Free Essay

Civil Construction

In:

Submitted By df09a09b0
Words 2341
Pages 10
Civil Construction
Assignment 1.
29 October 2012
Michael McCormick
Index page………… 1. Project- South West Rail Link
Principal- Transport Projects Department NSW
Contractor- John Holland Pty Ltd

2. Introduction to the Project
The South West Rail Link includes a major upgrade of the Glenfield Station and interchange and a new twin track passenger rail line from Glenfield to Leppington via Edmondson Park. Transport for NSW is delivering the project on behalf of the NSW Government. John Holland has been appointed to design and Construct the project between Glenfield south and Leppington.
The project will provide: * A new rail line between the existing rail corridor at Glenfield and the new Train Stabling Facility at Rosmore including tracks, embankments, cuttings, bridges and culverts. * New railway stations at Edmondson Park and Leppington including commuter car parks.
The project civil scope involves the construction of: 1. 11.4 km of new rail line 2. There are seven underbridges to carry the rail line over the road 3. There are 5 over bridges to carry the rail line under the road. 4. 23 box culvert crossings 5. 2 stations 6. 1 stabling yard that holds 20 train sets (cars each) 7. 1 million cubic metres of cut fill earthworks 8. Retaining walls and soil nail walls to the cut areas 9. … cubic metres of concrete 10. …. Tonnes of reinforcing steel 11. An overhead viaduct 600m long at Cowpasture Rd.
The work force currently employed directly on site by John Holland is 210 be engineers, supervisor and direct workforce. There are approximately a further 800 workforce employed by the subcontractors carrying out the works. There were also some 200 designers, engineers and draughts people involved in the design work. 3. Works
In the following I have selected some of the work activities viewed on the construction site. Where possible I have described the plant and equipment involved in the works and described the work sequence.

Soil nailed walls
Soil nailed walls are constructed simultaneously with the earthworks cut operations. They are cheaper and faster to construct than a conventional retaining wall as they save on the amount of formwork, concrete and reduce the amount of fill and cut required for the conventional retaining wall. The soil nailed wall also works well in a confined space like a railway corridor.
The engineer stated that there were 5 separate teams of 12 men working at different soil nailed walls through the project.
Basically the sequence is as follows:- 1. The top of the wall is benched so that the capping beam can be formed and poured. There are conduits left in the capping beam to allow the holes to be drilled for the soil nails.
Photos of the capping beam 2. The back of the wall is then cut at a slope to the vertical bellow the capping beam so that the drilling machine can drill the first 2 rows of the soil nails to the depths shown on the drawings for that wall
Picture of the drilling machine and the excavated wall if I have one……? 3. The soil nails are then placed in the bored holes and grouted and left to cure for at least 7days. The grout needs to reach 67% of its design strength. The drainage cell and the galvanised mesh is then place on the wall with spacers.
Pictures of the wall with the mesh and bolts in place 4. The wall is then covered with a sprayed concrete layer to the correct depth then trimmed off
Pictures of the spraying operation 5. If the earthworks cut needs to be deeper than the cut is then made deeper and the soil nailed wall sequence above is repeated. The wall is extended deeper as the cut is excavated.
Plant and equipment * Formwork and reinforcing steel for the capping beam * Frana crane to place the formwork. * Excavators to cut the walls * Air compressors and spraying equipment for the concrete walls * Concrete agitator trucks * Utes for the transport of men and small materials
Pics of the plant?

