Standardized Baseline Development Support
Alexandra Soezer MDG Carbon

Regional Training for Asia, Pacific and Eastern Europe, 2 September 2013

1

Outline

• Activities globally;
• Technical/financial support needs; • Support/funding; • Support challenges; • SBs and NAMAs;

2

Standardized Baseline support activities
Supporter IGES Sector Energy use in the rice mill sector Supply side energy efficiency Country/Region Cambodia Status Initial assessment successfully concluded Capacity development for incorporation of SB into NMMs or PoAs Road map study Concept stage Not yet started

IGES

Mongolia

ADB UNDP MDG Carbon Global Environment Center Foundation

Cook stoves Agricultural sector Not yet defined

Solomon Islands Asia-Pacific Not yet defined

UNDP LED

Grid Emission Factor

Uzbekistan

Initial assessment successfully concluded

3

Standardized Baseline support activities
Supporter ACAD/UNEP Riso Sector Grid Emission Factor for the Southern African Power Pool Country/Region Botswana, DRC, Lesotho, Mozambique, Namibia, South Africa, Swaziland, Zambia, Zimbabwe Uganda Status Approved

Green Resources

Charcoal (fuel switch, technology switch, methane destruction) Clinker production in the cement sector Positive List for electricity generation from landfill gas and methane destruction factor

Approved

Ethane Biofuels/Ethiopia UNFCCC/RCCs (Africa/LAC)

Ethiopia West- and EastAfrica/Caribbean and Latin America

Initial assessment QA on initial submissions/concept stage

4

Standardized Baseline support activities
Supporter KfW/UNFCCC RCC, Lomé Sector Replication of the charcoal SB (with methane avoidance component) WAPP GEF SB GEF SB Country/Region West Africa Status Scope is being determined

ACAD/UNEP Riso UNFCCC RCC Lomé /St. George's

West Africa Cape Verde, Guinea Bissau, Sao Tome and Principe + 16 countries in LAC West Africa Senegal

Feasibility study Templates for data collection has been sent to the CV authorities/concept stage Concept stage Data collection/surveys

UNFCCC RCC Lomé GIZ

Cook stoves Cook stoves

5

Standardized Baseline support activities
Supporter UNEP Riso Sector GEF Country/Region Nigeria Status Awaiting allocation of funding by the DNA Feasibility study/assessment finalized KfW funding approval pending Initial discussions Initial discussions

UNDP

Off-grid rural electrification Solar kits

SSA

KfW

Togo

Standard Bank GIZ

Low Pressure Solar Water Heating Institutional cook stoves

South Africa Uganda

6

Standardized Baseline support needs
Technical support needs:

• Capacity development for DNAs;
• Development of TORs, tenders; • Data collection, compilation, SB calculations, Monitoring;
Financial support needs:

• International and national experts, stakeholder meetings; • DOE assessment (assessment report); • Application of the SB/first pilots; • Monitoring;
7

UNFCCC funding for Assessment Report
Selection of DOE to prepare Assessment Report
• • • • • • Request for funding for AR form (F-CDM-PSB-RF); Copies of letters sent to at least 3 DOEs (by DNA or representative); Proof of communication with DOEs; Justification for the selection of one of the DOEs; Contact and payment details of the DOE; Max. fund 20,000 USD & 5,000 for additional Party/ies;

8

UNFCCC funding for Assessment Report
Agreement between DNA and Secretariat “Agreement for funding for preparation of assessment report for submission of standardized baseline” (F-CDM-PSB-FA) - amount & document submission by DNA Submission of AR and payment by UNFCCC:

• Assessment Report;

• DOE invoice to DNA;
• “Proposed SB submission form” (F-CDM-PSB);
9

SBs Support/Funding

UNDP MDG Carbon UNDP’s corporate framework for Carbon finance (funded by AusAID) 3 components: • Capacity development; • PoA support; • SB development; More information at: www.mdgcarbon.org or e-mail to: alexandra.soezer@undp.org

10

SBs Support/Funding

UNDP Low Emission Development Path (Uzbekistan) Objective: “Helping in transition to more sustainable energy use.”

