction In recent years, software has become the most expensive component of computer system projects. The bulk of the cost of software development is due to the human effort, and most cost estimation methods focus on this aspect and give estimates in terms of person-months...

Words: 6839 - Pages: 28

Premium Essay

Good Day.

...TIME MANAGEMENT PLAN “NEOES” NEW ERA UNIVERSITY #9 CENTAL AVE. BRGY. NEW ERA Q.C QUEZON CITY,1116 OCTOBER 8, 2014 Table of Contents Activity Definition 2 Sequence of Activities 2 Activity Duration Estimation 3 ACTIVITY DEFINITION The proposed system aims to provide and improve the Enrollment System for New Era University using a modern’s technology. In order to achieve success on the online Enrollment projects, the following objectives must be met within designated time and budget allocations SEQUENCE OF ACTIVITIES |Activity List | |Project: Online Enrollment for New Era University |Start Date: 09/01/14 | |Activity ID No |Activity Name |Description of Work |Responsibility | |001 |System Designer |System designer undertakes design tasks for business |A. Raveche has primary | | | |computer systems such as payroll or stock control. |responsibility  | |002 |Development and Configuring |Configuring the Online Enrollment. ...

Words: 956 - Pages: 4

Premium Essay

Business Plan

...Sekolah Drive – Orphanage/Children Single Mother Group/Children from Underprivileged background | Activities | Duration | List of activities to be carried out during the program/initiative in chronological order including decision required 1. For the Hereafter – Upgrade of amenities (carpets/curtains/abulation area etc) 2. Clean & Go – Gotong-royong/mural painting/recreational area 3. Childrens Day 4. Buka Sekolah Drive – School registration fee and equipment to 100 Primary and Secondary School kids. | 1 Day1-2 Days1 Day1 Day | Potential Partner / Vendor | Scope of Work | 1. Teambuilding Company 2. Ketua Kampung/Imam 3. Operator of orphanages/old folks home/SPCA 4. Mydin/Giant and Headmaster | | Budget Estimation | Items | Amount (RM) | 1. Curtains/Carpet/Repair of abulation area RM60,0002. Painting and landscape facility RM40,0003. Children’s Day RM30,0004. School...

Words: 1141 - Pages: 5

Premium Essay

C# and Asp.Net Project by Shivprasad Koirala Sham Shaikh

...C# and ASP.NET Projects By Shivprasad Koirala Sham Shaikh Visit us http://www.questpond.com for free interview question e-book. Mail bpb@bol.net.in to buy the book Write to the author directly at shiv_koirala@yahoo.com The e-Book is free but below are the limitation of this free e-book:-- The book has only 5 projects which are far less than what the actual book contains. -- Practical Videos and code walkthrough of the projects is not available for download. -- The book also has lot of installations provided in CD even that is not available for Download. Finally hard copy is a hard copy if you are interested below are the ways you can buy the Book:• Buy directly from the Author call 09867628636. If you are buying from the Author You get a chance to meet him and believe us you will enjoy it. Please send DD of Rupees 300 in favor of (Please send us detail that you want a hard copy or E-book CD) Shivprasad Bist E – 8, Amar Nager , Hoechst Colony , Opposite ShreeRam towers Mulund West Mumbai 82. • Call your city book shop MUMBAI-22078296/97/022-22070989, KOLKATA22826518/19,HYDERABAD-24756967,24756400,BANGALORE25587923,25584641,AHMEDABAD-26421611, BHATINA(PUNJAB)2237387,CHENNAI-28410796,28550491,DELHI/NEWDELHI23254990/91,23325760,26415092,24691288 • Are you a Pakistani reader then contact M/s. Vanguard Books P Ltd, 45 The Mall, Lahore, Pakistan (Tel: 0092-427235767, 7243783 and 7243779 and Fax: 7245097) E- mail: vbl@brain.net.pk • If you are not from india or pakistan :- ...

Words: 16342 - Pages: 66

Premium Essay

Flat Cargo

...Flat Cargo Berhad (FCB) Introduction FCB obtained listing in Bursa Malaysia on the 15 September 2001. The main core business was to provide air freight transportation within the Asian region. As a fast growing company, FCB secured agreements from well-establish company within the transportation industry such as Worldwide Express, United Parcel Services (UPS), Nationwide Express, City link and others. Issue on FCB 1) The auditors were unable to verify the aircrafts claimed have been purchased by FCB in 2005. The audit team found a non-functional rundown aircraft barely worth 231 million in a hangar. Aircrafts that was claimed have been purchased are categorize as an asset for FCB. It’s because the business nature in providing delivering transportation services to customer that generate income for the company. But acquired an asset must be recorded through legal transaction and within controlled of the company. These items are expected to be used in future activities that will generate cash inflows to the company. From the financial statement in 2005, the account equipment, at cost of the aircrafts acquired is increased and cash decreased for the same amount. But, failing to verify the legal amount of purchased assets, we consider the expenditure was not happening and the amount of fixed asset was overstated and the cash was understated in the balance sheet. Non-functional aircraft barely worth 231 million in the hangar were a huge asset for FCB that within their control...