Earthworks
The earthworks were very carefully planned. The engineers considered the quality of the soils to determine whether it could be used in select fill(under structures like retaining walls or abutments etc), general fill under the rail line or roads or whether it was unsuitable fill material in which case it was stockpiled for noise mounds etc.
The soils on the project were graded using the Californian Bearing Ratio or CBR to determine which soil could be used in which fill. A soil with a CBR of 8 or better could be used as select fill, a soil with a CBR of 5 could be used as general fill but soils less than CBR of 3 were used in large noise mounds. Sometimes soils were treated with lime and then compacted to get better CBR ratios.
The engineers always tried to balance the amount of cut and fill required so that there was not surplus. This becomes very difficult especially if the qualities of the soils are different form the early geotechnical soils assessment. The engineers were always checking the CBR of the soils to make sure that the soils had a high enough CBR but on site and lab testing. Pics of the stabling yard zoomed in a bit

-Cut and fill operations
Where the cut and fill has to only travel a short distance and the soils were clay or highly weathered rock then the cute was done with scrapers which could cut the soil out of the ground, then transport the soil to the fill area and place it in a layer. Sometimes the scrapers are assisted with dozers to push the scrapers when they were loading. On this project they used Caterpillar 633 scrapers and high track Caterpillar D8H dozers. Pics of scapers and dozers here
Where the cut and fill has to travel a longer distance or the soils were harder (soft rock) or the area was in a deeper cutting the soils/ rock were excavated with a tracked excavator. This was in turn transported with large 6 wheeled dump trucks to the fill site where the loads were dumped. The excavators used on this project were usually 40-80 tonne and the trucks were Volvo 740’s. They called them Moxy’s. Pics of excavators and moxy’s
The fill was delivered by the scrapers or the 6 wheeled dump trucks. The fill delivered by the scrapers could be levels out but the pad foot vibrating compactor which had a blade on the front of it or a dozer which levelled the fill and also track rolled it. If the fill was delivered by the 6 wheeled dump truck then the loads had to be levelled by the dozer. Then compaction was done by the pad foot compactor in layers. The placed fill sometimes had to be dried which was done with a grader to turn the soil and left to dry in the sun. Other time the fill had to be wetted down with a water truck, mixed then compacted again. These operations were controlled by a geotechnical engineer and to get the correct compactor required by the designers. The designers could specify different compactions which ion this project was95%, 98% or 100% mod ASSHO. Pics of compactor, water truck and grader
When the fill reached the correct finished or subgrade level the surface was trimmed of using a grader. The grader was controlled using a GPS and a laser to cut to the correct levels that were on the design drawings. On this project they used a 3D program called MX. Pic of grader
Plant and equipment
-Scraper- Cat 633 (30m3)
-Dozer Cat D8H
-Excavator various sizes, 40-80 tonne
-6 wheeled dump truck, Volvo 740
-Water tanker
-Pad foot vibrating compactor
-Grader, Cat 14 G
- Truck and trailer
Piling
Piling works were used to support structures throughout the project. Piles were used to support bridges, viaducts, light poles and the overhead wiring structures for the train catenary.
The piles varied in sizes from 600mm to 1200mm diameter. Most of the piles had to reach a particular class of rock (say class 3 shale) and then the pile had to be socketed a minimum into that rock (usually another 3.2m)
The drilling machine could use an auger to get to the rock. The auger was then changed to a circular core which cut a ring of rock out to form the pile. Once the hole reached the correct depth it was cleaned out with a cleaning bucket which had non return flaps on the bottom of it. Pics of the bucket and drilling rig
A reinforcement cage was then lowered into the pile an was held off the sides and bottom by spacers. The pile was then poured with concrete. They used a tremmie so that the concrete did not segregate. The pile was finished with a formed concrete cap which was poured with the hold down bolts for the steel structure that went on top. Pics of concrete truck, tremmie and the pile cap.
Plant and equipment
-truck mounted drilling rig with augers and rock cores
-concrete agitator trucks
-slid steer excavator to place reinforcement and move materials
Rock cutting
On the project there were sections of rock which had to be cut in order to allow the train line to maintain a minimum gradient change. The largest rock cutting was at cut 1 where the rail line had to also pass under the Hume Highway.
The rock in cut 1 required a cut of 12m into hard rock extending approximately 400m on the eastern side and 200m on the western side of the Hume Highway. The rock in the top levels was class 5-3 shale which could be seen to break out in slabs so that the excavators with rock breakers could make good progress. However the lower layers in the cut were a class 1 - 2 sandstone which was very hard and did not have many fractures and so required very heavy excavators and rock breakers. Very slow progress was made in this rock. At the time of viewing in October the rock breakers (four) had been there 4 moths and there was still 5 m further to excavate. Pic of the excavators rock breaking
The rock was excavated after the rock breaking, loaded into Volvo 740 dumpers and taken to the stockpile beside a crushing plant. The crushing plant after crushing the rock then graded and mixed the crushed rock so that it was suitable for road sub base course, rip pap at the culvert entrances and exits and construction roads. Pic of crusher?
As the rock was very hard the retaining walls that were originally designed for this area could be omitted. However the walls still had to be trimmed with rock saws to achieve the required profiles of the cut. The engineer said that the rock had to be weather tested in an accelerated test to make sure that it would not fret and meet the 100year design life. Pic of rock saw
The rail line extends under the Hume Highway via a tunnel. The tunnel roof was constructed by coring a series of 600 mm diameter tubes through the rock under the highway which were grout filled. It is intention to break out the rock with excavator and rock hammers and progressively support the roof with steel arches. This will be encased with concrete. The highway was checked every day to monitor any settlement. The engineer said that the rock drilling team would have known from their machinery whether there any settlement immediately. Pics drilling machinery of the drilling machines
Equipment
-80 tonne excavator with rock hammer
-excavator for loading dump trucks -6 wheeled dump truck, Volvo 740
-Water tanker
-Excavator with rock saw
- rock crushing plant
- rock coring machinery