Focus: • Assist in developing a low emission development strategy; • Mobilize resources for the strategy; • Road Map for the Development of the Biogas Market in Uzbekistan;

More information at: http://www.leds.uz/

11

SBs Support/Funding

Asia Development Bank’s Carbon Market Initiative Supplementary to the CMI is the Technical Support Facility: Focus: • Build the pipeline of clean energy projects eligible for CDM; • Enhance the technical knowledge of project developers; Activities: • Project identification; • Project development and CDM processing support; • Capacity development; • Project implementation and monitoring support; More information at: http://www.climatefinanceoptions.org/cfo/node/56
12

SBs Support/Funding

IGES – Institute for Global Environmental Strategies (Funded by Ministry of Environment, Japan) Focus: • Facilitate the introduction of market mechanisms; • Provide database and research reports; • Support institutional framework for NAMA crediting and bilateral schemes; • Propose CDM reform; More information at: http://www.iges.or.jp/en/

13

SBs Support/Funding

UNFCCC Regional Collaboration Centres (Togo, Uganda, Grenada, Colombia) Objective: “The RCCs are designed to help under-represented regions increase their attractiveness and potential for CDM, by build their capacity and reducing the risk for investors.” Activities: • Identification of CDM projects; • Assistance for PDD development; • Assistance during validation; More information at: http://cdm.unfccc.int/stakeholder/rcc/index.html
14

SBs Support/Funding

Global Environment Centre Foundation (GEC) (funded by the Ministry of Environment, Japan) GEC serves as the secretariat of the Feasibility Study (FS) Programme on Climate Change Mitigation Projects for the Ministry of Japan.

Activities: • Identify promising CDM/JO projects; • Provide information to project developers and policy makers; • Supports Japanese entities to undertake FS for mitigation projects;
More information at: http://gec.jp/main.nsf/en/-Contact

15

SBs Support/Funding

African Carbon Asset Development • • • Funded by BMU ICI; Implemented by UNEP; Embedded in Standard Bank;

Objective: “Developing local capacity, industries and market-driven solutions on a sustainable basis.” ACAD’s application guidelines and application form can be found here: http://www.acadfacility.org/apply.php

16

SBs Support/Funding

KfW Carbon Fund Objective: “Contributing to the future design of the carbon market with new instruments and concepts.” Activities: • Supports climate protection projects worldwide; • Contributes to innovative approaches to the development of carbon markets; • Facilitates the access of European enterprises to the use of emission credits; More information at: www.kfw.de

17

SBs Support/Funding

GIZ (Gesellschaft fuer Internationale Zusammenarbeit) (funded by Germany - BMU and BMZ) Objective: “GIZ’s support helps to improve the performance of public and private actors in their new roles and functions in the carbon market and facilitates their access to the market.” Activities: • Capacity Development for CDM/strategy studies/sector studies of GHG potential; • Feasibility studies for CDM projects (focus on PoAs); • Development of PDDs, support of validation process; • Facilitating the purchase of CERs; More information at: http://www.giz.de/Themen/en/28915.htm
18

SBs Support/Funding

World Bank’s Carbon Initiative for Development (Readiness Fund) Goal: “Generate lessons of value by enhancing existing and developing new carbon finance mechanisms for future carbon markets.” Activities: • Capacity Development in LDCs; • Support DNAs to develop SBs; • Development of new methodologies, proposals for simplified CDM rules; • Establishing "suppressed demand" accounting standards; More information at: https://wbcarbonfinance.org/Router.cfm?Page=CIDEV&ft=About
19

What can SB deliver to NAMAs

In order to track the achievements resulting from the NAMA intervention a SB can help to:
•Address to a certain extent issue on data quality (QA/QC guidelines); •Performance benchmark and additionality; •Transparency - Methods, Emission factors and Activity data; •Accuracy – Neither an over-estimate or underestimate; •Consistency – Same method, same data source; •Completeness – Sources, Sinks and Gas; •Comparability – Inter region and country;
20

What can SB deliver to NAMAs
Uganda NAMA study on sustainable charcoal: MRV objectives: • Clear goal for the intervention; • Impacts to measure the progress towards the goal; • Results which enable impacts; Emission-related component of the baseline established on basis of the SB for charcoal in Uganda (Ref. ASB0002; Perspectives 2011), other factors were included into the baseline in order to have a comprehensive and holistic NAMA. Read the full study here: http://www.undp.org/content/undp/en/home/librarypage/environmentenergy/mdg-carbon/NAMA.html
21