Words: 1030 - Pages: 5

Premium Essay

C Sharp Project

...C# and ASP.NET Projects By Shivprasad Koirala Sham Shaikh Visit us http://www.questpond.com for free interview question e-book. Mail bpb@bol.net.in to buy the book Write to the author directly at shiv_koirala@yahoo.com The e-Book is free but below are the limitation of this free e-book:-- The book has only 5 projects which are far less than what the actual book contains. -- Practical Videos and code walkthrough of the projects is not available for download. -- The book also has lot of installations provided in CD even that is not available for Download. Finally hard copy is a hard copy if you are interested below are the ways you can buy the Book:• Buy directly from the Author call 09867628636. If you are buying from the Author You get a chance to meet him and believe us you will enjoy it. Please send DD of Rupees 300 in favor of (Please send us detail that you want a hard copy or E-book CD) Shivprasad Bist E – 8, Amar Nager , Hoechst Colony , Opposite ShreeRam towers Mulund West Mumbai 82. • Call your city book shop MUMBAI-22078296/97/022-22070989, KOLKATA22826518/19,HYDERABAD-24756967,24756400,BANGALORE25587923,25584641,AHMEDABAD-26421611, BHATINA(PUNJAB)2237387,CHENNAI-28410796,28550491,DELHI/NEWDELHI23254990/91,23325760,26415092,24691288 • Are you a Pakistani reader then contact M/s. Vanguard Books P Ltd, 45 The Mall, Lahore, Pakistan (Tel: 0092-427235767, 7243783 and 7243779 and Fax: 7245097) E- mail: vbl@brain.net.pk • If you are not from india or pakistan :- ...

Words: 16342 - Pages: 66

Premium Essay

Osi Model Presentation

...Meeting federal and state standards ◦ Meeting security standards  Stakeholder satisfaction Supporting Measures for Success  Business goals  Compliance Requirements  Supporting Strategies  Prioritization  Prevention Tangible Measures for Success  Operational  Technical  Economic Summary of Project Feasibility  Measurement of how proposed system solves the problem  Management Commitment  Dependent on Human Resources Operational Feasibility Analysis  A large part of determining resources that has to do with assessing technical feasibility  Contact with Vendors  Internal Technical Capability Technical Feasibility Analysis  Cost and benefits analysis  Frequently used method  Used to determine the benefits and savings Economic Feasibility Analysis  Project Description  Goals and Objectives  Project Performance  Project Assumptions  Project Constraints  Major Project Milestones Business Process Summary Business Process Summary (Cont.) Process Objective Model • Negotiations • Proper and Conducive Project Plan • Assigning Tasks to Team Members • Proper Estimation of Project Quantitatively/Qualitatively • Reviewing and doing rework when needed Descriptive  Types ◦ Emergent Approach and Prescriptive Approach  Downfalls ◦ Does not consider that unexpected changes may occur  Details ◦ The...

Words: 939 - Pages: 4

Premium Essay

Enhanced Auditor Reports

...------------------------------------------------- Speech at the August 2013 CReCER Conference, Cartagena, Colombia Good afternoon ladies and gentlemen, it is my pleasure to be with you again. I say ‘again’ as there are many familiar faces in the audience from the 2012 CReCER Conference in Nicaragua. For me, this in and of itself is a clear signal of the commitment of stakeholders in Latin America to engage in dialogue on international developments. At last year’s conference,I noted a number of important challenges in financial reporting and auditing, and in the surrounding environment. For example, today’s financial reporting involves more complexity, more areas of judgment, and more qualitative disclosures; and users have higher expectations than ever before, with many saying “We want to hear more.” Perhaps most importantly, the global financial crisis has triggered questions concerning the quality of audits, their effectiveness, and the role of professional judgment and skepticism – which have given way to fundamental questions to the profession about relevance and trust. So why change the auditor’s report now? What we learned from research is a positive message: the auditor’s opinion is valued, and users want to hear more from the auditor – more pertinent, and more tailored, information about the specific audit performed on an entity’s financial statements. There is symbolic value in the current report, but little communicative value – and users see the potential...

Words: 8489 - Pages: 34

Free Essay

Interior Design Contract

...EXECUTIVE SUMMARY HYPOTHETICAL SITUATION Tropical lagoon is a new exclusive construction in the thane district of Maharashtra. The project undertaken is a 2bhk residence of 1250 sq.ft with an attached terrace/garden of 350sq.ft.The designer was contracted to carry out interior decoration work for a family of 3(A couple and their son).The theme chosen was a mixture of traditional African decor and contemporary decor. AGREEMENT CLAUSE I /We ___________________________________ (please print name) wish to appoint ___________________________________ (designers name) as the ___________________________________ (professional title) on the ____________________________________________________________________________ __________________________________________________________ (project description) at __________________________________________________________ (project address) I/We agree to the terms set out in this agreement which comprises of Schedule of Services, Schedule of Fees and Terms & Conditions. This appointment was made on ___________ Day of___________ (month) ___________ (Year) Signed _________________________________________________ (client) Signed __________________________________________________ (designer) STRATEGY Strategy is very transparent and simple. It is as follows: Upon acceptance of our client’s proposal to work with us, we get to know them through extensive research and one on one meetings. After gathering...

Words: 1925 - Pages: 8

Premium Essay

Risk Assessment

...fastest rate of development and application in all branches of business, requires adequate protection to provide high security. The focus of the safety analysis applied on an information system is to recognize and evaluate threats, vulnerabilities and safety characteristics. IT assets are uncovered to risk of harm or losses. IT security includes protecting information stored electronically. That protection implies data integrity, availability and confidentiality. According to“Risk Assessment of Information Technology Systems” (2009) risk assessment is the most critical part of Information Security Management (ISM).  Risk Management and Risk Assessment involves analysis, planning, implementation, control and monitoring of implemented measurements, and Risk Assessment, as part of Risk Management. It involves several processes: · Risk identification, · Relevant risk analysis, · Risk evaluation The main purpose of Risk Assessment is to make a choice whether a system is acceptable, and which measures would provide its acceptability. For every organization using IT in its business process it is important to conduct the risk assessment. Numerous threats and vulnerabilities are presented and their identification, analysis, and evaluation enable evaluation of risk impact, and proposing of suitable measures and controls for its mitigation on the acceptable level. According to Stallings and Brown (2012), the risk assessment is the first process in the risk management, and methodology...

Words: 742 - Pages: 3