Structures
There were structures that were also being constructed on this project. As they were not civil works they were not considered for this report.
However it was very interesting to see how well they organised operations. The engineer who showing me around the project explained the amount of planning and temporary design work required when building the structures.
Workplace Health and Safety
………………………..WHS……………….……
Induction
Safety signs
Radio procedure s and control through the whole site
No passing any plant unless the operator can see you
PPE
Fences, stairs, construction tape for path ways, give way to all plant, aberrance’s to the road rules strictly.
Pics of stairs and scaffolds and safety signs

Conclusion
The SWRL project was a very large infrastructure project that involved many engineering disciplines. This report focussed on some key civil activities but there were also many structures in the project.
There was much design work that was done before the works were started on site. There were many investigations that occurred such as the investigations on the geotechnical ground conditions, a study of hydrology to see where all the water flowed in a storm and even included identifying the trees and shrub that grew in the area so that the correct plants could be used. The engineers even did construction safety checks on their designs before they were approved.
The planning involved in organising each construction activity was very detailed and thorough. Particular attention was paid to the safety aspects and every activity was reviewed and signed off by senior engineers before the work was allowed to proceed.
Actually viewing the construction happening was very informative and assisted with understanding the lessons in class. The reality is that that our lessons in class give us the basics and when actually doing each construction activity takes a great deal of planning to actually be able to build safely.
At this point I would like to thank John Holland and particularly Tom Bentley- Site Engineer for their time and assistance.
References
-SWRL design plans….. repeat
Appendices and References * Drawings to indicate the extent of the line * Perspectives of the bridges and structures * Perspective of the ….. Station in the cut. * SWRL selected drawings

Similar Documents

Premium Essay

Essay On Civil Engineering

...Abstract- Being a Civil Engineering Student and specialization in infrastructure development Engineering Geology is very important. It is that branch of applied sciences which deals with the application for a safe, stable and economic design and construction of a civil engineering projects. It is rather a new field of applied sciences that has developed due to interaction between the civil engineering practice and geological sciences. Introduction- In today’s fastest growing world day by day infrastructure development of any country like India is very important for their growth and for a career as a civil engineer, grasp of fundamental of engineering geology is almost universally considered as essential as that of soil mechanics, strength of material or theory of structures. The present application of geological knowledge in planning, designing and construction of very big civil engineering projects is considered not only desirable but also absolutely essential. The scope of engineering is best studied with references to major activities of the profession of a civil engineer are construction, water resource development, town and regional planning. In all types of heavy construction jobs such as building, towers, tanks,...