Thank you!
UNDP MDG Carbon at www.mdgcarbon.org alexandra.soezer@undp.org 22

Similar Documents

Free Essay

The United Nations Convention on the Law of the Sea

...UNCLOS Name Institution Affiliation Outline Introduction 3 History & Ratification 3 Effects of Non Ratification 4 Conclusion 5 References 6 Introduction The United Nations Convention on the Law of the Sea also referred to as (UNCLOS) has been in place for many years after its initial establishment. The UNCLOS convention has been amended overtime since it was established for many years. There are calls to revisit the whole convention as some aspects does not auger well with the current trends in the world. The Law of the Sea has caught the public attention due to certain activities such as fishing and the activities in the Arctic. There are arguments that with the continued shrinking of the polar ice cap, there countries that surround the Arctic Ocean have started positioning themselves to the anticipated biggest geographical brawls in the coming years. History & Ratification During the 17th century, the sea was governed by the concept that was known as the ‘freedoms of the seas. The regulation marked boundaries of the sea that countries should not go beyond in their activities. The distance marked was approximately three nautical miles. During the 20th century, many countries wanted this distance to be extended for economic purpose. The extraction of minerals and fishing were seen as very valuable activities that were boosting the country's wealth. In the year 1930 there was a conference that was held to debate the issues in The Hague but the discussion...

Words: 685 - Pages: 3

Free Essay

Bmc Best Practice

...White Paper November 2006 BMC® Best Practice Process Flows for Asset Management and ITIL Configuration Management Copyright 2006 BMC Software, Inc. All rights reserved. BMC, the BMC logo, all other BMC product or service names, BMC Software, the BMC Software logos, and all other BMC Software product or service names, are registered trademarks or trademarks of BMC Software, Inc. All other trademarks belong to their respective companies. BMC Software, Inc., considers information included in this documentation to be proprietary and confidential. Your use of this information is subject to the terms and conditions of the applicable end user license agreement or nondisclosure agreement for the product and the proprietary and restricted rights notices included in this documentation. Restricted Rights Legend U.S. Government Restricted Rights to Computer Software. UNPUBLISHED -- RIGHTS RESERVED UNDER THE COPYRIGHT LAWS OF THE UNITED STATES. Use, duplication, or disclosure of any data and computer software by the U.S. Government is subject to restrictions, as applicable, set forth in FAR Section 52.227-14, DFARS 252.227-7013, DFARS 252.227-7014, DFARS 252.227-7015, and DFARS 252.227-7025, as amended from time to time. Contractor/Manufacturer is BMC Software, Inc., 2101 CityWest Blvd., Houston, TX 77042-2827, USA. Any contract notices should be sent to this address. Contacting Us If you need technical support for this product, contact Customer Support by email at customer_support@bmc...

Words: 5623 - Pages: 23

Free Essay

Managerial Issues

...Managerial Issues Ernest Odel CMGT 445 05/12/2014 Mike Goyden Managerial Issues Citizens demand an assortment of fundamental municipal services like cleanliness, sanctuary, transportation, condition of energy and water, and etc., to be supplied by the city and or state that they reside in. Any region where one resides in requires a sustained infrastructure which necessitates the technical arrangements helping with the provision of services. “The infrastructure of a city, for example, includes not only components such as streets and power, telephone, water, and sewage lines, but also schools, retail stores, and law enforcement.” Similarly, indispensable personnel frequently choose organizations with superior amenities, management, and business processes. The goal of this paper is to list and discuss the managerial issues associated with managing an organization’s IS infrastructure. The topics that will be covered include the information related to configuration management and preventative maintenance, the industry standards in configuration management and control, the training approaches to allow for adaptive maintenance and confidence and the effect of globalization on managing and IS infrastructure. The infrastructure components of an information system consists of computer hardware software, communication and collaboration networks, databases, facilities, and human resources to sustain the network personnel’s decision making...

Words: 966 - Pages: 4

Free Essay

Managerial Issues

...Managerial Issues Ruth Walker July 14, 2014 CMGT/445 As every country relies on an operating basic level of organizational structure, corporations in service in a digital world are depending on information structure to maintain their commerce procedures and viable tactics. With rising momentum, business dealings are completed; similarly, with rising amounts of information to be examined, and housed in computer memory. Companies have to carefully arrange and direct their basic organization needs to obtain the maximum returns on their information systems investments. Management has issues with networks and structure of computer systems as they get more and more complicated. There are configuration issues so order and control like IT configuration administration are becoming ever more serious in order to keep hardware and software operating at the highest point. Management issues with IT configuration management is there must be continual methods in place that generate and preserve a current record of all the components of the basic organization. Skilled IT management thinks that IT configuration management by itself is not sufficient to avoid system breakdowns as well as additional technology issues. In order to be most victorious, IT configuration management must be part of a comprehensive in content IT service management plan that also contains modifications, events/occurrences, predicaments, and discharge administration. The ISO (International Standards Organization)...

