Habitat for Humanity – Simulation 1. When the project first started, you were asked to order the tasks to build the WBS. How did you decide the order tasks should appear in for the WBS? In a typical project, how do you think a WBS should be created, and what stakeholders or team members should be involved? Answer – The approach that I took for ordering tasks is to order them in the sequence of work that would generally be completed, so buying the supplies would come before installing them
Words: 832 - Pages: 4
ST. MARY’S MEDICAL CENTER A. The network for the given problem is as shown below B. The various activities given in the case may be broken down into sub-activities as follows. a. Meet with department heads i. Fix appointments with department head ii. Prepare agenda and inform department heads as needed iii. Meet department heads and discuss plans b. Appoint move advisory committee iv. Decide broad advice required from advisory committee
Words: 1361 - Pages: 6
original project plan. 4. Analysis * Schedule: The positive schedule variance and SPI above 1.0 indicates the project is ahead of schedule; however, the critical path for this project is A - C - E, and CP tasks are significantly behind schedule (SPI for A = 0.80). Be careful when analyzing project totals for SPI, as the critical path is not taken directly into consideration. * Budget: The project is currently significantly over budget (CPI = 0.78) by 27.5% where CV / EV = $ over budget
Words: 482 - Pages: 2
Teradyne’s 45-year-history. It had set out to create an entirely new semiconductor test-system platform. The resulting Ultra Flex system, designed to be flexible enough to allow customers to test a full range of semiconductor devices, was critical to the success of Teradyne’s new competitive strategy. The Jaguar project had marked a culmination of sorts in Teradyne’s eight-year effort to improve its product development process. The Jaguar team had used a number of project management
Words: 457 - Pages: 2
•A lack of trust and respect has developed between the departments heads due to poor communication. •Decisions are being made based mainly on rather than performing formal research and analysis Conclusion The success of “Operation Optimize” is critical to the future success of AcuScan by directly impacting an increase in sales revenue and broadening the company’s customer base and marketing versatility. AcuScan must take immediate action to address concerns of both departments, and guide the project
Words: 747 - Pages: 3
F H 3 5 7 G I 2 3 4 G,H A- Determine the expected times and variances for each activity B- Construct a project network for this problem C- Determine the EST, EFT, LST, LFT and slack for each activity. Also determine the critical path and project completion time. D- What is the probability that the project will be finished in less than 57 days? E- What is the probability that the project will need at least 50 days? Activity | Early Start | Early Finish
Words: 1200 - Pages: 5
completion time. Show the critical path. What would happen if activity 6 were revised to take six weeks instead of one week? 8. Construct a Gantt chart for the project defined in question 7. 12. Assume that you have a project with seven activities labeled A-G (below). Derive the earliest completion time (or early finish – EF), latest completion time (or late finish – LF), and slack for each of the following tasks (begin at time = 0). Which tasks are on the critical path? Draw a Gantt chart
Words: 374 - Pages: 2
Jane Doe 02/10/2014 QAT1 309.3.2-01-06 A. See table 1.1 attachment B. 1. Expected time to complete: * a= the optimistic completion time estimate * b= the pessimistic completion time estimate * m= the most likely completion time estimate The activities mean completion time is: t= (a+4m+b)/6 * Task A. (2+12+4)/6=3 * Task B. (5+24+13)/6=7 * Task C. (3+16+8)/6=4.5 * Task D. (10+44+15)/6=11.5 * Task E. (4+20+6)/6=5 * Task F. (8+40+12)/6=10 * Task
Words: 727 - Pages: 3
CONTENT i DEDICATION ii ACKNOWLEDGEMENT iii INTRODUCTION 1 Project Overview 1 System Requirement – For Developer 2 System Requirement – For Server 3 USER MANUAL 4 System Requirement – For End User 4 Product Operating Guideline 5 CRITICAL EVALUATION REPORT 6 Product Evaluation 6 Project Evaluation 7 Personal Evaluation 8 CONCLUSION 9 REFERENCES 10 APPENDIX 11 Weekly Progress Report 11 Story Board 12 Gantt Chart 13 Design Project Accessories 14 LIST OF FIGURE
Words: 291 - Pages: 2
Estimation of Project Timeline and Completion Date We estimate that the project will have a start date of January 2, 2008 and will be completed on December 22, 2008. The duration of the project will be 254 days. Discussion of Critical path The critical path consists of the following activities: Market Analysis, Product Design, Product Design Selection and Detailed Product design, Test prototype, Finalized product design, Order production equipment, Install production equipment and celebrate
Words: 702 - Pages: 3