Words: 713 - Pages: 3

Premium Essay

Cv Resume

...Vrushank Shah Post-Graduation in Construction & Project Management, CEPT University Bachelors of Technology (Hons.) in Civil-Construction, SBST, CEPT University Permanent Address: 12-B Sangita Society, Beside Ankur Complex, Ankur, Naranpura, Ahmedabad-380013. Email Address: vrushank.shah.cpm12@cept.ac.in ; vrushank5406@gmail.com ; Cell No. : 91-9924110902 PROFILE I have work experience of 32 months in execution and project management work in construction industry. I have keen knowledge of required software and tools of construction project management. My research paper "Challenges in Multi Project Management of Construction Company" has been approved and accepted for publication in the NICMAR-Journal of Construction Management. My objective is to work in challenging construction project, where I can use my experience and skills for advancement of the firm and enhance my skill sets. MAJOR INTEREST AREA * Advanced Construction Technology * Controlling and Monitoring - Project Management Techniques * Resource Optimization, Planning and Management - Construction Management Techniques * Building Information Modeling WORK EXPERIENCE (32 MONTHS) Duration | 2 months and 15 days - May '2013 to July '2013 | Company Name | Rohit Infraprojects Pvt. Ltd., Mumbai | Designation | Project Manager Trainee (Project Training of Post-Graduation CPM Course) | | | Duration | 4 months and 15 days - March '2012 to July '2012 | Company Name | HCP...

Words: 575 - Pages: 3

Premium Essay

Construction

...CONSTRUCTION In the fields of architecture and civil engineering, construction is a process that consists of the building or assembling of infrastructure. Far from being a single activity, large scale construction is a feat of human multitasking. Normally, the job is managed by a project manager, and supervised by a construction manager, design engineer, construction engineer or project architect. For the successful execution of a project, effective planning is essential. Involved with the design and execution of the infrastructure in question must consider the environmental impact of the job, the successful scheduling, budgeting, construction site safety, availability ofbuilding materials, logistics, inconvenience to the public caused by construction delays and bidding, etc. Types of construction projects In general, there are four types of construction: 1. Residential Building construction 2. Industrial construction 3. Commercial Building construction 4. Heavy Civil construction Each type of construction project requires a unique team to plan, design, construct and maintain the project. Building construction Building construction is the process of adding structure to real property. The vast majority of building construction jobs are small renovations, such as addition of a room, or renovation of a bathroom. Often, the owner of the property acts as laborer, paymaster, and design team for the entire project. However, all building construction projects include some...

Words: 3036 - Pages: 13

Premium Essay

M. Degree In Civil Engineering

...In the different realms of Engineering and technology, I think construction engineering is the powerful domain that can create the better world by harmonizing and shaping the natural and built environment. I see that the world is changing faster than ever before. Modern global megatrends shaking up the construction industry such as society and workforce, market and customers, sustainability and resilience, politics and regulation: an ever-increasing global population that continues to shift to urban areas, all of them need affordable housing as well as, transportation, social and utility infrastructure. To face such challenges, the construction industry is almost under a moral obligation to transform. The increasing breadth, complexity,...

Words: 816 - Pages: 4

Premium Essay

Project Management and Control

...Department of Computing, Engineering, and Technology The Life cycle (Environmental and Economic) Assessment of Complex Building Construction Project A Critical Reference Report Project Management and Control ENGM91 Assignment 1 Name: Manoj Rajendran Student ID: 149142740 1. Introduction Environmental issue has become economically important from the civil construction project. Especially in complex building project. As the construction field in need of resources like steel, cement, and power generation, it could definitely affect the eco-friendly system. Hence the sustainability of environmental and economic assessment should be conduct in entire life cycle of building construction project (Chan-joong Kim, 2015)The economic, social development and environmental protection are the major aspects of sustainability in building industry, which represents the impact of using raw material. Moreover the developed countries like Europe and USA has the findings that building operation contributes more to greenhouse gas emissions (B. De Meester, 2008). The usage of energy intensive elements is right from the start of the building which gives more importance to the development of environmental sustainability. But it is highly concern that...