Words: 1249 - Pages: 5

Free Essay

A Comprehensive Review of the Pnp-Maritime Group's Jurisdiction

...MARITIME GROUP JURISDICTION/AOR Maritime Jurisdiction – The PNP Maritime Group shall perform Maritime Law Enforcement and Internal Security Operations over Philippine territorial1, archipelagic2 and internal3 waters, rivers, ports4 of entry and exits. 1Territorial waters or a territorial sea as defined by the 1982 UNCLOS, is a belt of coastal waters extending at most 12 nautical miles (22.2 km; 13.8 mi) from the baseline (usually the mean low-water mark) of a coastal state. 2archipelagic waters are the waters enclosed by the archipelagic baselines as drawn in accordance with section 6; "conservation and management" includes all methods and measures which are: (a) Required to rebuild, restore or maintain, or which are useful in rebuilding, restoring or maintaining any (UNCLOS 1982). 3 internal waters according to the UNCLOS, includes the nation’s waters on the landward side of the baseline of a nation's territorial waters, except in archipelagic states. It includes waterways such as rivers and canals, and sometimes the water within small bays 4On major ports operated by the Philippine Ports Authority, MG should coordinate prior to the conduct of law enforcement activities therein. 5Coastal Area/Zone - is a band of dry land and adjacent ocean space (water and submerged land) in which terrestrial processes and uses directly affect oceanic processes and uses, and vice versa; its geographic extent may include areas within the landmark limit of one (1) kilometer from the shoreline...

Words: 440 - Pages: 2

Premium Essay

Nt1330 Unit 3 Assignment

...Configuration is a major implementation task in which business and functional settings in the ERP system are changed to make the “out of the box” software support the customer’s business needs. Configuration does not make any changes to the core software code, but instead updates tables with settings and entries specific to the customer’s business. Called configuration tables, these tables enable a company to tailor a particular aspect of the system to the way it chooses to do business. Project team members can use configuration tools to select alternatives through an easy to use GUI. These selections then behave like switches that tell the software to perform differently based on the values selected. For example, configuration may allow the company to specify: • Whether accounting for inventory should be based on LIFO or FIFO. • Whether the company wants to recognize revenue by geographical unit, product line, or distribution channel (or all three) • How many legal entities are reflected in the system • What the default currency will be. SAP has over 3,000 configuration tables and there are approximately 8,000 configuration decisions to make when implementing it. Navigating through them can be a formidable task. For example, when Dell Computers implemented SAP, the configurations alone took over a year to decide upon. As ERP software vendors attempt to gain market share, they continue to provide configuration options to address and increasing number of system requirements...

Words: 1017 - Pages: 5

Premium Essay

Schedule Management Plan

...1 Introduction 1.1 Scope The scope of this procedure is to describe the process of producing project plans for the Project. This includes both tender plans and project plans as well as plans for collection of modifications. Further the planning process includes: • Establishment and updating of project planning • Progress monitoring and reporting • Re-planning & Re-baselining 1.2 Objective The objectives for this procedure are to ensure: A common understanding of the planning process and the ability of the planning tool Flexibility, scalability and adaptability of the planning process in order to be able to satisfy both the Customer’s requirements and the internal needs • Standardize the planning process • Standardize planning inputs and outputs • That all project participants are aware of the planning requirements 2 Responsibility There are several responsible parts in the process of planning and measuring projects. 2.1 Project Manager The PM is responsible for the planning, monitoring, regular review and updates in order to establish the required work activities, budget, durations/dates and relationships between the activities of the overall plan. This particularly refers to the relationships between and across multiple CTR’s. PM is also responsible for ensuring that all project participants are familiar with the relevant part of the planning procedure. 2.2 CTR Lead The CTR Lead is responsible for the planning, monitoring, regular review and...

Words: 2131 - Pages: 9

Premium Essay

Concussionmangement

...The second goal is to expedite recovery to sports and normal activities and the third goal is to decrease the athletic program’s risk and accountability. To address the need to establish operative concussion management in sports, ten systematic steps and commitments will be discussed (Lovell, Giola 14). Saunders 2 The first step relates to pre-injury knowledge and preparation. This is a basic understanding of the injury, its evaluation and treatment. The second step addresses the pre-season baseline testing. Base Line testing by properly trained professionals should be conducted for neuropsychological function, postural stability/ balance and pre-injury symptoms to serve as comparison with post-injury evaluation. Obtaining baseline symptom reports from parents is recommended for young athletes (Reimann, Guskiewiez 280-297, Giola 14). The third step deals with...

Words: 1242 - Pages: 5

Free Essay

Self Employed

...Obtaining Baselines The Alterrain IT Department does little server monitoring because most if its resources have beenspent upgrading servers and network equipment as well responding to user needs. You recommendstarting the Computer Reliability initiative by developing a plan for gathering baseline performancedata on each server. Prepare a report or slide presentation for the IT director that describes the baselinedata you would gather.  Answer: Obtaining baseline data is a good starting point for achieving reliability goals. This can be a valuable source of information so that the company has a better way to track growth, prevent problems before they occur, and address problems after they occur. The types of baselines that Alterrain should look at developing include: Overall data about the following server elements: CPU performance  Disk performance  Memory performance  Hardware peripheral performance  I/O performance  System file caching   Number of users  Proportion of users that use specific resources Software application performance   Network performance at the servers  Performance information about slow, average, and peak usage periods  Performance information about new software after it is installed  Statistics regarding growth in use of the server in terms of increases in users, increases insoftware use and duration of the use, increases in the amount of time users are on the systems The company should consider keeping the baseline information...

Words: 1293 - Pages: 6

Free Essay

Sustainable Livelihood

...Sustainable livelihood livelihood is defined as the combination of all activities developed in relation to the resources that permit households to cover their needs in order to continue surviving and developing. Various elements at different levels interact within these systems: * The context of vulnerability may reflect geographical factors, climate, history, demographics, and the social and economic situation. This context defines the risks that the population faces. * The resources or assets to which the family or individuals have access, control or possess and with which they carry out productive processes, participate in the labour market or use for exchange with other families or individuals. These can be classified in the following manner: * Natural capital: made up of natural resources such as land, water and other biological resources. * Physical capital: includes the goods that have been created through productive processes, for example infrastructure (roads, bridges) and machinery. * Human capital: the ability to work and the labour capacity of a family unit or individual. * Financial capital: the household’s access to money, which may be through savings or credit. * Social capital: attitude towards reciprocity within the community, between households or individuals, based on the confidence formed through social links. * Policies, institutions and organisations influence the access to necessary livelihood resources and...

Words: 1006 - Pages: 5

Premium Essay

Best Practices

...Kristine Beck Assignment Week 1 From 1940 to present, project management has continuously advanced from line managers using a small set of processes that were considered nice to have to the formal assignment of one individual assigned as the project manager that utilized a formal methodology by which to manage the project. Often the term “best practices” is referenced within a defined methodology. Documenting Best Practices: Mature Project Management Processes Best practice refers to the optimal method recognized within a given industry or discipline to achieve a stated goal or objective. These practices are consistently predictable and proven to provide successful results and these practices are dynamic—evolving and maturing over time (Devine, 2013). The Business Dictionary defines a best practice as a, “method or technique that has consistently shown results superior to those achieved with other means, and that is used as a benchmark (Business Dictionary, n.d.).” A more simple definition is that a best practice is a method or technique that has consistently shown results superior to those achieved with other means, and that is used as a benchmark. In addition, a "best" practice can evolve to become better as improvements are discovered. Best practice is considered by some as a business buzzword, used to describe the process of developing and following a standard way of doing things that multiple organizations can use. Organizations that have had constant success have adapted...

Words: 1854 - Pages: 8

Premium Essay

Warehouse Kpis by Segment (Sharing)

...Focused Metrics Tom Vander Weide G-3 Enterprises and Tom Patterson Saddle Creek Corporation Saddle Creek Corporation Saddle Creek is a 3rd Party Logistics Services Company Service offering includes warehousing, transportation, and packaging/value adding services G-3 Enterprises Manufacturing, transportation, warehousing (beverage packaging components & logistics services) Network of 8 Regional Distribution Centers (RDC’s) – 4PL Operating over 8 million sq. ft. Rail deployment – Truck fulfillment 20+ facilities in 6 states Six 3PL operators 1,200 associates plus flex staff Variety of business systems – EDI Organizational structure and processes Relationship of Saddle Creek and G-3 Enterprises Saddle Creek began working with G-3 in 1997 Operate (3) RDC’s – DFW, ATL, FLA Warehouse, transportation & value-added 15MM cases annually throughput Metrics Program (KPIs) developed in 1999 Goals of this session What makes KPIs/Metrics Programs effective from Customer and Provider perspective? Case Study – Understanding the G-3 Metrics from both perspectives Determining if your KPIs are focused and standardized Distinguishing Metrics & KPIs G-3 Supply Chain Metrics Perfect Order Product Availability Inventory DOS Product Quality G-3 RDC KPIs Order Accuracy Inbound Timing Inventory Accuracy SCC Operation Metrics Damage/Hold Metrics/KPIs from the 3PL perspective What is an effective Metrics Program...