Words: 3177 - Pages: 13

Premium Essay

Diversity in Construction Management

... | | Objective |Seeking a Construction Management position with a company that has goals for expansion and growth. | | Core Competencies & Traits |Client Relations ▪ Team Building ▪ Leadership ▪ Quality Assurance ▪ Safety & Health Detail Oriented ▪ Adaptable ▪ | | |Flexibility ▪ Self Starter ▪ Problem Solving Skills Communication Skills ▪ Contractor Management ▪ Commercial | | |Awareness Construction Knowledge ▪ Scheduling ▪ Coordination ▪ Progress Tracking ▪ Planning Technical Skills ▪ | | |Documentation ▪ Daily Reporting ▪ Dependable ▪ Positive Attitude Confidence ▪ Due Diligence ▪ Lessons Learned | ___________________________________________________________ |Experience |Mr. Braden has over 20 years of Industrial and Commercial Construction experience as, Project Construction Manager,| | |Superintendent & Quality Manager. Responsible for providing leadership and overseeing the entire Construction | | |project and phase of Site Development, including all civil construction functions. Experienced in all disciplines | | |of construction (civil, structural, architectural, electrical, mechanical, and plumbing), including but not limited| | ...

Words: 1168 - Pages: 5

Premium Essay

Report on Construction Manager

...CONSTRUCTION INDUSTRY Construction Industry is one of the most growing industries in the whole world. This industry is mainly an urban based one which is concerned with preparation as well as construction of real estate properties. The repairing of any existing building or making certain alterations in the same also comes under Construction Industry. This industry can be categorized into three major categories namely :- * Construction involving heavy and civil engineering * General construction * Constructions involving specialty trades Construction Industry is a booming industry and remains so with the continuation of the development process especially in the developing countries. With the process of development, the migration of people takes place from the rural to urban areas. This phenomenon is most significantly observed in the "Asian Tiger" countries, China and India. Thus, the Construction Industry is also on a rise in such countries. Construction is the process of constructing a building or infrastructure. Construction differs from manufacturing in that manufacturing typically involves mass production of similar items without a designated purchaser, while construction typically takes place on location for a known client. Some Professions of Construction Industry are * Construction Manager * Architect * Design Engineer * Plumber * Electrician * Cement Mason and Concrete Finisher * Carpenter * Sheet Metal Worker *...

Words: 2317 - Pages: 10

Free Essay

Financial Analysis

...India's economic and social development. If we are talking about a double digit India's GDP growth for next 10-15 years we have to invest in the infrastructure development to achieve and sustain this growth. India has the necessary human and natural resources for becoming world's leading economy but without infrastructure these assets cannot be adequately utilized. Last twenty years of our journey has been quite enriching for the company and for all of us. It has been a continuous process of learning and today we are comfortably placed among our peers with a diversified and substantial order book. We have grown multifold and have been able to sustain this growth because of the dedicated and committed efforts of the entire team. From a small construction company we have matured ourselves in a large and diversified infrastructure organization. We have shown stellar business and financial performance year-on-year and have forayed into different business segments of the infrastructure sector. Economic and Industry Overview Supported by strong fundamentals and the Central Government's proactive measures India has been the most resilient and efficient economy to come out of the economic crisis. India's GDP growth for 2009-10 is estimated at 7.2 per cent. With an assumption of sustainable good performance of the industry and services sectors, the latest RBI projection placed the real GDP growth at 8.0 per cent for the year 2010-11. According to the latest IMF projection, India will grow at...

Words: 4742 - Pages: 19

Premium Essay

Nova Award

...Purpose and Background The NOVA Award was created by the Construction Innovation Forum in 1989 to recognize and encourage advancement and improvement in all areas of the construction industry. The Construction Innovation Forum, founded in 1987 is an international, non-profit organization formed to recognize innovations in the industry that improve quality, efficiency and most importantly, cost. It defines innovation as having a positive, important effective on construction or service, improving quality and reducing time or cost. Innovation is not limited to any one area it includes design, fabrication, building, detailing, rehabilitation, contract administration, labor relations, management, training, procurement, maintenance, equipment, materials, concepts or methods (Learn More About CIF). The founding chairman, Dr. Robert I. Carr has a degree in Architectural Engineering and Civil Engineering and is a life member of the American Society of Civil Engineers. With this background he implemented both the NOVA Award and the Construction Innovation Forum as a response to the Construction Industry Cost Effectiveness survey conducted in the early 1980's by Business Roundtable. The survey determined that the construction industry was lacking in the areas of productivity, skilled workers, managing increasing cost, fragmentation and the area of research and development (Robert I. Carr). In 1985, Steve Allen of the Dept. of Economics and Business for North Carolina State University...

Words: 1281 - Pages: 6

Premium Essay

Neoliberalism

...Exercises 1. Surance Brokers CC one day orientation programme that Jack can use to effectively orientate the new secretary: * Manager or supervisor meets with the new employee to: * review the employee orientation process and discuss plans for the day/week * review the position description, job posting, and discuss performance expectations (expected outcomes for the position)  * review of hours of work, dress code, flexible work arrangements (if applicable)  * review security processes, including access cards, codes, keys  * review information on office hours, building opening and closing hours, after hour entry/exit process  * identify location of washrooms, lunchrooms, common areas, mail room,  library, stationary cupboard, etc. * identify fires exits, first aid kit, OH&S information board, OH&S department representative, first aid attendant  * review computer and telephone set-up, use and protocol  * provide staff directory  * discuss any pertinent office procedures (vacation coverage, calling in sick, office supplies, etc.)  * Introductions to employees in the work unit and division * Complete forms and receive benefit and pension information * Obtain Government ID * Submit personal information for the employee record in the HR information system, * Complete HR Information Form  * Complete Payroll Direct Deposit Enrollment Form  * Complete...

Words: 401 - Pages: 2

Premium Essay

Asia Pacific Aviation Competitive Challenges & Growth Dynamics

...International Conference on Economics, Social Science, Arts, Education and Management Engineering (ESSAEME 2015) Study on trade-off of time-cost-quality in construction project based on BIM XU Yongge 1, a, Wei Ya 1, b 1 Xi’an Univ.of arch.﹠Tech., Xi’an 710055, China; a 15829690177@163.com, b631931577@qq.com Keywords: Building information modeling; Construction project; Time-cost-quality trade-off optimization; Genetic algorithm. Abstract. With the development of BIM technology, BIM provides a new direction for the project management of three objectives. Based on the current situation of the project time cost-optimized mass balance studies, pointing out the implementation mechanism of achieving the trade-off of time-cost-quality in construction project based on BIM mainly oriented components of the BIM model based; the use of Structured Query Language query statistics data information needs combined bill of quantities calculation method for the specification, preliminary engineering scale generation; establishment of Project relations system model. In the process duration is subject, for the construction of uncertainty factors such as interest rates and prices, through the establishment of quality, cost and schedule function, the establishment of quality balanced schedule cost optimization model, using genetic algorithm model of the optimal solution are obtained. With BIM case finally proves the rationality of the model and the effectiveness of the...

Words: 2798 - Pages: 12

Premium Essay

American School Counselor Association (2014). Mindsets and Behaviors for Student Success: K-12 College- and Career-Readiness Standards for Every Student. Alexandria, Va: Author

...BGG Development, LLC – a Texas Limited Liability Company engaged in the development, capitalization, marketing and operations of senior housing facilities in Texas. BGG Development, LLC’s management has assessed the initial opportunity and believes the total development budget for the initial phase of this project will be approximately $54.1 million, but the project is expected to have three (3) phased stages developed over a 3-year period (if all operations are met with material success). Should BGG Development, LLC be successful in executing its business model, the expected result will be a near-term net profit pool of approximately $6.2 million and BGG Development, LLC will be seeking to acquire approximately $1.2 million in pre-construction phase capital financing to address this business opportunity. To these ends, the company is providing this proposal for the purposes of entertaining discussions with qualified institutions, businesses and accredited investors regarding the potential investment preferences. This document is not an offer to sell securities of any kind, nor does it constitute a guarantee or warranty as to future performance of any kind. This Document is For Discussion Purposes Only. Northeast Houston Senior Housing Project Development Financing Proposal Pre-Development Phase Funding Round Capital Funding Proposal Notifications This document contains proprietary intellectual property and information created by BGG Development, LLC. This propriety information...