Words: 1027 - Pages: 5

Free Essay

Healthcare Leadership

...Learning Activities from Chapter 1 Master in health information management Healthcare information leadership Millennia Atlantic University Mariana Viloria 1. Differences between micro and macro perspective of healthcare. MACRO-PERSPECTIVE: Macro perspective is a form of analysis which focuses on the structure of society and provides a way of seeing society as a unified whole. In this macro perspective minimal attention is given to the individual or the subjectivity of actors - the structures of society are thought to be primary and responsible for shaping the individual. MICRO- PERSPECTIVE: A micro perspective focuses on the individual level, while a macro perspective focuses more broadly on society. Ethics is a major concern in the health care field. Health care professionals must ensure that they are benefitting patients and meeting ethical and moral guidelines in the provision of care. There are two types of ethical issues facing the health care community: micro issues and macro issues. Micro issues cover issues that arise on a daily basis, and they involve such factors as technological change and dealing with a diverse population. Macro issues concern the allocation, use, and management of health care resources. Macro issues are of major importance as the amount of resources being consumed by health care continues to rise. At the macro level there is a political issue, allegedly somewhere between 25 and 50 million persons who are "uninsured," by which the...

Words: 1455 - Pages: 6

Premium Essay

Six Sigma Benefits

...MANAGEMENT AND SCIENCE UNIVERSITY Usamah Hj Zaid usamah@asetsb.com.my SCHOOL OF GRADUATE STUDIES MANAGEMENT AND SCIENCE UNIVERSITY, SHAH ALAM INDIVIDUAL ASSIGNMENT Name Student ID Date Of Birth Contact Number Email Address House Address : Usamah Bin Zaid :012014050841 : 23 Aug 1983 : 019-602 2006 : usamah@asetsb.com.my : Lot 10, Jalan SP 6 Sri Petaling, 57000, KL Occupation Employer : Business Executive : Alam Sekitar EcoTechnology Sdn Bhd Usamah Bin Zaid Total Quality Management 1|Page SCHOOL OF GRADUATE STUDIES TABLE OF CONTENT MANAGEMENT AND SCIENCE UNIVERSITY, SHAH ALAM 1.0 Brief Introduction to selected organisation…………………………………..………….3 2.0 Comparing and contrasting the QMT used in the selected organisation…………….4 3.0 Analysis of findings……………………………………………………………………....8 4.0 Recommendations on quality management and conclusion…….……………….........8 Usamah Bin Zaid Total Quality Management 2|Page SCHOOL OF GRADUATE STUDIES MANAGEMENT AND SCIENCE UNIVERSITY, SHAH ALAM Brief Introduction to selected organisations: Panasonic Corporation formerly known as Matsushita Electric Industrial Co., Ltd. is a Japanese multinational electronics corporation headquartered in Kadoma, Osaka, Japan. The company was founded in 1918, and has grown to become one of the largest Japanese electronics producers alongside Sony, Hitachi, Toshiba and Canon Inc. In addition to electronics, it offers non-electronic products and services such...

Words: 2361 - Pages: 10

Premium Essay

Program Management

...1. Prepare opening comments that give the class an overview of project management. To understand what project management is we must first define what a project is. A project is a structured coordinated series of event, which result in a final deliverable. The deliverable in questions can be service oriented or produce a product to be delivered. A defined project will typically have a predetermined start and end date for the tasks within the project and the project itself. Additionally a project will normally be established to complete one goal that multiple tasks associated with it. A project does not have size limitations when it comes to resources, building a playground or building a skyscraper are both considered projects. The limitation of the project is associated with the limitation of the project triangle, cost, scope and time. The actions of managing the previously referenced cost, scope and money are where our overview of project management is provided. Project Management is the framework and process that is followed to meet the overall objectives through the tasks associated with the deliverables. Through the process of Project Management the resources needed to complete the objective is managed through the concept of the project triangle of cost, scope and time. The success of the project is contingent on the how well the project manager manages and balances the project triangle. All project contain the same framework to be completed by the project manager...

Words: 1468 - Pages: 6