Words: 5397 - Pages: 22

Premium Essay

Persasive Writting

...Concrete Installation Project Summary Concrete Installation LLC plans to become the leading provider of concrete formwork services in the area. This means always having the best and most efficient facilities, processes, and people. To achieve this, Concrete Installation is investing in many ways that will pay off in competitive advantages for its customers. The company's overall strategy will be based on a continuing improvement process of setting objectives, measuring results, and providing feedback to facilitate further growth and progress. Project Goals and Objectives 1- The company also plans to focus to a lesser extent on the residential and heavy construction industry, which is also very robust at the moment. 2- The company plans to rapidly develop marketing alliances with industry leaders and pursue new sales of its services to residential and commercial builders. The market strategy is to capitalize on Concrete Installation's alliances by securing city, county, and state and federal government contracts. 3- Concrete Installation plans to use a direct sales force, relationship selling, and subcontractors to reach its markets. These channels are most appropriate because of time to market, reduced capital requirements, and fast access to established distribution channels. Key Customers and 2 Stakeholders Concrete Installation plans to use a direct sales force, relationship selling, and subcontractors to reach its markets. These...

Words: 673 - Pages: 3

Premium Essay

Project Report on Construction

...and so I would like to acknowledge them as well. Overall all the above-mentioned people had a great role in my study. Their direct and indirect help indeed proved to be a great help. OM BUILDCON PVT. LTD. ------------------------------------------------- Company Profile HEAD OFFICE | : | 648, SEC. 16A, FARIDABAD, HARYANA | TELEPHONE | : | 0129-4070524 | FAX | : | 0129-4074648 | E-MAIL | : | ombuildconpltd@rediffmail.com | WEBSITE | : | www.ombuildcon.com | A BRIEF PROFILE | Name of the Firm | M/s Om Buildcon Pvt. Ltd. | Managing DirectorDirectorDirector | Mr. Raj Singh TewatiaMrs. Mukhi TewatiaMr. Sandeep Tewatia | Registered Office | F-7, 2nd Floor, East Of KailashDelhi-110065 | Main Activities | Civil Construction | Specialization | * Development of...

Words: 2691 - Pages: 11

Premium Essay

Moladi Housing Initiative

...[pic] PROJECT MANAGEMENT BUSINESS CASE: MOLADI HOUSING | NAME: | |KEFAYAT SAYED ALLY | |STUDENT NO: 206507344 | |WORD COUNT = 5129, EXCLUDING TABLES, | |BIBLIOGRAPHY & APPENDECIES | | | | | CONTENTS SECTION 1: 1.1. INTRODUCTION 3. SECTION 2: 2.1. BACKGROUND 3. SECTION 3: 3.1. PROJECT DESCRIPTION 4. 3.2. OBJECTIVES 5. 3.3. SCOPE 6. 3.4. VIABILITY 8. SECTION 4: 4.1 FINANCIAL COSTS AND FORECASTS 9. 4.1 STAGE 1 COSTING TABLE 10. 4.2 STAGE 2 COSTING TABLE 10. 4.3 STAGE 3 COSTING TABLE 12. SECTION 5: 5.1. INTERPRETATION OF FINANCIAL TABLES 13. SECTION 6: 6.1. CONCLUSION 13. 6.2. BIBLIOGRAPHY 15. 6.3 APPENDICIES 16-24. 1.1 INTRODUCTION This business case has been presented to provide a solution...

Words: 5643 - Pages: 23